Candidate Congestion Management Projects for FY 2014/15 & 2015/16Â FDOT Work Program FPN: 4125301 Priority
Project
Description
1
SR 544 at SR 17
SR 544 approach east of SR 17. Addition of EB thru lane east leg of intersection; extend WB left turn lane; sidewalk; and install a new mast arm traffic signal system.
2
Interstate 4 @ County Line Road Interchange
CST additional EB right-turn lane at the EB Ramp/County Line Rd intersection, b.) a second SB left-turn lane at the County Line/South Frontage intersection with a second receiving lane on South Frontage Rd, c.) signalization of the County Line/EB Ramp intersection and d.) signalization of the South Frontage/County Line Rd intersection. CMS funds will match a $1 million grant through the State Office of Trade, Tourism and Economic Development (OTTED) in FY 2012/13.
Type
Year
Cost
Intersection
FY 2014/15
$1,000,000
Intersection
FY 2012/13
$400,000
Intersection Total Cypress Gardens Blvd Olive St Pathway CR 655 (Rifle Range Road)
Complete sidewalk gaps and transit stop connections and enhance pedestrian crossings with pedestrian refuges at key intersections. 4-5 ft. wide bike lane on both sides of road from Wabash to Central. Project intended to be coordinated with programmed resurfacing project to maximize fiscal efficiencies. Construction of Sidewalk along east side of CR 655 (Rifle range Rd) in Wahneta between 10th St E and CR 559 (Bomber Rd).
1
Park-n-Ride Bus pull-off
2
PCTS/WHAT
Intown Bypass - Construct 12 ft. wide x 117 ft. long bus bay with 15 ft. sidewalk extending from bus bay to bridge abutment and 6 ft. wide sidewalk from bus bay to Main St. Bus Shelters: US 27 @ Burger King/Shopping Ctr. (H.C); US 92 @ Berkley/Neptune x2; and US 92 @ Redwood Apts. (Lk. Alfred).
1 2 3
Bike/Ped
FY 2014/15
$600,000
Bike/Ped
FY 2014/15
$411,000
Bike/Ped
FY 2015/16
$125,000
Bike/Ped Total
1 2 3 4
E Lake Howard Trail & Trailhead New Jersey Ave Pathway Bella Vista Pathway Ft. Fraser Trail Extension
8 ft. wide trail/sidewalk along Lake Howard from Ave B NW to Ave D SW, include upgrades to transit stops and connecting sidewalks, lighting, and conversion of old boat ramp to trail head w/parking. Remove existing sidewalk on west side of street and install 10 ft. wide asphalt pathway (narrowing where needed) from Edgewood to S Crystal Lake Dr. 10ft wide pathway on south side of street from MLK Jr. Ave to US 98 and 8 ft. pathway from US 98 to W Lake Parker. Includes landscaping and moving utilities underground. PD&E study to evaluate alternatives and feasibility of trail crossings at the Polk Parkway to allow the trail to be extended north to Lakeland.
Adopted: June 13, 2013 Amended: October 10, 2013
3
$1,136,000
Transit
FY 2014/15
$87,000
Transit
FY 2014/15
$110,000
Transit Total
$197,000
Trail
FY 2014/15
$600,000
Trail
FY 2015/16
$405,000
Trail
FY 2015/16
$440,000
Trail
FY 2015/16
$500,000
Trail Total
Adopted
$1,400,000
$1,945,000
June 7, 2012