Procedures of Purchase - Knockdown & Rebuild

Page 1

BUILDING

WITH US

NEW HOME BUILD PROCESS

KNOCK DOWN & REBUILD

At Plantation Homes, we believe in being clear and candid on the process ahead of you, and this guide will step you through every stage of the entire building process - from the first steps to the finishing touches on your new home, and beyond.

BUILDING A NEW HOME IS EASIER AND MORE ENJOYABLE WHEN YOU KNOW WHAT TO EXPECT

KNOCK DOWN AND REBUILD DEMOLITION INFORMATION

Love your location but need to upgrade your home? Make the smart move. Knock down your old home and rebuild a new home with Plantation Homes.

Congratulations on making the smart move to knock down and rebuild your new home with Plantation Homes.

We’ll take you through the step by step process which outlines the specific requirements you need to meet when demolishing your current home. Your designated Project Planner will be your main point of contact throughout this process.

How to prepare for a knock down rebuild project

STEP 1. RESEARCH AND PREPARATION

- Speak to your Council about your intention to demolish your home and find out relevant details about your land.

- When you speak to your Council, try to find out as much information as you can as this will help you to foresee potential issues. In particular, try to determine when sewer lines were installed in your area – this can flag potential future issues such as hidden items in the earth, septic tanks, wells, pools, pipes, etc.

- Find a demolition company and organise for them to obtain approval for the demolition.

- Arrange for the power and gas to be disconnected. Your utility company will need time to process your request so organise this in advance.

Important: We suggest that you start the process of Steps 1 and 2 once you’ve signed your Sales Quote.

1

STEP 2. ASSESSING YOUR LAND –ONSITE CONNECTIONS AND CONSIDERATIONS

- When your demolition company disconnects your sewer connection, please advise them that they must cap the sewer off at the main sewer connection point and in accordance with local authority guidelines. The demolition company can organise the Seal off Application Form and On Site Council inspection. Please note: A Form 4 will not be accepted.

Power connections

- If your current site has overhead power supply, then the setback of the house, location of the power supply and the height of your home will need to be considered to determine the new power connection. These factors will determine if you will need a temporary or permanent power pole to the front of your property.

- Your current and proposed power supply will need to be confirmed prior to demolition of your existing home. The supply availability to the front of the property will also need to be assessed, as conducted by a licensed electrician who will submit a Supply Availability request to Energex. If an upgrade is required, this process may take between 4 weeks to 6 months with application costs involved.

- Important: Whether your power connection is underground or overhead, it is important to ensure all power is abolished by Energex prior to demolition.

Identification survey

- As most knock down rebuild projects are in older areas where survey pegs are no longer present, you will require an Identification Survey to reinstate the pegs and provide a plan. You can organise this yourself or Plantation Homes can organise this at a cost.

- It’s important to wait until the house has been removed and the demolition company are finished on site before organising your Identification Survey in case any pegs are accidently disturbed during house removal.

Additional site requirements

- We require an Asbestos Clearance Certificate for all knock down rebuild projects. Please speak with your demolition company to obtain this.

- As most knock down rebuild projects have older services and infrastructure, you may require a CCTV report on your sewer or stormwater line depending on the age of proximity to your home. This is to ensure we capture if there is any damage to the infrastructure prior to commencing on site. This will be confirmed at Tender Stage.

- As some knock down rebuild projects are in built up areas or near parks/schools/ public areas, you may require a traffic control permit during construction. This will be confirmed at Tender Stage.

Important: We suggest that you start the process of Steps 1 and 2 once you’ve signed your Sales Quote.

2
Date Initials

STAGE ONE

LET’S CHAT ABOUT YOUR NEW HOME PROJECT

Take the opportunity to chat one-on-one with a Plantation Homes New Home Consultant. They will assist you with choosing a home design and will take you on a personalised walk through our display homes to assist with the preparation and presentation of your sales quotation.

SECURE YOUR QUOTE

We will carry out pre-deposit property inspections and checks before confirming your knock down rebuild project can go ahead. From there, an initial deposit is required to secure the current listed base house price and promotional offer (if applicable). Prior to paying your first deposit amount, your New Home Consultant will provide you with paperwork outlining the T+C’s of the deposit. You will be required to sign and return at the time of deposit payment.

• The initial deposit for a knock down rebuild is $2,500

Upon receipt of the initial deposit a soil report and contour survey are ordered. The deposit will be refundable for 30 days only (if no money is spent) and then non-refundable after that time. If required, the deposit will be used to cover Plantation Homes’ external and internal expenses to get your new home project documentation ready. In the case that any money is required to be spent in this time, you may be eligible for a partial refund only.

We will do two soil and survey reports. One predemolition and one post-demolition.

If your home is located in a Flood affected area, you must ensure the Site Specific Flood Study is completed and assessed by Plantation Homes prior to accepting your build project.

BE INSPIRED

Your New Home Consultant will book you in for your Inspiration Session, held virtually or in our Plantation Design Studio located in our Springwood head office, where you will discover how the colour selection appointment and process works.

CONFIRMING YOUR BUILD

Your New Home Consultant will confirm and review your land information and applicable site requirements, as well as finalise any plan or design changes and pricing queries. Please ensure all structural changes are finalised with your New Home Consultant during this appointment and your façade has been selected.

3
Date Initials
Now that you’ve considered everything you need to for a knock down rebuild project, here’s what the process will look like.

STAGE TWO

FINALISING YOUR PAPERWORK

The next appointment is to complete your sales paperwork.

Once complete, your paperwork will be submitted for review and acceptance. A Project Planner is appointed, and you will be booked in for your colour selection and tender appointment.

If you have titled land you will be booked in to the next available appointments when your Project Planner reaches out to introduce themselves.

If you have untitled land you will be booked in to a colour and tender appointment that aligns with your land title date to ensure that we have the neccessary land information available to complete your plans and pricing.

4
Date Initials

STAGE THREE

COLOUR YOUR VISION

Whether you know exactly what you want for your interior style or are yet to discover it, you’ll have everything at your fingertips at your Colour Selection Appointment at our Plantation Design Studio, located at our Springwood head office. You will have a professional Interior Design Stylist to assist you during your appointment. Allow approximately 3-4 hours for single storey homes and approximately 6 hours for double storey homes.

Appointments are available Monday to Friday only. You will also be provided with some preliminary information to help you to prepare for your Electrical Appointment.

For current Plantation Homes Design Studio opening hours please visit plantationhomes.com.au/plantation-design-studio

5
Date Initials

STAGE FOUR

TENDER APPOINTMENT

This is when all of your planning, information, quotes and payments come together in one place for your review and final sign off.

Your Tender incorporates all of your selections so far including your façade choice, catalogue options, variations, colour selection upgrades and site costs. You will also be presented with your preliminary drawings which include your site plan, floor plan and external elevations.

There are no further changes permitted after your Tender is signed.

Appointments are available Monday to Friday, taking approximately 4 hours for a single storey and a full day for double storey homes.

TENDER ACCEPTANCE AND SECOND DEPOSIT

Once you sign and accept your Tender, a further non-refundable payment of $1,500 is required in order to prepare your final contract documentation, which will include a set of drawings*. Please note: if council relaxation or town planning application are required, an additional deposit of up to $2,000 is required upon acceptance of tender.

COUNCIL RELAXATIONS AND TOWN PLANNING

Once you have accepted and signed your tender we can apply for all relevant council relaxations or town planning, if required.

DEMOLITION TIME

Plantation Homes will require you to remove your house prior to signing your building contract. We suggest organising the preparation and approvals with your demolition company once you’ve signed your Sales Quotation. Then once you have accepted and signed your Tender Document, you can proceed with removing your home if you haven’t done so already.

POST DEMOLITION

- Once you have confirmed the house is removed, please advise your Project Planner that the following is completed:

• Confirmation of clear site including removal of any debris

• Boundary pegs reinstated and an Identification Survey

• Asbestos Clearance Certificate

• If a CCTV report is required, this will be conducted – approximately 2 weeks

- Once the CCTV report is required (if required), an additional soil test, contour survey & site inspection can be carried out – approximately 2 weeks

- Once the results are received, our Project Planner can schedule your Contract Appointment and drafting and estimating will review these results in time for your Contract.

For further information on your specific timeframes for your project, please speak with your New Home Consultant or your Project Planner.

6
*Payment of the non-refundable deposit does not amount to a licence fee for the drawings. In no circumstances does Plantation Homes license its plan. All design sketches and drawings of your new home are subject to copyright and only Plantation Homes can construct a home in accordance with them. Date Initials

STAGE FIVE

ELECTRICAL APPOINTMENT

While you remove your home, your Project Planner will book you in for your Electrical Appointment.

This appointment is held in our Plantation Design Studio and is your opportunity to sit with our specialised Electrical Consultant to add additional lights, light fittings, security systems, fibre optic wiring, datapoints, home theatre provisions and other such items.

Between electrical and contract appointments we will be conducting second soil, survey and site inspections, working to finalise engineering and managing any outstanding changes from tender.

STAGE SIX

SIGNING ON YOUR CONTRACT

Your Contract documents have now been prepared including the industry standard HIA New Home Contract, finalised Tender, and contract plans, which are now ready for you to sign.

Upon signing your building contract, you will be required to pay the balance of 5% of your total contract value minus the initial deposits you have already paid, as set out in the Plantation Homes progress payment schedule.

STAGE SEVEN

OBTAINING APPROVALS

Now that the Building Contract is signed and your first progress payment made, we can submit the application of your full building approval. Please note building approval can take 4-8 weeks.

Now is also the time to organise your formal finance approval through your lender if required.

PREPARING FOR SITE START

Whilst we wait for the building and finance approvals, we will finalise your construction drawings and complete the final allocations on your file.

You can commence preparing for site start by providing Plantation Homes with the following:

• Finance approval letter from your lender

• Confirmation of land ownership via a rates notice or settlement statement

• A clear site including removal of debris and/or trees where required

• Any additional documents requested from your Customer Service Representative

SUMMARY OF PROGRESS PAYMENTS

We require progress payments as per the Plantation Homes progress payment schedule. There are 6 payments, totalling 100%.

Deposit – 5% (minus the initial deposits you have already paid)

Base – 15%

Frame – 20%

Enclosed – 25%

Fix – 20%

Completion – 15% (plus any variation costs)

7
Date Initials

STAGE EIGHT

CONSTRUCTION

Now is the time for Plantation Homes’ construction team to take the lead and do what we do best.

The next section will define the main stages of construction for you, and outlines some of the things which may take place during each stage.

BASE STAGE

Your block of land will be prepared and ready to build on, with temporary fencing installed, site excavation, and underground connections laid. Base stage is complete once the concrete slab is poured.

Upon completion of base stage, a 15% progress payment is due.

FRAME STAGE

This is when your dream home really starts to come to life. All walls are marked out in accordance with your final drawings and construction of walls, windows and door frames, and roof trusses begin.

Frame stage is complete once the wall and roof frames are fixed and all tie downs and bracing are complete.

Upon completion of frame stage, a 20% progress payment is due.

ENCLOSED STAGE

This is a significant milestone as it’s when we’re able to effectively ‘lock up’ your home. Brickwork, wall cladding and roofing are all installed. Temporary external doors may be hung and fixed into position in order to ensure the security of your home.

Upon completion of enclosed stage, a 25% progress payment is due.

FIXING STAGE

This is where we begin fixing everything into position. We will complete all internal plaster architraves and skirts, and cabinets and cupboards (excluding shelves) to your kitchen. Upon completion of fixing stage, a 20% progress payment is due.

FIT OFF STAGE

The focus shifts to the inside of your home during this stage, and you will see your colour selections come to life. Whilst we paint your home, we will install tiles, benchtops, shower screens, mirrors and door furniture. We will fit off all plumbing and electrical connections.

PRACTICAL COMPLETION INSPECTION (PCI) STAGE

Two weeks ahead of anticipated completion of your home, your Project Planner will contact you to book in your New Home Presentation. On this day, you will meet with a Plantation Homes representative who will present your new home to you demonstrating its features and functions. At the time of your New Home Presentation you will be able to settle on site and receive your keys should you have your final payment ready.

Upon completion of your home, the final progress payment of 15% is due, along with any additional variations ordered.

8
Date Initials
Congratulations! Your brand new Plantation home is complete, and ready for you to move in.

STAGE NINE AFTERCARE

Now that you have settled into your brand new home, it is time to commence with Plantation Homes’ industry leading aftercare program. We have a commitment to quality at every step of your new home build, which is supported by a 12 month maintenance period. We understand that in Queensland your home will experience a vast variety of effects as four seasons come and go, which is why we allow your home to settle over 12 months. A team member from our Quality Assurance team will contact you at approximately eleven months after settlement to book in a suitable time to assess your home.

Should you wish to have your 12 month maintenance inspection brought forward, please contact our team by email or phone. Beauty meets quality craftsmanship at Plantation Homes, which is why we confidently and proudly stand by our work, even after you have moved in. Each and every home that we build also comes with a 50 year structural guarantee*, so that your home is protected from structural defects that may arise. This demonstrates our commitment to giving you peace of mind, knowing that you have made the right decision in choosing to build with Plantation Homes.

9
Date Initials *Exclusions apply. For full terms and conditions please visit www.plantationhomes.com.au/building-with-us. All photos and illustrations are for illustrative purposes only and should be used as a guide only.

EVERYDAY /ADVANTAGE /

UPFRONT PRICING

We don’t hide our prices

CUSTOMISE YOUR HOME

We offer lots of ways to customise our house designs which are all ready to quote

BETTER

INCLUSIONS

More of what you want included at no extra cost

PERSONALISE YOUR HOME

We offer lots of choice at no extra cost and include an interior designer whois not paid commissions to upgrade

BUILD WITH CONFIDENCE

We are part of a 330 year old company with a big rainy day reserve, so we’ll complete your home no matter what

PEACE OF MIND

We inspect your home after it’s experienced 4 seasons and give you a 50 year structural guarantee

10

CUSTOMER

Below are the actions and touch points that you will experience throughout your building journey

Visit display centre and meet your sales team to discuss your desired home design and provide a copy of your land documents, including registered survey plan and any additional land information

Attend New Home Appointment and New Home Walkthrough at display centre to confirm façade and floorplan options

Secure your sales quotation pricing and promotion with your initial deposit and receive your My Home Planner.

Attend Inspiration Session at Plantation Design Studio prepare all required work and paperwork to comply with knock down rebuild guidelines

PLANTATION HOMES

Below are the actions that Plantation Homes will take to complete your building journey

Complete pre-deposit site inspection

Complete complementary siting of home design on land and prepare base quote

Book Plantation Design Studio Inspiration Session

Order soil test, contour survey (if available) and preliminary council information.

Meet with your new home sales consultant to finalise and sign off on paperwork including site plan, sales quotation and floor plan.

Your Project Planner will now be your main point of contact as they facilitate your build file in head office

Submit finalised sales paperwork to our Springwood head office

Schedule Colour Selection appointment and Tender appointment

Attend Colour Selection appointment

Attend Tender appointment and sign off on Tender

A second non-refundable deposit is due of $1,500 Organise demolition at site

Apply for all relevant council relaxations or town planning

Second soil test, survey and site inspection carried out

Schedule Contract appointment and Electrical appointment and begin preparation of Contract documents, including complete and final plans and pricing

Attend Electrical Selection appointment

Contract appointment to approve and sign your new home contract and pay 5% of contract total (minus deposits already paid)

Prepare plans for the submission of your building application

Provide confirmation of land settlement to Project Planner

Provide unconditional finance approval document to Project Planner

Provide written confirmation from your lender to your Project Planner that funds are ready to be released

Introduction to your Construction Supervisor who will facilitate your new home build

Congratulations! Your new home is now complete

Submit application for building permit

Order materials ready for construction

Construction begins on your new Plantation home Progress payments are required as outlined in stage 8 on page 8

Commencement of 12 month maintenance period

PLAN 1 SALES 2 DESIGN 3 TENDER 4 ELECTRICAL 5 FINANCE 7 CONTRACT 6 BUILD 8 HOME 9
Date Initials

PLANTATION HOMES

3354 Pacific Highway Springwood QLD 4127

T (07) 3290 8888 plantationhomes.com.au

PLANTATION DESIGN STUDIO

Ground Floor 3354 Pacific Highway Springwood QLD 4127

T (07) 3290 8888 plantationhomes.com.au/plantation-design-studio

include upgrade
and
not offered by
Homes. Copyright
Properties (QLD) Pty Ltd trading as Plantation
All rights reserved. QBCC 73955 3478_Printed May 2023
This is an overview to building your Plantation home and should be used as a guide only. Photography and illustrations are for illustrative purposes only as they will
items and may show furniture, screens, landscaping and structures, pools, pergolas, decking, driveway, fencing
decorative finishes
Plantation
Henley
Homes.