Exhibit E - Interconnection Reports

Page 1


Interconnection Reports

AF1-122 Feasibility Study Report

1 Introduction

This Feasibility Study has been prepared in accordance with the PJM Open Access Transmission Tariff, 36.2, as well as the Feasibility Study Agreement between the Interconnection Customer (IC), and PJM Interconnection, LLC (PJM), Transmission Provider (TP). The Interconnected Transmission Owner (ITO) is American Transmission Systems Incorporated (ATSI).

2 Preface

The intent of the feasibility study is to determine a plan, with ballpark cost and construction time estimates, to connect the subject generation to the PJM network at a location specified by the Interconnection Customer. The Interconnection Customer may request the interconnection of generation as a capacity resource or as an energy-only resource. As a requirement for interconnection, the Interconnection Customer may be responsible for the cost of constructing: (1) Direct Connections, which are new facilities and/or facilities upgrades needed to connect the generator to the PJM network, and (2) Network Upgrades, which are facility additions, or upgrades to existing facilities, that are needed to maintain the reliability of the PJM system.

In some instances a generator interconnection may not be responsible for 100% of the identified network upgrade cost because other transmission network uses, e.g. another generation interconnection, may also contribute to the need for the same network reinforcement. Cost allocation rules for network upgrades can be found in PJM Manual 14A, Attachment B. The possibility of sharing the reinforcement costs with other projects may be identified in the feasibility study, but the actual allocation will be deferred until the impact study is performed.

The Interconnection Customer seeking to interconnect a wind or solar generation facility shall maintain meteorological data facilities as well as provide that meteorological data which is required per Schedule H to the Interconnection Service Agreement and Section 8 of Manual 14D.

PJM utilizes manufacturer models to ensure the performance of turbines is properly captured during the simulations performed for stability verification and, where applicable, for compliance with low voltage ride through requirements. Turbine manufacturers provide such models to their customers. The list of manufacturer models PJM has already validated is contained in Attachment B of Manual 14G. Manufacturer models may be updated from time to time, for various reasons such as to reflect changes to the control systems or to more accurately represent the capabilities turbines and controls which are currently available in the field. Additionally, as new turbine models are developed, turbine manufacturers provide such new models which must be used in the conduct of these studies. PJM needs adequate time to evaluate the new models in order to reduce delays to the System Impact Study process timeline for the Interconnection Customer as well as other Interconnection Customers in the study group. Therefore, PJM will require that any Interconnection Customer with a new manufacturer model must supply that model to PJM, along with a $10,000 fully refundable deposit, no later than three (3) months prior to the starting date of the System Impact Study (See Section 4.3 for starting dates) for the Interconnection Request which shall specify the use of the new model.

The Interconnection Customer will be required to submit a completed dynamic model study request form (Attachment B-1 of Manual 14G) in order to document the request for the study.

The Feasibility Study estimates do not include the feasibility, cost, or time required to obtain property rights and permits for construction of the required facilities. The project developer is responsible for the right of way, real estate, and construction permit issues. For properties currently owned by Transmission Owners, the costs may be included in the study.

3 General

The Interconnection Customer (IC), has proposed a Solar generating facility located in Morrow County, Ohio. The installed facilities will have a total capability of 64 MW with 26.88 MW of this output being recognized by PJM as Capacity. The proposed in-service date for this project is November 11, 2022. This study does not imply a TO commitment to this in-service date.

4 Point of Interconnection

AF1-122 will interconnect with the ATSI transmission system at the Cardington 138 kV substation.

4.1 Primary POI

The interconnection of the project to the ATSI system will be accomplished by constructing a direct connection to the Cardington 138 kV substation. The IC will be responsible for acquiring all easements, properties, and permits that may be required to construct the associated Attachment facilities.

Attachment 1 shows a one-line diagram of the proposed primary direct connection facilities for the AF1-122 generation project to connect to the FirstEnergy (“FE”) transmission system. IC will be responsible for constructing all of the facilities on its side of the POI, including the attachment facilities which connect the generator to the FE transmission system’s direct connection facilities.

4.2 Secondary POI

The interconnection of the project at a Secondary POI can be accomplished by tapping the Cardington –Liberty 69 kV line. A full scope of work or estimated cost is not provided for the proposed Secondary POI.

5 Cost Summary

The AF1-122 project will be responsible for the following costs:

In addition, the AF1-122 project may be responsible for a contribution to the following costs

Cost allocations for these upgrades will be provided in the System Impact Study Report.

The Feasibility Study is used to make a preliminary determination of the type and scope of Attachment Facilities, Local Upgrades, and Network Upgrades that will be necessary to accommodate the Interconnection Request and to provide the Interconnection Customer a preliminary estimate of the time that will be required to construct any necessary facilities and upgrades and the Interconnection Customer’s cost responsibility. The System Impact Study provides refined and comprehensive estimates of cost responsibility and construction lead times for new facilities and system upgrades. Facilities Studies will include, commensurate with the degree of engineering specificity as provided in the Facilities Study Agreement, good faith estimates of the cost, determined in accordance with Section 217 of the Tariff,

(a) to be charged to each affected New Service Customer for the Facilities and System Upgrades that are necessary to accommodate this queue project;

(b) the time required to complete detailed design and construction of the facilities and upgrades; and

(c) a description of any site-specific environmental issues or requirements that could reasonably be anticipated to affect the cost or time required to complete construction of such facilities and upgrades.

The costs provided above exclude the Contribution in Aid of Construction (“CIAC”) Federal Income Tax Gross Up charge. If, at a future date, it is determined that the CIAC Federal Income Tax Gross charge is required, the Transmission Owner shall be reimbursed by the Interconnection Customer for such taxes.

The required Attachment Facilities and Direct and/or Non-Direct Connection work for the interconnection of the AF1-122 generation project to the FE Transmission System is detailed in the following sections. The

associated one-line with the generation project Attachment Facilities and the Primary Direct and Non-Direct Connection facilities are shown in Attachment 1.

6 Transmission Owner Scope of Work

The interconnection of the project at the Primary POI will be accomplished by constructing a new 138 kV three (3) breaker ring at Cardington Substation and connecting the AF1-122 138 kV line into the station. The IC will be responsible for acquiring all easements, properties, and permits that may be required to construct the line from Cardington Substation to their collector substation.

7 Attachment Facilities

The total preliminary cost estimate for the Attachment work is given in the table below. These costs do not include CIAC Tax Gross-up.

8 Direct Connection Cost Estimate

The total preliminary cost estimate for the Direct Connection work is given in the table below. These costs do not include CIAC Tax Gross-up.

Description

Reconfigure existing 138 kV yard at Cardington Substation to a 3-breaker ring bus for AF1-122

Reconnect existing Cardington-Galion 138 kV line to the new 3-breaker ring at Cardington Substation

9 Non-Direct Connection Cost Estimate

The total preliminary cost estimate for the Non-Direct Connection work is given in the table below. These costs do not include CIAC Tax Gross-up. Description

10 Schedule

Based on the scope of work for the Attachment Facilities and the Direct and/or Non-Direct Connection facilities, it is expected to take a minimum of 18 months after the signing of an Interconnection Construction Service Agreement to complete the installation. This includes the requirement for the IC to make a preliminary payment that compensates FE for the first three months of the engineering design work that is related to the construction of the interconnection substation. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined direct connection and network upgrades, and that all transmission system outages will be allowed when requested.

The schedule for the required Network Impact Reinforcements will be more clearly identified in future study phases. The estimate elapsed time to complete each of the required reinforcements is identified in the “System Reinforcements” section of the report.

11 Transmission Owner Analysis

11.1 Power Flow Analysis

FE performed an analysis of its underlying transmission <100 kV system. The AF1-122 project did not contribute to any overloads on the FE transmission system.

12 Interconnection Customer Requirements

12.1 System Protection

The IC must design it’s Customer Facilities in accordance with all applicable standards, including the standards in FE’s “Requirements for Transmission Connected Facilities” document located at: http://www.pjm.com/planning/design-engineering/to-tech-standards/private-firstenergy.aspx. Preliminary Protection requirements will be provided as part of the Facilities Study. Detailed Protection Requirements will be provided once the project enters the construction phase.

The IC has requested a non-standard GSU transformer winding configuration. This transformer is in violation of section 14.2.6 of FE’s “Requirements for Transmission Connected Facilities” document and will not be accepted. The GSU transformer must have a grounded wye connection on the high (utility) side and a delta connection on the low (generator) side.

12.2 Compliance Issues and Interconnection Customer Requirements

The proposed Customer Facilities must be designed in accordance with FE’s “Requirements for Transmission Connected Facilities” document located at: http://www.pjm.com/planning/design-engineering/to-techstandards/private-firstenergy.aspx. In particular, the IC is responsible for the following:

1. The purchase and installation of a fully rated 138 kV circuit breaker to protect the AF1-122 generator lead line. A single circuit breaker must be used to protect this line; if the project has several GSU transformers, the individual GSU transformer breakers cannot be used to protect this line.

2. The purchase and installation of the minimum required FE generation interconnection relaying and control facilities. This includes over/under voltage protection, over/under frequency protection, and zero sequence voltage protection relays.

3. The purchase and installation of supervisory control and data acquisition (“SCADA”) equipment to provide information in a compatible format to the FE Transmission System Control Center.

4. Compliance with the FE and PJM generator power factor and voltage control requirements.

5. The execution of a back-up service agreement to serve the customer load supplied from the AF1-122 generation project metering point when the units are out-of-service. This assumes the intent of the IC is to net the generation with the load.

The IC will also be required to meet all PJM, ReliabilityFirst, and NERC reliability criteria and operating procedures for standards compliance. For example, the IC will need to properly locate and report the over and under voltage and over and under frequency system protection elements for its units as well as the submission of the generator model and protection data required to satisfy the PJM and ReliabilityFirst audits. Failure to comply with these requirements may result in a disconnection of service if the violation is found to compromise the reliability of the FE system.

12.3 Power Factor Requirements

The IC shall design its non-synchronous Customer Facility with the ability to maintain a power factor of at least 0.95 leading (absorbing VARs) to 0.95 lagging (supplying VARs) measured at the high-side of the facility substation transformer(s) connected to the FE transmission system.

13 Revenue Metering and SCADA Requirements

13.1

PJM Requirements

The Interconnection Customer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for IC's generating Resource. See PJM Manuals M-01 and M14D, and PJM Tariff Section 8 of Attachment O.

13.1.1

Meteorological Data Reporting Requirements

The solar generation facility shall provide the Transmission Provider with site-specific meteorological data including:

 Temperature (degrees Fahrenheit)

 Atmospheric pressure (hectopascals)

 Irradiance

 Forced outage data

13.2

FE Requirements

The IC will be required to comply with all FE revenue metering requirements for generation interconnection customers which can be found in FE’s “Requirements for Transmission Connected Facilities” document located at: http://www.pjm.com/planning/design-engineering/to-tech-standards/private-firstenergy.aspx

14 Network Impacts – Primary POI

The Queue Project AF1-122 was evaluated as a 64.0 MW (Capacity 26.9 MW) injection at the Cardington 138 kV substation in the ATSI area. Project AF1-122 was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Project AF1-122 was studied with a commercial probability of 53%. Potential network impacts were as follows:

Summer Peak Load Flow

14.1 Generation Deliverability

(Single or N-1 contingencies for the Capacity portion only of the interconnection)

None

14.2 Multiple Facility Contingency

(Double Circuit Tower Line, Fault with a Stuck Breaker, and Bus Fault contingencies for the full energy output)

None

14.3 Contribution to Previously Identified Overloads

(This project contributes to the following contingency overloads, i.e. "Network Impacts", identified for earlier generation or transmission interconnection projects in the PJM Queue)

None

14.4 Potential Congestion due to Local Energy Deliverability

PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting a Merchant Transmission Interconnection request.

Note: Only the most severely overloaded conditions are listed below. There is no guarantee of full delivery of energy for this project by fixing only the conditions listed in this section. With a Transmission Interconnection Request, a subsequent analysis will be performed which shall study all overload conditions associated with the overloaded element(s) identified.

14.5 System Reinforcements

None

14.6 Flow Gate Details

The following indices contain additional information about each flowgate presented in the body of the report. For each index, a description of the flowgate and its contingency was included for convenience. However, the intent of the appendix section is to provide more information on which projects/generators have contributions to the flowgate in question. Although this information is not used "as is" for cost allocation purposes, it can be used to gage other generators impact. It should be noted the generator contributions presented in the appendices sections are full contributions, whereas in the body of the report, those contributions take into consideration the commercial probability of each project.

Affected Systems

14.7 Affected Systems

14.7.1 LG&E

LG&E Impacts to be determined during later study phases (as applicable).

14.7.2 MISO

MISO Impacts to be determined during later study phases (as applicable).

14.7.3 TVA

TVA Impacts to be determined during later study phases (as applicable).

14.7.4 Duke Energy Progress

Duke Energy Progress Impacts to be determined during later study phases (as applicable).

14.7.5 NYISO

NYISO Impacts to be determined during later study phases (as applicable).

Short Circuit

14.8 Short Circuit

The following Breakers are overduty

None

15 Network Impacts – Secondary POI

The Queue Project AF1-122 was evaluated as a 64 MW (Capacity 26.88 MW) injection tapping the Cardington to Liberty 69 kV line in the ATSI area. Project AF1-122 was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Project AF1-122 was studied with a commercial probability of 53%. Potential network impacts were as follows:

Summer Peak Load Flow

15.1 Generation Deliverability

(Single or N-1 contingencies for the Capacity portion only of the interconnection)

None

15.2 Multiple Facility Contingency

(Double Circuit Tower Line, Fault with a Stuck Breaker, and Bus Fault contingencies for the full energy output)

None

15.3 Contribution to Previously Identified Overloads

(This project contributes to the following contingency overloads, i.e. "Network Impacts", identified for earlier generation or transmission interconnection projects in the PJM Queue)

None

15.4 Potential Congestion due to Local Energy Deliverability

PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting a Merchant Transmission Interconnection request.

Note: Only the most severely overloaded conditions are listed below. There is no guarantee of full delivery of energy for this project by fixing only the conditions listed in this section. With a Transmission Interconnection Request, a subsequent analysis will be performed which shall study all overload conditions associated with the overloaded element(s) identified.

None

Affected Systems

15.5 Affected Systems

1.1.1 LG&E

LG&E Impacts to be determined during later study phases (as applicable).

1.1.2 MISO

MISO Impacts to be determined during later study phases (as applicable).

1.1.3 TVA

TVA Impacts to be determined during later study phases (as applicable).

1.1.4 Duke Energy Progress

Duke Energy Progress Impacts to be determined during later study phases (as applicable).

1.1.5 NYISO

NYISO Impacts to be determined during later study phases (as applicable).

Short Circuit

15.6 Short Circuit

The following Breakers are overduty

None

Interconnection Reports

AF1-122 System Impact Reports

9.1SystemProtection

9.2ComplianceIssuesandInterconnectionCustomerRequirements

1Introduction

ThisSystemImpactStudyhasbeenpreparedinaccordancewiththePJMOpenAccessTransmissionTariff,205, aswellastheSystemImpactStudyAgreementbetweentheInterconnectionCustomer(IC),andPJM Interconnection,LLC(PJM),TransmissionProvider(TP).TheInterconnectedTransmissionOwner(ITO)isATSI.

2Preface

TheintentoftheSystemImpactStudyistodetermineaplan,withapproximatecostandconstructiontime estimates,toconnectthesubjectgenerationinterconnectionprojecttothePJMnetworkatalocationspecified bytheInterconnectionCustomer.Asarequirementforinterconnection,theInterconnectionCustomermaybe responsibleforthecostofconstructing:NetworkUpgrades,whicharefacilityadditions,orupgradestoexisting facilities,thatareneededtomaintainthereliabilityofthePJMsystem.Allfacilitiesrequiredforinterconnection ofagenerationinterconnectionprojectmustbedesignedtomeetthetechnicalspecifications(onPJMwebsite) fortheappropriatetransmissionowner.

InsomeinstancesanInterconnectionCustomermaynotberesponsiblefor100%oftheidentifiednetwork upgradecostbecauseothertransmissionnetworkuses,e.g.anothergenerationinterconnectionormerchant transmissionupgrade,mayalsocontributetotheneedforthesamenetworkreinforcement.Thepossibilityof sharingthereinforcementcostswithotherprojectsmaybeidentifiedintheFeasibilityStudy,buttheactual allocationwillbedeferreduntiltheSystemImpactStudyisperformed.

TheSystemImpactStudyestimatesdonotincludethefeasibility,cost,ortimerequiredtoobtainpropertyrights andpermitsforconstructionoftherequiredfacilities.Theprojectdeveloperisresponsiblefortherightofway, realestate,andconstructionpermitissues.ForpropertiescurrentlyownedbyTransmissionOwners,thecosts maybeincludedinthestudy.

TheInterconnectionCustomerseekingtointerconnectawindorsolargenerationfacilityshallmaintain meteorologicaldatafacilitiesaswellasprovidethatmeteorologicaldatawhichisrequiredperScheduleHto theInterconnectionServiceAgreementandSection8ofManual14D.

3General

TheInterconnectionCustomer(IC),hasproposedaSolargeneratingfacilitylocatedinMorrowCounty,Ohio. Theinstalledfacilitieswillhaveatotalcapabilityof64MWwith26.88MWofthisoutputbeingrecognizedby PJMasCapacity.Theproposedin-servicedateforthisprojectisNovember30,2022.Thisstudydoesnotimply aTOcommitmenttothisin-servicedate.

AnynewservicecustomerswhocanfeasiblybecommerciallyoperablepriortoJune1stofthebasecasestudy yeararerequiredtorequestinterimdeliverabilityanalysis.

4PointofInterconnection

AF1-122willinterconnectwiththeATSItransmissionsystemontheCardington-Tangy69kVLine,about0.8 milesfromCardingtonSubstation.

5CostSummary

TheAF1-122projectwillberesponsibleforthefollowingcosts:

*Asyourprojectprogressesthroughthestudyprocessandotherprojectsmodifytheirrequestorwithdraw, thenyourcostallocationcouldchange.

ThiscostexcludesaFederalIncomeTaxGrossUpcharges.Thistaxmayormaynotbechargedbasedon whetherthisprojectmeetstheeligibilityrequirementsofIRSNotice88-129.Ifatafuturedateitisdetermined thattheFederalIncomeTaxGrosschargeisrequired,theTransmissionOwnershallbereimbursedbythe InterconnectionCustomerforsuchtaxes.

Note1:PJMOpenAccessTransmissionTariff(OATT)section217.3Aoutlinecostallocationrules.Therulesare furtherclarifiedinPJMManual14AAttachmentB.Theallocationofcostsforanetworkupgradewillstart withthefirstQueueprojecttocausetheneedfortheupgrade.Laterqueueprojectswillreceivecost allocationcontingentontheircontributiontotheviolationandareallocatedtothequeuesthathavenot closedlessthan5yearsfollowingtheexecutionofthefirstInterconnectionServiceAgreementwhich identifiestheneedforthisupgrade.

Note2:ForcustomerswithSystemReinforcementslisted:IfyourpresentcostallocationtoaSystem Reinforcementindicates$0,thenpleasebeawarethataschangestotheinterconnectionprocessoccur,such aspriorqueuedprojectswithdrawingfromthequeue,reducinginsize,etc,thecostresponsibilitiescan changeandacostallocationmaybeassignedtoyourproject.Inaddition,althoughyourpresentcost allocationtoaSystemReinforcementispresently$0,yourprojectmayneedthissystemreinforcement completedtobedeliverabletothePJMsystem.Ifyourprojectcomesintoservicepriortocompletionofthe systemreinforcement,aninterimdeliverabilitystudyforyourprojectwillberequired.

6TransmissionOwnerScopeofWork

TheinterconnectionoftheprojectatthePrimaryPOIwillbeaccomplishedbyconstructinganew69kVthree (3)breakerringbussubstationandloopingtheCardington-Tangy69kVLineintothenewstation.Thenew substationwillbelocatedapproximately0.8milesfromCardingtonSubstation.TheICwillberesponsiblefor acquiringalleasements,properties,andpermitsthatmayberequiredtoconstructboththenew interconnectionswitchingstationandtheassociatedfacilities.TheICwillalsoberesponsiblefortherough gradeofthepropertyandanaccessroadtotheproposedthree-breakerringbussite.Theprojectwillalso requireNon-DirectConnectionupgradesatCardingtonSubstationandTangySubstation.

Thetotalphysicalinterconnectioncostsisgiveninthetablebelow:

Description

AttachmentFacility:MOABandfirstspanforCustomer connectiontotheringbus

DirectConnection:Constructathree-breakerringbusonthe CardingtonTangy69kVLineapprox.0.8milesfromthe CardingtonSubstationatAF1-122RingBus

DirectConnection:Reviewdrawings,nameplates,andrelay settingsatAF1-122CustomerSubstation

DirectConnection:Design,install,andtest/commissionMPLS EquipmentforSCADAtransport. $217,100

DirectConnection:PLCequipment(maynotbeneeded -122 RingBus $349,900

Non-DirectConnection:LineterminalUpgradesatCardington Substation

Non-DirectConnection:LineterminalUpgradesatTangy Substation

Non-DirectConnection:ProjectManagement,Environmental, Forestry,RealEstateandSCADA.

Non-DirectConnection:PLCequipmentatTangySubstation inverters)

Non-DirectConnection:LooptheCardington-Tangy69kVLine tocreatetheinterconnectionforthenewAF1-1223-breaker ringbus,approximately0.8milesfromtheCardington Substation.InstallfiberfromthenewAF1-1223-breakerring bustotheCardingtonSubstation.

7Schedule

BasedonthescopeofworkfortheAttachmentFacilitiesandtheDirectand/orNon-DirectConnection facilities,itisexpectedtotakeaminimumof21monthsafterthesigningofanInterconnectionConstruction ServiceAgreementtocompletetheinstallation.ThisincludestherequirementfortheICtomakeapreliminary paymentthatcompensatesFEforthefirstthreemonthsoftheengineeringdesignworkthatisrelatedtothe constructionoftheinterconnectionsubstation.Thisassumesthattherewillbenoenvironmentalissueswith anyofthenewpropertiesassociatedwiththisproject,thattherewillbenodelaysinacquiringthenecessary permitsforimplementingthedefinedDirectConnectionandnetworkupgrades,andthatalltransmission systemoutageswillbeallowedwhenrequested.

TheschedulefortherequiredNetworkImpactReinforcementswillbemoreclearlyidentifiedinfuturestudy

8TransmissionOwnerAnalysis

FEperformedananalysisofitsunderlyingtransmission<100kVsystem.TheAF1-122projectdidnot contributetoanyoverloadsontheFETransmission<100kVSystem.

9InterconnectionCustomerRequirements

9.1SystemProtection

TheICmustdesignitsCustomerFacilitiesinaccordancewithallapplicablestandards,includingthestandards

http://www.pjm.com/planning/design-engineering/to-tech-standards/private-firstenergy.aspx.Preliminary ProtectionrequirementswillbeprovidedaspartoftheFacilitiesStudy.DetailedProtectionRequirementswill beprovidedoncetheprojectenterstheconstructionphase.

TheIChasrequestedanon-standardGSUtransformerwindingconfiguration.Thistransformerisinviolation entandwillnotbe accepted.

Inverter-basedgenerationthatisUL1741certifiedforanti-islandingprotectionconnectedtotheFE TransmissionSystemat<100kVshallhaveadeltaorungroundedwyewindingonthetransmissionside.

Inverter-basedgenerationthatisnotUL1741certifiedforanti-islandingprotectionconnectedtotheFE TransmissionSystemat<100kVshallhaveagroundedwyewindingonthetransmissionsideanddeltawinding onthegeneratorside.Inverter-basedgenerationthatisnotUL1741certifiedwillrequireadditionalback-up

anti-islandingprotectionestimatedtocostatotalof$699,800(excludingtaxes),asdetailedseparatelyinthe CostSummarysection.Thisback-upprotectionwillnotberequirediftheinvertersareUL1741certified.

9.2ComplianceIssuesandInterconnectionCustomerRequirements

http://www.pjm.com/planning/design-engineering/to-techstandards/private-firstenergy.aspx.Inparticular,theICisresponsibleforthefollowing:

1.Thepurchaseandinstallationofafullyrated69kVcircuitbreakertoprotecttheAF1-122generator leadline.Asinglecircuitbreakermustbeusedtoprotectthisline;iftheprojecthasseveralGSU transformers,theindividualGSUtransformerbreakerscannotbeusedtoprotectthisline.

2.ThepurchaseandinstallationoftheminimumrequiredFEgenerationinterconnectionrelayingand controlfacilities.Thisincludesover/undervoltageprotection,over/underfrequencyprotection,and zerosequencevoltageprotectionrelays.

3.Thepurchaseandins provideinformationinacompatibleformattotheFETransmissionSystemControlCenter.

4.CompliancewiththeFEandPJMgeneratorpowerfactorandvoltagecontrolrequirements.

5.Theexecutionofaback-upserviceagreementtoservethecustomerloadsuppliedfromtheAF1-122 generationprojectmeteringpointwhentheunitsareout-of-service.ThisassumestheintentoftheIC istonetthegenerationwiththeload.

TheICwillalsoberequiredtomeetallPJM,ReliabilityFirst,andNERCreliabilitycriteriaandoperating proceduresforstandardscompliance.Forexample,theICwillneedtoproperlylocateandreporttheoverand undervoltageandoverandunderfrequencysystemprotectionelementsforitsunitsaswellasthe submissionofthegeneratormodelandprotectiondatarequiredtosatisfythePJMandReliabilityFirstaudits. Failuretocomplywiththeserequirementsmayresultinadisconnectionofserviceiftheviolationisfoundto compromisethereliabilityoftheFETransmissionSystem.

9.3PowerFactorRequirements

TheICshalldesignitsnon-synchronousCustomerFacilitywiththeabilitytomaintainapowerfactorofatleast 0.95leading(absorbingVARs)to0.95lagging(supplyingVARs)measuredatthehigh-sideofthefacility substationtransformer(s)connectedtotheFETransmissionSystem.

10RevenueMeteringandSCADARequirements

10.1PJMRequirements

TheInterconnectionCustomerwillberequiredtoinstallequipmentnecessarytoprovideRevenueMetering (KWH,KVARH)andrealtimedata(KW,KVAR)forIC'sgeneratingResource.SeePJMManualsM-01andM14D,andPJMTariffSection8ofAttachmentO.

10.2MeteorologicalDataReportingRequirements

ThesolargenerationfacilityshallprovidetheTransmissionProviderwithsite-specificmeteorologicaldata including:

BackPaneltemperature(Fahrenheit)

Irradiance(Watts/meter2)

Ambientairtemperature(Fahrenheit)(Accepted,notrequired)

Windspeed(meters/second)(Accepted,notrequired)

Winddirection(decimaldegreesfromtruenorth)(Accepted,notrequired)

10.3InterconnectedTransmissionOwnerRequirements

TheICwillberequiredtocomplywithallFErevenuemeteringrequirementsforgenerationinterconnection customerswhic at:http://www.pjm.com/planning/design-engineering/to-tech-standards/private-firstenergy.aspx

11SummerPeakAnalysis

TheQueueProjectAF1-122wasevaluatedasa64.0MW(Capacity26.9MW)injectionattheCardington69kV substationintheATSIarea.ProjectAF1-122wasevaluatedforcompliancewithapplicablereliabilityplanning criteria(PJM,NERC,NERCRegionalReliabilityCouncils,andTransmissionOwners).ProjectAF1-122was studiedwithacommercialprobabilityof100.0%.Potentialnetworkimpactswereasfollows:

11.1GenerationDeliverability

(SingleorN-1contingenciesfortheCapacityportiononlyoftheinterconnection)

None

11.2MultipleFacilityContingency

(DoubleCircuitTowerLine,FaultwithaStuckBreaker,andBusFaultcontingenciesforthefullenergyoutput)

None

11.3ContributiontoPreviouslyIdentifiedOverloads

(Thisprojectcontributestothefollowingcontingencyoverloads,i.e."NetworkImpacts",identifiedforearlier generationortransmissioninterconnectionprojectsinthePJMQueue)

None

11.4Steady-StateVoltageRequirements

Tobedetermined

11.5PotentialCongestionduetoLocalEnergyDeliverability

PJMalsostudiedthedeliveryoftheenergyportionofthisinterconnectionrequest.Anyproblemsidentified belowarelikelytoresultinoperationalrestrictionstotheprojectunderstudy.Thedevelopercanproceed withnetworkupgradestoeliminatetheoperationalrestrictionattheirdiscretionbysubmittingaMerchant TransmissionInterconnectionrequest.

Note:Onlythemostseverelyoverloadedconditionsarelistedbelow.Thereisnoguaranteeoffulldeliveryof energyforthisprojectbyfixingonlytheconditionslistedinthissection.WithaTransmissionInterconnection Request,asubsequentanalysiswillbeperformedwhichshallstudyalloverloadconditionsassociatedwiththe overloadedelement(s)identified.

None

11.6SystemReinforcements

None.

11.7QueueDependencies

TheQueueProjectsbelowarelistedinoneormoreindicesfortheoverloadsidentifiedinyourreport.These projectscontributetotheloadingoftheoverloadedfacilitiesidentifiedinyourreport.Thepercentoverload ofafacilityandcostallocationyoumayhavetowardsaparticularreinforcementcouldvarydependingonthe actionoftheseearlierprojects.Thestatusofeachprojectatthetimeoftheanalysisispresentedinthetable. Thislistmaychangeasearlierprojectswithdrawormodifytheirrequests.

None

Notrequiredforsolarprojects.

13ShortCircuitAnalysis

ThefollowingBreakersareoverdutied:

None

13.1SystemReinforcements-ShortCircuit

None

14StabilityandReactivePower

(SummaryoftheVARrequirementsbasedupontheresultsofthedynamicstudies)

TobedeterminedintheFacilitiesStudyPhase.

15AffectedSystems

15.1NYISO

NYISOImpactstobedeterminedduringlaterstudyphases(asapplicable).

15.2MISO

MISOImpactstobedeterminedduringlaterstudyphases(asapplicable).

16Attachment1:OneLineDiagram

AF1-122 System Impact Study Report

v0.09 released 2022-11-16 08:20

Cardington-Liberty 69 kV

26.88 MW Capacity / 64.0 MW Energy

Introduction

This System Impact Study Report (SIS) has been prepared in accordance with the PJM Open Access Transmission Tariff, 205, as well as the System Impact Study Agreement between Crossroads Solar I, LLC, the Interconnection Customer (IC), and PJM Interconnection, LLC (PJM), Transmission Provider (TP). The Interconnected Transmission Owner (ITO) is American Transmission Systems, Incorporated.

Revision 1: November 2022 - The AF1-122 System Impact Study Report has been revised to reflect the results of the PJM's re-tool analysis and to included finalized stability analysis. Final scope, cost and schedule for the physical interconnection will be provided in the Facilities Study Report.

• AF1-122 does not meet the reactive power requirement at the high side of main transformer. Reactive power compensation is required for this project.

Preface

The intent of the System Impact is to determine a plan, with approximate cost and construction time estimates, to connect the subject generation interconnection project to the PJM network at a location specified by the Interconnection Customer. As a requirement for interconnection, the Interconnection Customer may be responsible for the cost of constructing: Network Upgrades, which are facility additions, or upgrades to existing facilities, that are needed to maintain the reliability of the PJM system. All facilities required for interconnection of a generation interconnection project must be designed to meet the technical specifications (on PJM web site) for the appropriate transmission owner.

In some instances an Interconnection Customer may not be responsible for 100% of the identified network upgrade cost because other transmission network uses, e.g. another generation interconnection or merchant transmission upgrade, may also contribute to the need for the same network reinforcement. The possibility of sharing the reinforcement costs with other projects may be identified in the Feasibility Study, but the actual allocation will be deferred until the System Impact Study is performed.

The System Impact study estimates do not include the feasibility, cost, or time required to obtain property rights and permits for construction of the required facilities. The project developer is responsible for the right of way, real estate, and construction permit issues. For properties currently owned by Transmission Owners, the costs may be included in the study.

General

The Interconnection Customer (IC), has proposed a generating facility located in Morrow County, Ohio. The installed facilities will have a total capability of 64.0 MW with 26.88 MW of this output being recognized by PJM as Capacity. The proposed in-service date for this project is Wednesday, November 30, 2022. This study does not imply a TO commitment to this in-service date.

Project Information

Queue Number AF1-122

Project Name Cardington-Liberty 69 kV

Developer Name Crossroads Solar I, LLC

State Ohio County Morrow

Point of Interconnection

AF1-122 will interconnect with on the ATSI transmission system at the Cardington 138 kV substation.

Cost Summary

The project may be responsible for a contribution to the following costs:

Description

Physical Interconnection

System Reinforcements

$8,215,200

$0

Note 1: PJM Open Access Transmission Tariff (OATT) section 217.3A outline cost allocation rules. The rules are further clarified in PJM Manual 14A Attachment B. The allocation of costs for a network upgrade will start with the first Queue project to cause the need for the upgrade. Later queue projects will receive cost allocation contingent on their contribution to the violation and are allocated to the queues that have not closed less than 5 years following the execution of the first Interconnection Service Agreement which identifies the need for this upgrade.

Note 2: For customers with System Reinforcements listed: If your present cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as prior queued projects withdrawing from the queue, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to your project. In addition, although your present cost allocation to a System Reinforcement is presently $0, your project may need this system reinforcement completed to be deliverable to the PJM system. If your project comes into service prior to completion of the system reinforcement, an interim deliverability study for your project will be required.

Transmission Owner Scope of Work

The interconnection of the project at the Primary POI will be accomplished by constructing a new 69 kV three (3) breaker ring bus substation and looping the Cardington-Tangy 69 kV Line into the new station. The new substation will be located approximately 0.8 miles from Cardington Substation. The IC will be responsible for acquiring all easements, properties, and permits that may be required to construct both the new interconnection switching station and the associated facilities. The IC will also be responsible for the rough grade of the property and an access road to the proposed three-breaker ring bus site. The project will also require Non-Direct Connection upgrades at Cardington Substation and Tangy Substation.

The total preliminary cost estimate is given in the table below. These costs do not include CIAC Tax Gross-up.

Physical Interconnection:

RTEP ID Description

(TBD) MOAB and first span for Customer connection to the ring bus

(TBD)

Construct a three-breaker ring bus on the Cardington – Tangy 69kV Line approx. 0.8 miles from the Cardington Substation at AF1-122 Ring Bus

(TBD) Review drawings, nameplates, and relay settings at AF1-122 Customer Substation

(TBD) Design, install, and test/commission MPLS Equipment for SCADA transport

(TBD) PLC equipment (may not be needed depending on generator’s selection of inverters) at AF1-122 Ring

(TBD) Line terminal Upgrades at Cardington Substation

(TBD) Line terminal Upgrades at Tangy Substation

(TBD) Project Management, Environmental, Forestry, Real Estate and SCADA.

(TBD) PLC equipment at Tangy Substation (may not be needed depending on generator’s selection of inverters)

(TBD)

Loop the Cardington-Tangy 69kV Line to create the interconnection for the new AF1-122 3-breaker approximately 0.8 miles from the Cardington Substation. Install fiber from the new AF1-122 3-breaker bus to the Cardington Substation.

Based on the scope of work for the interconnection facilities, it is expected to take a range of 21 to 21 month(s) after the signing of an Interconnection Construction Service Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

The schedule for any required Network Impact Reinforcements will be more clearly identified in future study phases. The estimated time to complete each of the required reinforcements is identified in the "System Reinforcements" section of the report.

Transmission Owner Analysis

ATSI performed an analysis of its distribution system. The AF1-122 project did not contribute to any overloads on the distribution system.

Interconnection Customer Requirements

System Protection

The IC must design its Customer Facilities in accordance with all applicable standards, including the standards in FE’s “Requirements for Transmission Connected Facilities” document located at: http://www.pjm.com/planning/design-engineering/to-techstandards/private-firstenergy.aspx. Preliminary Protection requirements will be provided as part of the Facilities Study. Detailed Protection Requirements will be provided once the project enters the construction phase.

The IC has requested a non-standard GSU transformer winding configuration. This transformer is in violation of section 14.2.6 of FE’s “Requirements for Transmission Connected Facilities” document and will not be accepted.

Inverter-based generation that is UL1741 certified for anti-islanding protection connected to the FE Transmission System at <100kV shall have a delta or ungrounded wye winding on the transmission side.

Inverter-based generation that is not UL1741 certified for anti-islanding protection connected to the FE Transmission System at <100kV shall have a grounded wye winding on the transmission side and delta winding on the generator side. Inverter-based generation that is not UL1741 certified will require additional back-up

Compliance Issues and Interconnection Customer Requirements

The proposed Customer Facilities must be designed in accordance with FE’s “Requirements for Transmission Connected Facilities” document located at: http://www.pjm.com/planning/design-engineering/to-techstandards/privatefirstenergy.aspx. In particular, the IC is responsible for the following:

1. The purchase and installation of a fully rated 69 kV circuit breaker to protect the AF1-122 generator lead line. A single circuit breaker must be used to protect this line; if the project has several GSU transformers, the individual GSU transformer breakers cannot be used to protect this line.

2. The purchase and installation of the minimum required FE generation interconnection relaying and control facilities. This includes over/under voltage protection, over/under frequency protection, and zero sequence voltage protection relays.

3. The purchase and installation of supervisory control and data acquisition (“SCADA”) equipment to provide information in a compatible format to the FE Transmission System Control Center.

4. Compliance with the FE and PJM generator power factor and voltage control requirements.

5. The execution of a back-up service agreement to serve the customer load supplied from the AF1-064 generation project metering point when the units are out-ofservice. This assumes the intent of the IC is to net the generation with the load.

The IC will also be required to meet all PJM, ReliabilityFirst, and NERC reliability criteria and operating procedures for standards compliance. For example, the IC will need to properly locate and report the over and under voltage and over and under frequency system protection elements for its units as well as the submission of the generator model and protection data required to satisfy the PJM and ReliabilityFirst audits. Failure to comply with these requirements may result in a disconnection of service if the violation is found to compromise the reliability of the FE Transmission System.

Power Factor Requirements

The IC shall design its solar Customer Facility with the ability to maintain a power factor of at least 0.95 leading (absorbing VARs) to 0.95 lagging (supplying VARs) measured at the high-side of the facility substation transformer(s) connected to the FE transmission system.

Revenue Metering and SCADA Requirements

PJM Requirements

The Interconnection Customer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for IC's generating Resource. See PJM Manuals M-01 and M14D, and PJM Tariff Section 8 of Attachment O.

Meteorological Data Reporting Requirement

The solar generation facility shall provide the Transmission Provider with site-specific meteorological data including:

• Temperature (degrees Fahrenheit)

• Atmospheric Pressure (hectopascals)

• Irradiance

• Forced outage data

Interconnection Transmission Owner Requirements

The IC will be required to comply with all Interconnected Transmission Owner's revenue metering requirements for generation interconnection customers located at the following link: PJM - Transmission Owner Engineering & Construction Standards.

PJM Transmission Network Impacts Analysis

Summer Peak Analysis

The Queue Project was evaluated as a 64.0 MW (Capacity 26.88 MW) injection in the area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential Summer peak period network impacts were as follows:

(No impacts were found for this analysis)

Summer Potential Congestion due to Local Energy Deliverability

PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting a Merchant Transmission Interconnection request.

Note: Only the most severely overloaded conditions are listed below. There is no guarantee of full delivery of energy for this project by fixing only the conditions listed in this section. With a Transmission Interconnection Request, a subsequent analysis will be performed which shall study all overload conditions associated with the overloaded element(s) identified.

(No impacts were found for this analysis)

Winter Peak Analysis

At this time winter peak analysis not required for this project.

Winter Potential Congestion due to Local Energy Deliverability

At this time winter peak analysis not required for this project.

Light Load Analysis

At this time light load analysis not required for this project.

Light Load Potential Congestion due to Local Energy Deliverability

At this time light load analysis not required for this project.

Short Circuit Analysis

The following breakers are overdutied:

None

Stability Analysis

No Stability issues were found.

Reactive Power Analysis

AF1-122 was assessed for compliance with reactive power capability requirements using the supplied capability curves. Please note this is a new facility.

• Generation shall have the ability to maintain a power factor of at least 0.95 leading to 0.95 lagging at the high side of facility transformer or the result of the System Impact Study indicated that, for the safety and reliably of the Transmission System, no power factor requirement is required, .

AF1-122 does not meet the reactive power requirement at the high side of main transformer. Reactive power compensation is required for this project. This project needs to have additional reactive power capabilities to fulfill the power factor requirement. The estimated required additional capacitive reactive power is 7.35 MVAr. See attachments for full stability report.

Steady-State Voltage Analysis

Steady State Voltage analysis is not required for this queue project at this time.

Queue Dependencies

The Queue Projects below are listed in one or more dispatch for the overloads identified in your report. These projects contribute to the loading of the overloaded facilities identified in your report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of these earlier projects. The status of each project at the time of the analysis is presented in the table. This list may

change as earlier projects withdraw or modify their requests. This table is valid for load flow analyses only.

Queue Number Project Name Status

Affected Systems

Midcontinent Independent System Operator (MISO) Not required

New York Independent System Operator (NYISO) Not required

Tennessee Valley Authority (TVA) Not required

Louisville Gas & Electric (LG&E) Not required

Duke Progress Energy (DUKE) Not required

System Reinforcements

Attachments

AF1-122 One-Line Diagram

AF1-122-3 Dynamic Analysis Report

AF1-122 System Impact Study

Dynamic Simulation Analysis

AF1-122

System Impact Study

Dynamic Simulation Analysis

Prepared by CF Power Ltd

For PJM Interconnection, LLC

Reference AF1-122-3-1

Date October 28th , 2022

Revision Issue Date

Revision Table

Description

0 July 29th, 2020 Initial Issue

1 October 28th, 2022

Re-study per the updated data and latest information

Reviewers

Name Interest Date

Approval

Name Position Date

AF1-122 System Impact Study Dynamic Simulation Analysis AF1-122-3-1

AF1-122 System Impact Study Dynamic Simulation Analysis

Executive Summary

Generator Interconnection Request AF1-122 is for a 64 MW Maximum Facility Output (MFO) solar generating facility consisting of 32 SMA SC2200 inverters connecting to the First Energy (FE) transmission system, ATSI zone. The AF1-122 solar generating facility will be located at Morrow County, Ohio.

The interconnection of the project at the Point of Interconnection (POI) will be accomplished by tapping the Cardington - Liberty 69 kV line via a 0.20 Miles 69 kV transmission line. The Point of Interconnection (POI) will be where the Interconnection Customer gen-tie line terminates at the new substation.

This report describes a dynamic simulation analysis of AF1-122 as part of the overall system impact study. The load flow scenario for the analysis was based on the RTEP 2023 peak load case, modified to include applicable queue projects. AF1-122 has been dispatched online at maximum power output, with approximately unity power factor at the high side of the GUS, 1.02 pu voltage at the generator terminal, and 1.03 pu voltage at the POI bus

AF1-122 was tested for compliance with NERC, PJM, Transmission Owner, and other applicable criteria. 86 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

a) Steady state operation (Category P0);

b) Three phase faults with normal clearing time on the intact network (Category P1);

c) Single phase to ground faults with delayed clearing due to a stuck breaker (Category P4);

d) Single phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5);

e) Single phase to ground faults with normal clearing for common structure (Category P7).

For all 86 fault contingencies tested on the 2023 peak load case:

a) AF1-122 was able to ride through the faults.

b) Post-contingency oscillations were positively damped with a damping margin of at least 3%.

c) Following fault clearing, all bus voltages recover to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

d) No other transmission element trips, other than those either directly connected or designed to trip as a consequence of that fault

Please note that the solar generating facility AF1-122 does not meet the reactive power requirement at the high side of main transformer. Reactive power compensation is required for this project. This project needs to have additional reactive power capabilities to fulfill the power factor requirement. The estimated required additional capacitive reactive power is 7 35 MVAR

No other mitigations were found to be required for this project.

AF1-122 System Impact Study Dynamic Simulation Analysis

1. Introduction

Generator Interconnection Request AF1-122 is for a 64 MW Maximum Facility Output (MFO) solar generating facility consisting of 32 SMA SC2200 inverters connecting to the First Energy (FE) transmission system, ATSI zone. The AF1-122 solar generating facility will be located at Morrow County, Ohio.

The interconnection of the project at the Point of Interconnection (POI) will be accomplished by tapping the Cardington - Liberty 69 kV line via a 0.20 Miles 69 kV transmission line. The Point of Interconnection (POI) will be where the Interconnection Customer gen-tie line terminates at the new substation.

This analysis is effectively a screening study to determine whether the addition of AF1122 will meet the dynamic requirements of the NERC, PJM, and Transmission Owner reliability standards.

In this report the AF1-122 project and how it is proposed to be connected to the grid are first described, followed by a description of how the project is modeled in this study. The fault cases are then described and analyzed, and lastly a discussion of the results is provided.

AF1-122 System Impact Study Dynamic Simulation Analysis

2. Description of Project

Generator Interconnection Request AF1-122 is for a 64 MW Maximum Facility Output (MFO) solar generating facility consisting of 32 SMA SC2200 inverters connecting to the First Energy (FE) transmission system, ATSI zone. The AF1-122 solar generating facility will be located at Morrow County, Ohio.

The interconnection of the project at the Point of Interconnection (POI) will be accomplished by tapping the Cardington - Liberty 69 kV line via a 0.20 Miles 69 kV transmission line. The Point of Interconnection (POI) will be where the Interconnection Customer gen-tie line terminates at the new substation.

The connection diagram of the AF1-122 generating facility is shown in Figure 1. Table 1 lists the parameters given in the impact study data and the corresponding parameters of the AF1-122 load flow model.

Additional project details are provided in Attachments 1 through 4:

• Attachment 1 contains the Impact Study Data which details the proposed AF1122 project.

• Attachment 2 shows the one line diagram of the ATSI network in the vicinity of AF1-122.

• Attachment 3 provides a diagram of the PSS/E model in the vicinity of AF1-122.

• Attachment 4 gives the PSS/E loadflow and dynamic models of the AF1-122.

To LibertyMarengo-OxfordHartford-Tangy 944572

AF1-122 System Impact Study Dynamic Simulation Analysis

Inverter Based Step-up Transformer 32 x 2 2 MVA 34 5/0 39 kV transformers 1 2 3 To Cardington

Inverter Based Main Transformer 43/57/71 MVA 69/34.5 kV

Lumped equivalent 32 x 2.2 MVA

Figure 1: AF1-122 Plant Model

Solar Inverters

Inverter Based Step-up Transformers

Main

Transformer

Collector System Equivalent

Table 1: AF1-122 Plant Model

Impact Study Data

32 X 2.2 MVA SMA SC2200

MVA base = 2.2 MVA

Vt = 0.39 kV

Zsource = N/A

Pgen1 = 2.03 MW

Qmax2 = 0.848 MVAr

Qmin = -0.848 MVAr

32 X 34.5/0.39 kV transformer

Rating = 2.2 MVA

Transformer base = 2.2 MVA

Impedance = 0.007132 + j0.057050 pu @ MVA base

Number of taps = N/A

Tap step size = N/A

1 x 69/34.5 kV transformers

Rating = 43/57/71 MVA (ONAN/ONAF/ONAF)

Transformer base = 43 MVA

H-L Impedance = 0.003101 + j0.089946 pu @ MVA base

Number of taps = N/A

Tap step size = N/A

34.5 kV collector equivalent circuit

Rating = 0 MVA

MVA base = 100 MVA

Impedance = 0.007284+ j0.004800 pu @ MVA base

Charging susceptance = 0.003255 pu @ MVA base

AF1-122 System Impact Study Dynamic Simulation Analysis

Model

1 x 70.40 MVA generator

Pgen 64.96 MW

Pmax 64.96 MW

Pmin 0.0 MW

Qgen 0.0 MVar

Qmax 27 14 MVAr

Qmin -27 14 MVAr

Mbase 70.40 MVA

Zsorce j99999pu @ Mbase

1 x 34.5/0.39 kV two winding transformer (Dy1)

Rating = 70.40 MVA

Transformer base = 70.40 MVA

Impedance = 0.007132 + j0.057050 pu @ MVA base

Number of taps = 5

Tap step size = 2.5 %

1 x 69/34.5 kV transformer (DY)

Rating = 43/57/71 MVA

Transformer base = 43 MVA

H-L Impedance = 0.003101 + j0.089946 pu @ MVA base

Number of taps = 33 Tap step size = 0.625 %

34.5 kV collector equivalent circuit

Rating = 0 MVA

MVA base = 100 MVA

Impedance = 0.007284+ j0.004800 pu @ MVA base

Charging susceptance = 0.003255 pu @ MVA base

1 MW/inverter was adjusted to 2.03 to meet the requested MFO at the POI.

2 The Leading and lagging values are calculated based on “SMA CP Series P-Q Diagram.PDF”.

Transmission Line

Auxiliary load3

Station Load

0.2 Miles 69 kV transmission line

Rating = 0 MVA

MVA base = 100 MVA

Impedance = 0.000044 + j0.007808 pu @ MVA base

Charging susceptance = 0.000013 pu @ MVA base

Active power = 0.0 MW

Reactive power = 0.0 MVAr

Active power = 0.0 MW

Reactive power = 0.0 MVAr

AF1-122 System Impact Study Dynamic Simulation Analysis AF1-122-3-1

0.2 Miles 69 kV transmission line

Rating = 0 MVA

MVA base = 100 MVA

Impedance = 0.000044 + j0.007808 pu @ MVA base

Charging susceptance = 0.000013 pu @ MVA base

P = 0.0 MW Q = 0.0 MVAr

P = 0.0 MW Q = 0.0 MVAr

3 According to the document “Planning Center - Reference Number_ 8800S9ZI, Queue_ AF1122_Updated 8-27-21.pdf”, there are no auxiliary loads or station loads.

Figure 2: AF1-122 Single Line Diagram (PSS/E)

System Impact Study Dynamic Simulation Analysis

3. Reactive Power Assessment

AF1-122 was assessed for compliance with reactive power capability requirements using the supplied capability curves. Please note this is a new facility.

• Generation shall have the ability to maintain a power factor of at least 0.95 leading to 0.95 lagging at the high side of facility transformer or the result of the System Impact Study indicated that, for the safety and reliably of the Transmission System, no power factor requirement is required4, 5

AF1-122 does not meet the reactive power requirement at the high side of main transformer. Reactive power compensation is required for this project. This project needs to have additional reactive power capabilities to fulfill the power factor requirement. The estimated required additional capacitive reactive power is 7.35 MVAr.

4. MFO Assessment

The MFO of AF1-122 was also assessed and found that the MFO at POI is equal to the requested MFO.

4 As specified in the document “Reactive Power Requirements.doc”, Date: 6/15/2018.

5 As specified in Attachment O of the document “PJM Open Access Transmission Tariff” Effective Date: 4/23/2018.

AF1-122 System Impact Study Dynamic Simulation Analysis

5. Loadflow and Dynamics Case Setup

The dynamics simulation analysis was carried out using PSS/E Version 33.12.

The load flow scenario and fault cases for this study are based on FE Transmission Planning Criteria6, PJM’s Regional Transmission Planning Process7 and discussions with PJM.

The selected load flow scenario is the RTEP 2023 peak load case with the following modifications:

a) Addition of all applicable queue projects prior to AF1-122.

b) Addition of AF1-122 queue project.

c) Removal of withdrawn and subsequent queue projects in the vicinity of AF1-122.

d) Dispatch of units in the PJM system in order to maintain slack generators within limits.

In the load flow the AF1-122 generator was set to maximum power output, with approximately unity power factor at the high side of the GUS, 1.02 pu voltage at the generator terminal, and 1.03 pu voltage at the POI bus

Table 2: AF1-122 machine initial conditions

Generation within the vicinity (within five buses) of AF1-122 has been dispatched online at maximum output (PMAX). The dispatch within the FE ATSI area is given in Attachment 5.

The following changes were made in order to complete the AF1-122 dynamic analysis:

1. For power flow model, in order to make the total MW value at the POI close to the requested MFO 64 MW, the MW/inverter was adjusted from 2.09 MW (as shown in the planning center data) to 2.03 MW. Thus, in the power flow model, the total project Pmax would be 64.96 MW, and the total project Qmax/min would be +/-27 14 MVAr according to the provided PQ curve.

2. For the dynamic model, parameters of REGCAU1, REECAU1, and REPCAU1 were set in accordance with the provided file ‘Generic SMA_DYR_REECA zip’, except for the below parameters in the REECAU1 and REPCAU1 models which were updated per the inverter capability as shown below.

a. REECAU1

i. CON(J+5) = 0.5 (Kqv (pu), Reactive current injection gain)

b. REPCAU1

6 First Energy, Transmission Planning Criteria – Transmission Systems, December 18, 2014.

7 Manual 14B: PJM Region Transmission Planning Process, Rev 46, August 28, 2019, Attachment G: PJM Stability, Short Circuit, and Special RTEP Practices and Procedures.

AF1-122 System Impact Study Dynamic Simulation Analysis

i. ICON(M) = 944570 (Bus number for voltage control)

ii. ICON(M+1) = 944571 (Monitored branch ‘FROM’)

iii. ICON(M+2) = 944570 (Monitored branch ‘TO’)

iv. ICON(M+3) = 1 (Branch circuit ID)

v. ICON(M+4) = 0 (VCFlag, droop flag (0: with droop,1: line drop compensation))

vi. ICON(M+5) = 1 (RefFlag, flag for V or Q control(0: Q control, 1: V control))

vii. ICON(M+6) = 0 (Fflag, 0: disable frequency control, 1: enable)

Meanwhile, parameters of the Frequency and Voltage relay models, ‘FRQTPAT’ and ‘VTGTPAT’, were set according to “SMAGeneric_ V33.dyr”. Lower voltage threshold for over-voltage relays was set to be -0.1 p.u. to avoid protection system misoperations. Under-voltage relay pickup time for 94457508 and 94457509 was set to 0.6s per the latest information

a. VTGTPAT

i. 94457501: CON(J) = -0.1 (VL);

ii. 94457502: CON(J) = -0.1 (VL);

iii. 94457503: CON(J) = -0.1 (VL);

iv. 94457504: CON(J) = -0.1 (VL);

v. 94457505: CON(J) = -0.1 (VL);

vi. 94457508: CON(J+2) = 0.6 (TP)

vii. 94457509: CON(J+2) = 0.6 (TP)

AF1-122 System Impact Study Dynamic Simulation Analysis

6. Fault Cases

The project was tested for compliance with NERC, FE, PJM, and other applicable criteria. 86 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Contingencies to be studied include:

a) Steady state operation (Category P0);

b) Three phase faults with normal clearing time on the intact network (Category P1);

c) Single phase to ground faults with delayed clearing due to a stuck breaker (Category P4);

d) Single phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5);

e) Single phase to ground faults with normal clearing for common structure (Category P7).

No High Speed Reclosing (HSR) contingencies were found in the vicinity of AF1-1228

Buses at which the faults listed above were applied are:

• Cardington 138/69 kV

• AF1-122 POI

• Tangy 69/138/345 kV

Table 3 gives the details of typical fault clearing time for 69 kV, 138 kV and 345 kV breakers at FE-ATSI9. Actual fault clearing times of some 69 kV breakers were used under FE’s instruction.

Table 3: AF1-122 breaker details – ATSI zone

A complete list of the contingencies that were studied is given in Table 5 to Error! Reference source not found.

8 PJM_HighSpeedReclosing_List_2019.xlsx

9 Rev. 22 of “2020 Revised Clearing time for each

AF1-122 System Impact Study Dynamic Simulation Analysis

7. Evaluation Criteria

This study is focused on AF1-122, along with the rest of the PJM system, maintaining synchronism and having all states return to an acceptable new condition following the disturbance. The recovery criteria applicable to this study are as per PJM’s Regional Transmission Planning Process and Transmission Owner criteria:

a) AF1-122 is able to ride through the faults (except for faults where protective action trips the generator(s)).

b) The system with AF1-122 included is transiently stable and post-contingency oscillations should be positively damped with a damping margin of at least 3%.

c) Following fault clearing, all bus voltages recover to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

d) No transmission element trips, other than those either directly connected or designed to trip as a consequence of that fault.

AF1-122 System Impact Study Dynamic Simulation Analysis

8. Summary of Results

Plots from the dynamic simulations are provided in Attachment 6, with results summarized in Table 5 through Error! Reference source not found..

Frequency protection in the model is disabled for faults at the POI due to the deficiency of PSSE frequency calculation for inverter based generation facilities.

For all 86 fault contingencies tested on the 2023 peak load case:

a) AF1-122 was able to ride through the faults.

b) Post-contingency oscillations were positively damped with a damping margin of at least 3%.

c) Following fault clearing, all bus voltages recover to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

d) No other transmission element trips, other than those either directly connected or designed to trip as a consequence of that fault

Network non-convergence was also observed as summarized in Table 4

Table 4: Summary of Network Non-Convergence

P1.24* 1.0~1.1042 AF1-122_GEN 944575

P1.27* 1.0~1.1042 AF1-122_GEN 944575

* Non-convergence during fault that should not be a problem if it recovers back after the fault is removed.

AF1-122 System Impact Study Dynamic Simulation Analysis AF1-122-3-1

Table 5: Steady State Operation – Category P0

P1.01

P1.02

P1.03

Table 6: Three-phase Faults with Normal Clearing – Category P1

description

3ph Fault at AF1-122 69 kV on AF1-122 circuit resulting in additional loss of :

• AF1-122 6 Stable

3ph Fault at AF1-122 69 kV on Cardington circuit (CRD-TAN) resulting in additional loss of :

• AF1-122 POI - Cardington (CRD-TAN) 5 (near end) / 35 (far end)10 Stable

3ph Fault at AF1-122 69 kV on Liberty - Marengo - Oxford - Hartford - Tangy circuit (CRD-TAN) resulting in additional loss of :

• AF1-122 POI - Liberty - Marengo - Oxford - Hartford - Tangy circuit (CRD-TAN)

P1.04

P1.05

P1.06

3ph Fault at Tangy 69 kV on Sciot0 - Radnor - Prospect Marion Muni - Richwood / Kirby circuit (KIR-RWD) resulting in additional loss of :

P1.08

P1.09

P1.10

5 (near end) / 35 (far end) Stable

• Tangy - Sciot0 - Radnor - Prospect Marion Muni - Richwood / Kirby circuit (KIR-RWD) 5 (near end) / 35 (far end) Stable

3ph Fault at Tangy 69 kV on Hartford - Oxford - Marengo - Liberty - AF1-122 circuit (CRD-TAN) resulting in additional loss of :

• Tangy - Hartford - Oxford - Marengo - Liberty - AF1-122 circuit (CRD-TAN) 5 (near end) / 35 (far end) Stable

3ph Fault at Tangy 69 kV on New California Union REC - Darby circuit (LON-TAN) resulting in additional loss of :

• Tangy - New California Union REC - Darby circuit (LON-TAN)

3ph Fault at Tangy 69 kV on Tangy 138 / 69 kV Transformer #1 resulting in additional loss of :

• Tangy 138 / 69 kV Transformer #1 6 Stable

3ph Fault at Tangy 69 kV on Tangy 138 / 69 kV Transformer #2 resulting in additional loss of :

• Tangy 138 / 69 kV Transformer #2

3ph Fault at Tangy 138 kV on Tangy 138 / 69 kV Transformer #1 resulting in additional loss of :

• Tangy 138 / 69 kV Transformer #1

3ph Fault at Tangy 138 kV on Tangy 138 / 69 kV Transformer #2 resulting in additional loss of :

Stable

• Tangy 138 / 69 kV Transformer #2 6 Stable

10 Fault clearing time of 5 cycles at the near end and 35 cycles at the far end are applied to P1.02, P1.03, P1.04, P1.05 and P1.25 in the simulation.

P1.12

3ph Fault at Tangy 138 kV on National Mod - London circuit (LON-TAN) resulting in additional loss of :

Tangy - National Mod - London circuit (LON-TAN)

3ph Fault at Tangy 138 kV on Bellepoint - Mill Creek - AD2-163 circuit (BVW-TAN) resulting in additional loss of : • Tangy - Bellepoint - Mill Creek - East Springfield circuit (BVW-TAN)

3ph Fault at Tangy 138 kV on Delaware Business Park - Crissinger circuit (CRS-TAN) resulting in additional loss of : • Tangy - Delaware Business Park - Crissinger circuit (CRS-TAN)

Stable

P1.14

P1.16

3ph Fault at Tangy 138 kV on South Sciot0 - Kirby circuit (KIR-TAN) resulting in additional loss of : • Tangy - South Sciot0 - Kirby circuit (KIR-TAN)

Fault at Tangy 138 kV on Tangy 138 / 345 kV Transformer #3 resulting in additional loss of : • Tangy 138 / 345 kV Transformer #3

Fault at Tangy 138 kV on Tangy 138 / 345 kV Transformer #4 resulting in additional loss of :

Tangy 138 / 345 kV Transformer #4

/

Tangy 138 / 345 kV Transformer #5

P1.18 3ph Fault at Tangy 345 kV on Tangy 138 / 345 kV Transformer #3 resulting in additional loss of : • Tangy 138 / 345 kV Transformer #3

P1.19

3ph Fault at Tangy 345 kV on Tangy 138 / 345 kV Transformer #4 resulting in additional loss of : • Tangy 138 / 345 kV Transformer #4

P1.20 3ph Fault at Tangy 345 kV on Tangy 138 / 345 kV Transformer #5 resulting in additional loss of : • Tangy 138 / 345 kV Transformer #5

P1.21

P1.22

Stable

3ph Fault at Tangy 345 kV on Marysville circuit (MRY-TAN) resulting in additional loss of :

• Tangy - Marysville circuit (MRY-TAN) 5 Stable

3ph Fault at Tangy 345 kV on Hyatt circuit (HYA-TAN) resulting in additional loss of :

• Tangy - Hyatt circuit (HYA-TAN)

Stable

P1.23

P1.24

P1.25

P1.26

P1.27

P1.28

3ph Fault at Cardington 69 kV on AF1-122 circuit (CRD-TAN) resulting in additional loss of :

• Cardington - AF1-122 circuit (CRD-TAN)

3ph Fault at Cardington 69 kV on Yutaka circuit (CRD-YUT) resulting in additional loss of :

• Cardington - Yutaka circuit (CRD-YUT)

3ph Fault at Cardington 69 kV on Schaaf - Edison - Bingham circuit (CRD-GAL) resulting in additional loss of :

Stable

Stable

• Cardington - Schaaf - Edison - Bingham circuit (CRD-GAL) 5 (near end) / 35 (far end) Stable

3ph Fault at Cardington 69 kV on Cardington 69 kV capacitor bank resulting in additional loss of :

• Cardington 69 kV capacitor bank

3ph Fault at Cardington 69 kV on Cardington 138 / 69 kV Transformer resulting in additional loss of : • Cardington 138 / 69 kV Transformer

3ph Fault at Cardington 138 kV on Galion circuit (CAR-GAL) resulting in additional loss of :

• Cardington - Galion circuit (CAR-GAL)

Stable

Stable

• Cardington 138 / 69 kV Transformer 6 Stable

P4_1B1.01

Table 7: Single-phase Faults with Stuck Breaker – Category P4

SLG Fault at AF1-122 POI on AF1-122 circuit resulting in additional loss of :

⚫ AF1-122

Breaker 2 stuck. Fault cleared with loss of :

P4_1B1.02

P4_1B1.03

P4_1B1.04

P4_1B1.05

P4_1B1.06

AF1-122 System Impact Study Dynamic Simulation Analysis

⚫ AF1-122 POI - Liberty - Marengo - Oxford - Hartford - Tangy circuit (CRD-TAN) 5/74

SLG Fault at AF1-122 POI on AF1-122 circuit resulting in additional loss of :

⚫ AF1-122

Breaker 3 stuck. Fault cleared with loss of :

⚫ AF1-122 POI - Cardington circuit (CRD-TAN) 5/74 Stable

SLG Fault at AF1-122 POI on Liberty - Marengo - Oxford - Hartford - Tangy circuit (CRD-TAN) resulting in additional loss of :

⚫ Tangy - Hartford circuit (CRD-TAN)

Breaker 1 stuck. Fault cleared with loss of :

⚫ AF1-122 POI - Liberty - Marengo - Oxford - Hartford circuit (CRD-TAN)

⚫ AF1-122 POI - Cardington circuit (CRD-TAN)

⚫ AF1-122

SLG Fault at AF1-122 POI on Cardington circuit (CRD-TAN) resulting in additional loss of :

⚫ AF1-122 POI - Cardington circuit (CRD-TAN)

Breaker 1 stuck. Fault cleared with loss of :

⚫ AF1-122 POI - Liberty - Marengo - Oxford - Hartford - Tangy circuit (CRD-TAN)

⚫ AF1-122

SLG Fault at AF1-122 POI on Cardington circuit (CRD-TAN) resulting in additional loss of :

⚫ AF1-122 POI - Cardington circuit (CRD-TAN)

Breaker 3 stuck. Fault cleared with loss of :

⚫ AF1-122

⚫ AF1-122 POI - Liberty circuit (CRD-TAN)

SLG Fault at Tangy 69 kV on Hartford - Oxford - Marengo - Liberty - AF1-122 circuit (CRD-TAN) resulting in additional loss of :

⚫ Liberty - AF1-122 circuit (CRD-TAN)

Breaker 166 stuck. Fault cleared with loss of :

Fault ID

P4_1B1.07

⚫ Tangy 138/69 kV Transformer #2

⚫ Tangy - Hartford - Oxford - Marengo - Liberty circuit (CRD-TAN)

SLG Fault at Tangy 69 kV on Hartford - Oxford - Marengo - Liberty - AF1-122 circuit (CRD-TAN) resulting in additional loss of :

⚫ Liberty - AF1-122 circuit (CRD-TAN)

Breaker 4 stuck. Fault cleared with loss of :

⚫ Tangy - Hartford - Oxford - Marengo - Liberty circuit (CRD-TAN)

⚫ Tangy - New California Union REC - Darby circuit (LON-TAN)

SLG Fault at Tangy 69 kV on Sciot0 - Radnor - Prospect Marion Muni - Richwood / Kirby circuit (KIR-RWD) resulting in additional loss of :

⚫ Kirby - Richwood circuit (KIR-RWD)

P4_1B1.08

P4_1B1.09

Breaker 169 stuck. Fault cleared with loss of :

⚫ Tangy 138/69 kV Transformer #2

⚫ Tangy - Sciot0 - Radnor - Prospect Marion Muni - Richwood circuit (KIR-RWD)

SLG Fault at Tangy 69 kV on Sciot0 - Radnor - Prospect Marion Muni - Richwood / Kirby circuit (KIR-RWD) resulting in additional loss of :

⚫ Kirby - Richwood circuit (KIR-RWD)

Breaker 247 stuck. Fault cleared with loss of :

⚫ Tangy 138/69 kV Transformer #1

⚫ Tangy - Sciot0 - Radnor - Prospect Marion Muni - Richwood circuit (KIR-RWD)

SLG Fault at Tangy 69 kV on New California Union REC - Darby circuit (LON-TAN) resulting in additional loss of :

AF1-122 System Impact Study Dynamic Simulation Analysis

P4_1B1.10

P4_1B1.11

⚫ No normal clearing loss

Breaker 5 stuck. Fault cleared with loss of :

⚫ Tangy 138/69 kV Transformer #1

⚫ Tangy - New California Union REC - Darby circuit (LON-TAN) 5/74

SLG Fault at Tangy 69 kV on New California Union REC - Darby circuit (LON-TAN) resulting in additional loss of :

⚫ No normal clearing loss

Breaker 4 stuck. Fault cleared with loss of :

⚫ Tangy - Hartford - Oxford - Marengo - Liberty - AF1-122 circuit (CRD-TAN) 5/74

P4_1B1.12

P4_1B1.13

⚫ Tangy - New California Union REC - Darby circuit (LON-TAN)

SLG Fault at Tangy 69 kV on Tangy 138 / 69 kV Transformer #1 resulting in additional loss of :

⚫ Tangy 138 / 69 kV Transformer #1

Breaker 169 stuck. Fault cleared with loss of :

⚫ Tangy 69 kV bus

SLG Fault at Tangy 69 kV on Tangy 138 / 69 kV Transformer #2 resulting in additional loss of :

⚫ Tangy 138 / 69 kV Transformer #2

Breaker 166 stuck. Fault cleared with loss of :

P4_1B1.14

P4_1B1.15

P4_1B1.16

P4_1B1.17

Simulation Analysis

P4_1B1.18

⚫ Tangy 69 kV bus 5/74 Stable

SLG Fault at Tangy 138 kV on Tangy 138 / 69 kV Transformer #1 resulting in additional loss of :

⚫ Tangy 138 / 69 kV Transformer #1

Breaker 238 stuck. Fault cleared with loss of :

⚫ Tangy 138 kV bus 5/20 Stable

SLG Fault at Tangy 138 kV on Tangy 138 / 69 kV Transformer #2 resulting in additional loss of :

⚫ Tangy 138 / 69 kV Transformer #2

Breaker 56 stuck. Fault cleared with loss of :

⚫ Tangy 138 kV bus 5/20 Stable

SLG Fault at Tangy 138 kV on National Mod - London circuit (LON-TAN) resulting in additional loss of :

⚫ Tangy - National Mod - London circuit (LON-TAN)

Breaker 210 stuck. Fault cleared with loss of :

⚫ Tangy 138 kV bus 6/20 Stable

SLG Fault at Tangy 138 kV on Bellepoint - Mill Creek - AD2-163 circuit (ESP-TAN) resulting in additional loss of :

⚫ Tangy - Bellepoint - Mill Creek - AD2-163 circuit (ESP-TAN)

Breaker 155 stuck. Fault cleared with loss of :

⚫ Tangy 138 kV bus 6/20 Stable

SLG Fault at Tangy 138 kV on Delaware Business Park - Crissinger circuit (CRS-TAN) resulting in additional loss of :

⚫ Tangy - Delaware Business Park - Crissinger circuit (CRS-TAN)

Breaker 2 stuck. Fault cleared with loss of :

⚫ Tangy 138 kV bus 6/20 Stable

P4_1B1.19

P4_1B1.20

SLG Fault at Tangy 138 kV on South Sciot0 - Kirby circuit (KIR-TAN) resulting in additional loss of :

⚫ Tangy - South Sciot0 - Kirby circuit (KIR-TAN)

Breaker 54 stuck. Fault cleared with loss of :

⚫ Tangy 138 kV bus

SLG Fault at Tangy 138 kV on Tangy 138 / 345 kV Transformer #3 resulting in additional loss of :

⚫ Tangy 138 / 345 kV Transformer #3

Breaker 74 stuck. Fault cleared with loss of :

⚫ Tangy 138 kV bus 5/20 Stable

SLG Fault at Tangy 138 kV on Tangy 138 / 345 kV Transformer #4 resulting in additional loss of :

P4_1B1.21

P4_1B1.22

⚫ Tangy 138 / 345 kV Transformer #4

Breaker 63 stuck. Fault cleared with loss of :

⚫ Tangy 138 kV bus 5/20 Stable

SLG Fault at Tangy 138 kV on Tangy 138 / 345 kV Transformer #5 resulting in additional loss of :

⚫ Tangy 138 / 345 kV Transformer #5

Breaker 189 stuck. Fault cleared with loss of :

⚫ Tangy 138 kV bus 5/20

SLG Fault at Tangy 345 kV on Tangy 138 / 345 kV Transformer #3 resulting in additional loss of :

P4_1B1.23

P4_1B1.24

⚫ Tangy 138 / 345 kV Transformer #3

Breaker 182 stuck. Fault cleared with loss of :

⚫ Tangy 138 / 345 kV Transformer #4 5/14

SLG Fault at Tangy 345 kV on Tangy 138 / 345 kV Transformer #3 resulting in additional loss of :

⚫ Tangy 138 / 345 kV Transformer #3

Breaker 100 stuck. Fault cleared with loss of :

⚫ Tangy - Hyatt circuit (HYA-TAN) 5/14 Stable

SLG Fault at Tangy 345 kV on Hyatt circuit (HYA-TAN) resulting in additional loss of :

P4_1B1.25

P4_1B1.26

⚫ Tangy - Hyatt circuit (HYA-TAN)

Breaker 100 stuck. Fault cleared with loss of :

⚫ Tangy 138 / 345 kV Transformer #3

SLG Fault at Tangy 345 kV on Hyatt circuit (HYA-TAN) resulting in additional loss of :

⚫ Tangy - Hyatt circuit (HYA-TAN)

Breaker 174 stuck. Fault cleared with loss of : 5/14 Stable

⚫ Tangy 138 / 345 kV Transformer #5

P4_1B1.27

P4_1B1.28

P4_1B1.29

P4_1B1.30

P4_1B1.31

P4_1B1.32

P4_1B1.33

P4_1B1.34

description

SLG Fault at Tangy 345 kV on Tangy 138 / 345 kV Transformer #5 resulting in additional loss of :

⚫ Tangy 138 / 345 kV Transformer #5

Breaker 174 stuck. Fault cleared with loss of :

⚫ Tangy - Hyatt circuit (HYA-TAN)

SLG Fault at Tangy 345 kV on Tangy 138 / 345 kV Transformer #5 resulting in additional loss of :

⚫ Tangy 138 / 345 kV Transformer #5

Breaker 191 stuck. Fault cleared with loss of :

⚫ Tangy - Marysville circuit (MRY-TAN) 5/14 Stable

SLG Fault at Tangy 345 kV on Marysville circuit (MRY-TAN) resulting in additional loss of :

⚫ Tangy - Marysville circuit (MRY-TAN)

Breaker 191 stuck. Fault cleared with loss of :

⚫ Tangy 138 / 345 kV Transformer #5 5/14

SLG Fault at Tangy 345 kV on Marysville circuit (MRY-TAN) resulting in additional loss of :

⚫ Tangy - Marysville circuit (MRY-TAN)

Breaker 81 stuck. Fault cleared with loss of :

⚫ Tangy 138 / 345 kV Transformer #4

SLG Fault at Tangy 345 kV on Tangy 138 / 345 kV Transformer #4 resulting in additional loss of :

⚫ Tangy 138 / 345 kV Transformer #4

Breaker 81 stuck. Fault cleared with loss of :

⚫ Tangy - Marysville circuit (MRY-TAN) 5/14

SLG Fault at Tangy 345 kV on Tangy 138 / 345 kV Transformer #4 resulting in additional loss of :

⚫ Tangy 138 / 345 kV Transformer #4

Breaker 182 stuck. Fault cleared with loss of :

⚫ Tangy 138 / 345 kV Transformer #3 5/14 Stable

SLG Fault at Cardington 69 kV on AF1-122 circuit (CRD-TAN) resulting in additional loss of :

⚫ Cardington - AF1-122 POI circuit (CRD-TAN)

Breaker 16 stuck. Fault cleared with loss of :

⚫ Cardington 69 kV bus 35/74 Stable

SLG Fault at Cardington 69 kV on Schaaf - Edison - Bingham circuit (CRD-GAL) resulting in additional loss of : 35/74 Stable

AF1-122 System Impact Study

Simulation Analysis

P4_1B1.35

⚫ Edison - Bingham circuit (CRD-GAL)

Breaker 20 stuck. Fault cleared with loss of :

⚫ Cardington - Schaaf - Edison circuit (CRD-GAL)

⚫ Cardington 69 kV bus

SLG Fault at Cardington 69 kV on Yutaka circuit (CRD-YUT) resulting in additional loss of :

⚫ No normal clearing

Breaker 12 stuck. Fault cleared with loss of :

⚫ Cardington - Yutaka circuit (CRD-YUT)

⚫ Cardington 69 kV bus 5/74 Stable

SLG Fault at Cardington 69 kV on Cardington 69 kV capacitor bank resulting in additional loss of :

⚫ No normal clearing

P4_1B1.36

P4_1B1.37

P4_1B1.38

Breaker 24 stuck. Fault cleared with loss of :

⚫ Cardington 69 kV bus 5/74 Stable

SLG Fault at Cardington 69 kV on Cardington 138 / 69 kV Transformer resulting in additional loss of :

⚫ Cardington - Galion circuit (CAR-GAL)

⚫ Cardington 138 / 69 kV Transformer

Breaker 8 stuck. Fault cleared with loss of :

⚫ Cardington 69 kV bus 5/74 Stable

SLG Fault at Cardington 138 kV on Cardington 138 / 69 kV Transformer resulting in additional loss of :

⚫ Cardington - Galion circuit (CAR-GAL)

Breaker 8 stuck. Fault cleared with loss of :

⚫ Cardington 69 kV bus 5/20 Stable

Table 8: Single-phase Faults with Delayed (Zone 2) Clearing due to Primary Communication/Relay Failure – Category P5

P5.01 SLG @ 80% of 69 kV line from AF1-122 POI to AF1-122 circuit. Delayed clearing at AF1-122 POI. 5/65 Stable

P5.02 SLG @ 80% of 69 kV line from AF1-122 POI to Cardington circuit (CRD-TAN). Delayed clearing at AF1-122 POI. 35/65 Stable

P5.03 SLG @ 80% of 69 kV line from AF1-122 POI to Liberty - Marengo - Oxford - Hartford - Tangy circuit (CRD-TAN). Delayed clearing at AF1-122 POI

P5.04 SLG @ 80% of 69 kV line from Tangy to Sciot0 - Radnor - Prospect Marion Muni - Richwood / Kirby circuit (KIRRWD). Delayed clearing at Tangy 69 kV.

P5.05 SLG @ 80% of 69 kV line from Tangy to New California Union REC - Darby circuit (LON-TAN). Delayed clearing at Tangy 69 kV.

P5.06 SLG @ 80% of 138 kV line from Tangy to National Mod - London circuit (LON-TAN). Delayed clearing at Tangy 138 kV. 6/65 Stable

P5.07 SLG @ 80% of 138 kV line from Tangy to Bellepoint - Mill Creek - AD2-163 circuit (ESP-TAN). Delayed clearing at Tangy 138 kV. 6/65

P5.08 SLG @ 80% of 138 kV line from Tangy to Delaware Business Park - Crissinger circuit (CRS-TAN). Delayed clearing at Tangy 138 kV

P5.09 SLG @ 80% of 138 kV line from Tangy to South Sciot0 - Kirby circuit (KIR-TAN). Delayed clearing at Tangy 138 kV 6/65

P5.10 SLG @ 80% of 345 kV line from Tangy to Marysville circuit (MRY-TAN). Delayed clearing at Tangy 345 kV 5/65 Stable

P5.11 SLG @ 80% of 345 kV line from Tangy to Hyatt circuit (HYA-TAN). Delayed clearing at Tangy 345 kV. 5/65 Stable

P5.12 SLG @ 80% of 69 kV line from Cardington to Yutaka circuit (CRD-YUT). Delayed clearing at Cardington 69 kV. 5/65

P5.13 SLG @ 80% of 69 kV line from Cardington to Schaaf - Edison - Bingham circuit (CRD-GAL). Delayed clearing at Cardington 69 kV 35/65 Stable

P5.14 SLG @ 80% of 138 kV line from Cardington to Galion circuit (CAR-GAL). Delayed clearing at Cardington 138 kV. 6/65 Stable

P7.01

P7.02

P7.03

P7.04

P7.05

AF1-122 System Impact Study Dynamic Simulation Analysis

Table 9: Single Phase Faults with Normal Clearing on Common Structure – Category P7

CONTINGENCY 'ATSI-P7-1-OES-345-68T' /* TANGY-HYATT & TANGY-MARYSVILLE COMMON TOWER

Fault at Tangy - Hyatt circuit (HYA - TAN) and Tangy - Marysville circuit (MRY - TAN), tower failure with normal clearing loss of Tangy - Hyatt circuit (HYA - TAN), Tangy - Marysville circuit (MRY - TAN), Tangy 138 / 345 kV Transformer #3, #4 and #5

CONTINGENCY 'AEP_P7-1_#468'

Fault at Tangy - Hyatt circuit (HYA - TAN) and Tangy - Marysville circuit (MRY - TAN), tower failure with normal clearing loss of Tangy - Hyatt circuit (HYA - TAN), Tangy - Marysville circuit (MRY - TAN)

CONTINGENCY 'AEP_P7-1_#466'

Fault at Tangy - Hyatt circuit (HYA - TAN) and Hyatt - Marysville circuit, tower failure with normal clearing loss of Tangy - Hyatt circuit (HYA - TAN) and Hyatt - Marysville circuit

CONTINGENCY 'AEP_P7-1_#467'

Fault at Tangy - Marysville circuit (MRY - TAN) and Hyatt - Marysville circuit, tower failure with normal clearing loss of Tangy - Marysville circuit (MRY - TAN) and Hyatt - Marysville circuit

CONTINGENCY 'ATSI-P7-1-OES-138-067A' /* TANGY-BROADVIEW & TANGY-CRISSINGER

COMMON TOWER

Fault at Tangy - Bellepoint - Mill Creek - AD2-163 circuit (ESP-TAN) and Tangy - Delaware Business Park - Crissinger circuit (CRS-TAN), tower failure with normal clearing loss of Tangy - Bellepoint - Mill Creek - AD2-163 circuit (ESP-TAN) and Tangy - Delaware Business Park - Crissinger circuit (CRSTAN)

AF1-122 System Impact Study Dynamic Simulation Analysis

9. Recommendations and Mitigations

Based on the Impact Study Data provided, AF1-122 does not meet the reactive power requirement at the high side of the facility main transformer. Reactive power compensation is required for this project. This project needs to have additional reactive power capabilities to fulfill the power factor requirement. The estimated required additional capacitive reactive power is 7.35 MVAr.

No other mitigations were found to be required for this project.

Attachment 1. Impact Study Data

Attachment 2. FE - ATSI One Line Diagram

Attachment 3. PSS/E Model One Line Diagram

AF1-122 System Impact Study Dynamic Simulation Analysis AF1-122-3-1

Attachment 4.

AF1-122

PSS/E Load Flow and Dynamic Models

1. Load Flow Model (RAW Data) /**********************************************

/*** AF1-122 - 64 MW MFO Solar PV

/*** T-Tap connection between Cardington 69 kV and Liberty 69 kV at Ohio state, Morrow County /***********************************************

BAT_PURGBRN 240609, 238606, '1'

@! "AF1-122_Purge_3wnd.idv"

BAT_PURG3WND,944571,944572,944573,'1'

BAT_BSYSINIT,1

BAT_BSYSO,1,944573

BAT_EXTR,1,0,0,0

VERSION 33

RDCH 1

944570,'AF1-122_POI ', 69.0000,1, 202,1242, 202,1.02816,24.8351,1.10000,0.90000,1.10000,0.90000 944571,'AF1-122_MAIN', 69.0000,1, 202,1242, 202,1.02713,24.5639,1.10000,0.90000,1.10000,0.90000 944572,'AF1-122_SEC ', 34.5000,1, 202,1242, 202,1.01217,47.1149,1.10000,0.90000,1.10000,0.90000 944574,'AF1-122_COL ', 34.5000,1, 202,1242, 202,1.01655,46.9211,1.10000,0.90000,1.10000,0.90000 944575,'AF1-122_GEN ', 0.3900,2, 202,1242, 202,1.02000,73.9992,1.10000,0.90000,1.10000,0.90000

0 / END OF BUS DATA, BEGIN LOAD DATA

0 / END OF LOAD DATA, BEGIN FIXED SHUNT DATA

0 / END OF FIXED SHUNT DATA, BEGIN GENERATOR DATA 944575,'1 ', 64.960, -2.109, 27.140, -27.140,1.02000, 0, 70.400, 0.00000E+0, 9.99990E+4, 0.00000E+0, 0.00000E+0,1.00000,1, 100.0, 64.960, 0.000, 202,1.0000, 0, 1.0, 0, 1.0, 0, 1.0,1, 1.0000

0 / END OF GENERATOR DATA, BEGIN BRANCH DATA

238606,944570,'1 ', 1.21100E-2, 2.91100E-2, 0.00000, 85.00, 96.00, 110.00, 0.00000, 0.00000, 0.00000, 0.00000,1,2, 0.50, 202,1.0000 240609,944570,'1 ', 1.21100E-2, 2.91100E-2, 0.00000, 80.00, 96.00, 110.00, 0.00000, 0.00000, 0.00000, 0.00000,1,1, 0.50, 202,1.0000 944570,944571,'1 ', 4.40000E-5, 7.80800E-3, 0.00001, 0.00, 0.00, 0.00, 0.00000, 0.00000, 0.00000, 0.00000,1,1, 0.20, 202,1.0000 944572,944574,'1 ', 7.28400E-3, 4.80000E-3, 0.00326, 0.00, 0.00, 0.00, 0.00000, 0.00000, 0.00000, 0.00000,1,1, 0.00, 202,1.0000

0 / END OF BRANCH DATA, BEGIN TRANSFORMER DATA 944571,944572, 0,'1 ',1,2,1, 0.00000E+00, 0.00000E+00,2,' ',1, 202,1.0000, 0,1.0000, 0,1.0000, 0,1.0000,'DY '

3.10100E-3, 8.99460E-2, 43.00

1.00000, 69.000, 30.000, 43.00, 57.00, 71.00, 0, 0, 1.10000, 0.90000, 1.10000, 0.90000, 33, 0, 0.00000, 0.00000, 0.000 1.00000, 34.500

AF1-122 System Impact Study Dynamic Simulation Analysis AF1-122-3-1

AF1-122 System Impact Study Dynamic Simulation Analysis

944574,944575, 0,'1 ',1,2,1, 0.00000E+00, 0.00000E+00,2,' ',1, 202,1.0000, 0,1.0000, 0,1.0000, 0,1.0000,'Dy1 '

7.13200E-3, 5.70500E-2, 70.40 1.00000, 34.500, 30.000, 70.40, 70.40, 70.40, 0, 0, 1.05000, 0.95000, 1.10000, 0.90000, 5, 0, 0.00000, 0.00000, 0.000 1.00000, 0.390

0 / END OF TRANSFORMER DATA, BEGIN AREA DATA

0 / END OF AREA DATA, BEGIN TWO-TERMINAL DC DATA

0 / END OF TWO-TERMINAL DC DATA, BEGIN VSC DC LINE DATA

0 / END OF VSC DC LINE DATA, BEGIN IMPEDANCE CORRECTION DATA

0 / END OF IMPEDANCE CORRECTION DATA, BEGIN MULTI-TERMINAL DC DATA

0 / END OF MULTI-TERMINAL DC DATA, BEGIN MULTI-SECTION LINE DATA

0 / END OF MULTI-SECTION LINE DATA, BEGIN ZONE DATA

0 / END OF ZONE DATA, BEGIN INTER-AREA TRANSFER DATA

0 / END OF INTER-AREA TRANSFER DATA, BEGIN OWNER DATA

0 / END OF OWNER DATA, BEGIN FACTS DEVICE DATA

0 / END OF FACTS DEVICE DATA, BEGIN SWITCHED SHUNT DATA

0 / END OF SWITCHED SHUNT DATA, BEGIN GNE DATA

0 / END OF GNE DATA, BEGIN INDUCTION MACHINE DATA

0 / END OF INDUCTION MACHINE DATA

Q

/**********************************************************************

/*** Project: AF1-122 ends

/**********************************************************************

AF1-122 System Impact Study Dynamic Simulation Analysis

2. Dynamic Model (DYR file)

/**********************************************

/*** AF1-122 - 64 MW MFO Solar PV

/*** T-Tap connection between Cardington 69 kV and Liberty 69 kV at Ohio state, Morrow County

/***********************************************

/ PSSE Version 33 / 32 X 2.2 MVA SMA SC2200 Inverters

/********************************************************************************

944575, 'USRMDL', 1, 'REGCAU1', 101, 1, 1, 14, 3, 4 0

10

944575, 'USRMDL', 1, 'REECAU1', 102, 0, 6, 45, 6, 9 0 0 1 0 0 0

944575, 'USRMDL', 1, 'REPCAU1', 107, 0, 7, 27, 7, 9, 944570 944571 944570 '1' 0 1 0 0.0400 0.0000 0.5000 0.0000

94457501 'VTGTPAT' 944575 944575 1

1.11 1.000 0.01/ 94457502 'VTGTPAT' 944575 944575 1

94457503 'VTGTPAT' 944575 944575 1

94457504 'VTGTPAT' 944575 944575 1

94457505 'VTGTPAT' 944575 944575 1 -0.10 2.00 10.00 0.01/

AF1-122-3-1

94457506 'VTGTPAT' 944575 944575 1

0.89 1.80 3.000 0.01/

94457507 'VTGTPAT' 944575 944575 1

0.75 1.80 2.000 0.01/

94457508 'VTGTPAT' 944575 944575 1

0.65 1.80 0.600 0.01/

94457509 'VTGTPAT' 944575 944575 1

1.80 0.600 0.01/

94457510 'VTGTPAT' 944575 944575 1 0.00 1.80 10.00 0.01/

94457511 'FRQTPAT' 944575 944575 1 40.0 60.62 180.0 0.01/

94457512 'FRQTPAT' 944575 944575 1 40.0 61.6 30.00 0.01/

94457513 'FRQTPAT' 944575 944575 1 40.0 61.7 0.001 0.01/

94457514 'FRQTPAT' 944575 944575 1

40.0 65.0 10.00 0.01/

94457515 'FRQTPAT' 944575 944575 1 40.0 65.0 10.00 0.01/

94457516 'FRQTPAT' 944575 944575 1

40.0 65.0 0.001 0.01/

94457517 'FRQTPAT' 944575 944575 1

59.38 80.0 180.0 0.01/

94457518 'FRQTPAT' 944575 944575 1

58.4 80.0 300.0 0.01/

94457519 'FRQTPAT' 944575 944575 1

57.8 80.0 7.500 0.01/

94457520 'FRQTPAT' 944575 944575 1

57.3 80.0 0.750 0.01/

94457521 'FRQTPAT' 944575 944575 1

55.0 80.0 0.001 0.01/

94457522 'FRQTPAT' 944575 944575 1

AF1-122 System Impact Study Dynamic Simulation Analysis AF1-122-3-1

55.0 80.0 0.001 0.01/

/**********************************************************************

/*** Project: AF1-122 ends

/**********************************************************************

AF1-122 System Impact Study Dynamic Simulation Analysis

AF1-122-3-1

Attachment 5. AF1-122 PSS/E Case Dispatch

AF1-122 System Impact Study Dynamic Simulation Analysis AF1-122-3-1

AF1-122 System Impact Study Dynamic Simulation Analysis

Attachment 6. Plots from Dynamic Simulations

AF1-122-3-1

Interconnection Reports

AF1-122 Facilities Study Fee Receipt

BancFirst Bank

Outgoing Wire ‐ Advice of Debit

Date 08/28/2020

Wire Create Time (PST): 0721

Account #: ******4053

Name: CLEAN PLANET RENEWABLE ENERGY LLC

Amount : $100,000.00

GFX Reference: 20202410014500

Beneficiary Bank: PNCBANK NJ 031207607

Beneficiary: ****589826

PJM INTERCONNECTION

N/A

N/A

Beneficiary Info (OBI): CROSSROADS SOLAR I, LLC ‐ AF1‐122

FACILITIES STUDY DEPOSIT

Bank to Bank Info (BBI):

Reference for Beneficiary (RFB):

Other Info:

Fed Reference Number

IMAD: 20200828L1LFBS8C000051

OMAD: 20200828MMQFMPNP00069708281021FT03

Fees will be charged as per respective fee schedules.

This message is for the sole use of the intended recipient, and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient, please contact the sender by phone or fax and destroy all copies of the original message.

Please do not respond to this email address as it is an unmonitored mailbox.

Interconnection Reports

AF1-122 Facilities Study Report

January2023

Preface

TheintentoftheFacilityStudyistodetermineaplan,withapproximatecostandconstructiontimeestimates, toconnectthesubjectgenerationinterconnectionprojecttothePJMnetworkatalocationspecifiedbythe InterconnectionCustomer.Asarequirementforinterconnection,theInterconnectionCustomermaybe responsibleforthecostofconstructing:NetworkUpgrades,whicharefacilityadditions,orupgradestoexisting facilities,thatareneededtomaintainthereliabilityofthePJMsystem.Allfacilitiesrequiredforinterconnection ofagenerationinterconnectionprojectmustbedesignedtomeetthetechnicalspecifications(onPJMwebsite) fortheappropriatetransmissionowner.

Insomeinstances,anInterconnectionCustomermaynotberesponsiblefor100%oftheidentifiednetwork upgradecostbecauseothertransmissionnetworkuses,e.g.anothergenerationinterconnectionormerchant transmissionupgrade,mayalsocontributetotheneedforthesamenetworkreinforcement.

TheFacilityStudyestimatesattempttoidentifytheestimatedtimerequiredtoobtainpropertyrightsandpermits forconstructionoftherequiredfacilities.TheprojectICisresponsiblefortheright-of-way,realestate,and constructionpermitissues.ForpropertiescurrentlyownedbyTransmissionOwners,thecostsmaybeincluded inthestudy.

A.TransmissionOwnerFacilitiesStudySummary

1.DescriptionofProject

CrossroadsSolarI,LLC

MorrowCounty,Ohio.TheinstalledfacilitiesforAF1-122willhaveatotalcapabilityof64MWwith26.88 MWofthisoutputbeingrecognizedbyPJMascapacity.ThegenerationfacilitywillinterconnectwithAmerican TransmissionSystems,Inc.(ATSI)ofOhioEdison(OE),aFirstEnergyCompany(FE),hereafterreferredtoas -breakerringbussubstationtappedoffofthe Cardington-Tangy69kVtransmissionlinebetweenCardingtonandLiberty.

2.AmendmentstotheSystemImpactStudyorSystemImpactStudyResults

SincetheSystemImpactStudypostedAugust2020,thetitleoftheAF1-122GenerationInterconnection

OperationDate(COD)forthegenerationfacilityisMarch31,2026.

MilestoneSchedule:

10/15/25InitialBack-feedthroughProjectSubstationDate 03/31/26ProjectCommercialOperationDate

ICisresponsibleforalldesignandconstructionrelatedtoactivitiesontheirsideofthePointofInterconnection (POI).Thisincludes,butisnotlimitedto,thegenerationstep-up(GSU)transformer,69kV(AF1-122)generator leadlineandconnectiontothenew69kV3breakerringbusinterconnectionsubstation.

PointofInterconnection(POI):ThePOIwillbelocatedwithinthenew69kVringbusinterconnection substationwhereIC-owned69kVattachmentlineconductorwillterminateontheinsulatorsonthedeadend takeoffstructureandwillbedefinedasthePOI.

ICisrequiredtoown,install,andmaintainafullyrated,fault-interruptingcircuitbreakeronthehigh-sideofthe GSUtransformer,aswellasthenecessaryrevenuemeteringequipment.Therevenuemeteringcurrentand voltagetransformersshallbeinstalledonthehighvoltagesideoftheGSU,onthegenerationsideofthefaultinterruptingdevice,andwithinthelocalzoneoffaultprotectionforthefacility.Theprotectiverelayingand

TheeasementsandassociatedrightsofwayfortheTOownedsubstationalongwiththe69kVlinetapstothe substationwillbeacquiredbytheICandtransferredtotheTOatnocost.SitepreparationfortheTOown substationincludingclearing,gradingandanaccessroad,asnecessary,isassumedtobebytheIC.Theaccess roaddesignmustbeapprovedbyFirstEnergytoensureitprovidesadequateaccesstothesubstationtosupport constructionandmaintenanceactivities.Routeselection,linedesign,andrightfacilitiesarenotincludedinthisreportandaretheresponsibilityoftheIC.

Assumptions/Notes:

ICwillcoordinatedesignandalignmentofproposed69kVgeneratorleadlinewiththeTransmission Ownerforreviewofanyclearance,right-of-wayorright-of-wayencroachmentissueswithTOowned facilities.

ICwillcoordinatedesignandconstructionofproposed69kVLeadLine.Fortheseareas,theICshall provideTOwithproposeddrawingspriortoconstructionandas-builtdrawings,confirmedbyas-built surveydatapost-construction.

renceandavoidtransmissionlinecrossings withnew69kVterminalpositions.Asaminimum,ICfacilitiesshouldnotencroachwithin100feet

wouldneedtoreviewthisareaasaspecialexception.

AdditionalcostswillbeincurredbytheIC,iffinalalignmentofthe69kVgeneratorleadlinecauses encroachments,changes,ormodificationstoanyexistingorrelocatedTOfacilities.

ICisresponsibletomakeallarrangementsforelectricdistributionservice(ifrequired)forits generationstation.Nocostsorscheduleincludedherein.

TheICwillberequiredtoinstallatransformerwithadeltalowsidewindingandawyegrounded windingonthe69kVside.

5.DescriptionofFacilitiesIncludedintheFacilitiesStudy

AttachmentFacilities

TransmissionOwnerwilldesign,furnishandconstructthenew69kVlineterminalandtakeoffstructure.This workwillinclude,butnotbelimitedto,installationofa69kVlineexittake-offstructure,foundations, disconnectswitchandassociatedequipmenttoaccommodatetheterminationofthegeneratorleadline.

DirectConnection

AF1-122InterconnectionSubstation

Anew69kVthreebreakerringbussubstationwillbeconstructedalongtheCardingtonTangy69kV transmissionlinetointerconnecttheAF1-122solarprojectwiththeATSItransmissionsystem.ThePOIwill beattheTO-owneddeadendstructureinsidethesubstationyardwherethegeneratorleadlineterminates.

Non-DirectConnection

CardingtontoTangy69kVline

TheCardingtontoTangy69kVlinewillbecutandloopedintotheinterconnectionsubstation.Thiscutwill takeplaceatalocationthatisapproximately1.1milesfromtheCardingtonsubstation.Itisassumedthatthe newinterconnectionsubstationwillbelocatedwithinonespan(approximately300feet)fromtheexistingline.

TangySubstation

Relaysettings,oneline,andnameplateswillberevised.

CardingtonSubstation

TheexistinglinerelayingandcontrolpanelfortheTangylineexitwillbereplacedwithastandardprewired relayingpanel,andfiberfromtheAF1-122deadendwillbeinstalled.

AF1-122CustomerSubstation

Drawings,nameplates,andrelaysettingswillbereviewed.Revenuemeteringwillbeinstalled.

6.TotalCostofTransmissionOwnerFacilitiesIncludedintheFacilitiesStudy

7.SummaryoftheScheduleforCompletionofWorkfortheFacilitiesStudy

B.TransmissionOwnerFacilitiesStudyResults

Thissectiondescribesfacilitiesidentifiedtobeinstalled(attachmentfacilities),replaced,and/orupgraded (upgradefacilities)byFirstEnergytoaccommodatetheproject.Duringdetaileddesignandanalysisother componentsmaybeidentifiedforinstallationorreplacementduetothisinterconnection.

1.TransmissionLinesNew

2.TransmissionLinesUpgrade

Cardington-Tangy69kVLine

DescriptionofWork

oLooptheCardington-Tangy69kVlinetocreatetheinterconnectionforthenewAF1-1223breakerringbus,approximately1.1milesfromtheCardingtonsubstation.Installfiberfromthe newAF1-1223-breakerringbustotheCardingtonsubstation.

ExistingConditions

oTheexistinglineisconstructedonsinglecircuitwoodmonopolestructures.PerGISView, existingconductoris2/0ACSRshieldedby(1)80mcmACSR.

StructuresInstalled

o(1)69kVdoublecircuitwood2-poleloopstructure(TR-069419)

o0.1milesof336.4kcmil26/7ACSRconductor

o0.1milesof7#8Alumoweldshieldwiretobeinstalledontheinterconnectiontowardsthe Tangysubstation.o

o1.1milesofOPGWtobeinstalledfromthenewAF1-1223-breakerringbustothe Cardingtonsubstation

Install(13)OPGWsuspensionclamps

Install(8)OPGWdeadendclamps

oTransfertheexistingconductortobothpolesofthenewstructureandtheexistingshieldwire tothesouthernofthe(2)poles.

Itisassumedtheexistingshieldwireandconductorareingoodconditionandcanbe transferredtothenewstructure.

StructuresRemoved

o(1)69kVsinglecircuitwoodmonopoletangentstructure(Structure22PerTAMI)

oRemove1.1milesofexistingshieldwire.

Remove(14)existingshieldwiresuspensionclamps

Remove(6)existingshieldwiredeadendclamps

ConstructionConsiderations

oDuetolinevoltageandprojectlocation,nositingisrequired.

oTheOPGWreplacementportionoftheprojectcrossesWaldoFulton-ChestervilleRdandthen parallelsitforapproximately0.3miles.Trafficcontrolwillberequired.

oTheOPGWreplacementportionoftheprojectcrossestheColumbusLineSubdivisionRail andthenparallelsitforapproximately0.6miles.Flaggingwillberequired.

oAssumethenecessaryoutagecanbetakenontheline. Siting/Licensing

oAssumeminimalecologicalimpact.

oThelinecrossesrailroads(1)time.Flaggingwillberequired. Assumptions

oAssumeanaerialLiDARsurveywillberequired.

oAssumeOPGWwillbeutilizedfortheFiberpathbetweenthenewringbusandCardington substation.

oAssumetheexistingstructurescanhandlethechangeinloadingfromtheOPGWreplacement. Anengineeringanalysiswillberequiredtoconfirm.

Duringdetailedengineeringifthestructuresarenotabletoprovideenoughcapacity fortheOPGWthenanADSSunderbuildmayneedtobeconsidered.

oAssumetheadjacentstructurestothenewlyinstalledstructurescanhandlethenewloading. Anengineeringanalysiswillberequired.

oThelocationoftheringbusisassumed.Thefinallocationoftheringbusmayhaveimpacton thescheduleandcosts.

AncillaryLineEstimates

oPROJECTMANAGEMENT(PM)

Projectmanagementwillberequiredforthisasset.

oFORESTRY

Someclearingmayberequired.Prioritytreerightsmaybeexpanded.

oRE/ROW

AssumeallworkwillbeperformedwithintheexistingROWandnonewROWwill berequired.

ExistingEasementswillbeneedtobemodifiedforthenewloopterminations. Additionalguyingrightsmayneedtobeacquiredforthenewloopstructure. ArightsandrestrictionsreviewbyRealEstatewillberequired.

GeoreferencedROWextentswillberequiredtobeprovidedtoengineering.The linecrossesrailroads(1)time.Flaggingwillberequired.

oENVIRONMENTAL

Anenvironmentalreviewwillberequiredtoidentifyanyconstructionconstraintsand additionalpermittingrequirements.

oREVENUEMETERING

None

oIT/NETWORK

FIBER(RELAYINGANDCOMMUNICATION)

Install1.1milesofOPGW.OPGWtobeconfirmedpriortodetailed engineering.

oThestandardOPGWisheavierthantheexistingSW,soanonstandard OPGWmayberequirediftheintentistoreusetheexistingstructures.If thestandardOPGWisneeded,thenadditionalstructureswilllikelyneed tobereplacedoranADSSalternativewillneedtobeconsidered.

SCADA

None

oACCESSROADCONSTRUCTION

Accessroadwillberequiredtoinstallthenewloopstructure,removetheexisting shieldwire,andinstallthenewOPGW,approximately0.8milestotal.Terrainis mostlyflat.

ItisassumedthattheexistingWaldoFulton-ChestervilleRdcanbeutilizedfor approximately0.3miles.Trafficcontrolwillberequired.

oDISTRIBUTION

Distributionispresentontheexistingline.Thiswillhavetobetransferredto thenewstructureso

oTESTING&COMMISSIONING(TSCS)

TestingandCommissioningwillberequired

3.NewSubstation/SwitchyardFacilities

AF1-122RingBus

BelowGrade

oGroundgrid,stone,fence,andtrenchfornewringbus.

oFoundations,conduit,andgroundingfornewequipmentandstructures.

oConduitfromAF1-122andCardingtondeadendstocontrolbuildingforfiber.

AboveGrade

oInstall(1)prefabricatedcontrolbuilding.

oInstall(3)69kVcircuitbreakers.

oInstall(6)69kV,2000A,manualdisconnectswitches.

oInstall(3)69kV,1200A,lineMOABs.

oInstall(9)69kVCVTs.

oInstall(9)69kVclasssurgearresters.

oInstall(2)69kVSSVTs.

oInstall(1)lotofbus,conductor,supportstructures,insulators,connectors.

oEquipmentandconductormustexceed96MVASSTE R&C

oInstall(2)FEstandardtransmissionlinerelayingpanelsincludingdualSEL411Lrelayingfor linestoCardingtonandCustomerSubstation.

oInstall(1)FEStandardtransmissionlinerelayingpanelincludingdualSEL421relayingforthe linetoTangySubstation.

oInstall(3)FEstandardbreakercontrolpanelswith(1)SEL-501BFTand(1)SATECmeter.

oInstall(1)fiberterminationrack.

oInstall(1)SCADARTU,HMIpanel,RTACandotherstandardcommunicationequipment. AdditionalEquipmenttobeRemoved

oNone Assumptions

oDeveloperwillprovideroughgradedsiteandaccessroad.

oStationback-upACwillnotcomefromalocaldistributionline.

oCustomersubstationwillbeadjacenttothissubstation,soconnectionwillbemadeusingrigid bus.

AncillarySubstationEstimates

oPROJECTMANAGEMENT(PM)

oFORESTRY

Projectmanagementwillberequiredforthisasset.

oRE/ROW

None

None

oENVIRONMENTAL

Noneo

oREVENUEMETERING

None

oIT/NETWORK

FIBER(RELAYINGANDCOMMUNICATION)

SupportasrequiredtocustomersubstationandCardington

SCADA

NewSCADARTUandotherequipment

AddsubstationtoEMSscreen

oTESTING&COMMISSIONING(TSCS)

Commissiongreen-field69kV3-breakerringbus.

AF1-122CustomerSubstation

BelowGrade

oNone

AboveGrade

oReviewdrawings,nameplates,andrelaysettings.

oAddtoHVcircuitdiagram.

R&C

oNone

AdditionalEquipmenttobeRemoved

oNone Assumptions

oNone

AncillarySubstationEstimates

oPROJECTMANAGEMENT(PM)

oFORESTRY

oRE/ROW

Projectmanagementwillberequiredforthisasset.

None

None

oENVIRONMENTAL

None

oREVENUEMETERING

oIT/NETWORK

LocatedatcustomersubstationforPJMinterconnection.

FIBER(RELAYINGANDCOMMUNICATION)

None

SCADA

AddsubstationtoEMSscreen.

4.Substation/SwitchyardFacilityUpgrades

Cardington

BelowGrade

oConduitforfiberfromAF1-122linedeadendtocontrolbuilding.

AboveGrade

oNone

R&C

oReplaceexistingrelayingwith(1)FEstandardtransmissionlinerelayingpanelincludingdual SEL411L&SEL501BFrelayingforexistingTangyterminal.

oInstallfiberterminationrack.

AdditionalEquipmenttobeRemoved

oNone

Assumptions

oControlbuildinghasadequatespacefornewcontrolbuilding.

oSCADARTUandDCsystemareadequate.

AncillarySubstationEstimates

oPROJECTMANAGEMENT(PM)

oFORESTRY

oRE/ROW

Projectmanagementwillberequiredforthisasset.

None

None

oENVIRONMENTAL

None

oREVENUEMETERING

oIT/NETWORK

None.

FIBER(RELAYINGANDCOMMUNICATION)

SupportasrequiredforfiberconnectiontoAF1-122.

SCADA

None.

oTEST&COMISSIONING(TSCS) Commissionnew69kVlineprotectionpanel.

Tangy

BelowGrade

oNone

AboveGrade

oNone

R&C

oUpdaterelaysettings.

oOnelineandnameplatechangesforlinenamechange.

AdditionalEquipmenttobeRemoved

oNone

Assumptions

oDualSEL-421linerelayingexistsatTangyandisadequateforthisproject.

AncillarySubstationEstimates

oPROJECTMANAGEMENT(PM) Projectmanagementwillberequiredforthisasset.

oFORESTRY

oRE/ROW

None

None

oENVIRONMENTAL

None

oREVENUEMETERING

None.

oIT/NETWORK FIBER(RELAYINGANDCOMMUNICATION)

None. SCADA

None.

5.TelecommunicationsFacilitiesUpgrades

ICwilldesign,provide,install,ownandmaintainafiber-opticcommunicationscablebetweenthenew -opticchannelsare requiredforeachgeneratorprotectionschemetoobtainhigh-speedtrippingcapabilityforanyfaultwithinthe zoneofprotection.Shouldsubsequent/additionalPJMstudiesindicatethatstabilityissuesexist,theprimary andbackuprelayfiber-opticcommunicationchannelsmustbeinseparately-routedcablepathsandadditional fiber-opticconnectioncostswouldapply(notincludedherein).

TheICwillmakethefiberhouse.

TransmissionOwnerwillmakethefiberterminationconnectionsforitscable(s)attheinterconnection substationcontrolhouse.ICisresponsibleforobtainingandmaintainingallassociatedRights-of-Way(ROW), Easements,andPermitsforitsfibercable.

6.Metering&Communications

ICshallinstall,own,operate,testandmaintainthenecessaryrevenuemeteringequipment.ICshallprovide TransmissionOwnerwithdial-upcommunicationtotherevenuemeter.

Therevenuemeteringsystem(particularlytherevenuemeteringcurrenttransformers)shallbedesignedto accuratelymeterthelightloadsthatwilloccurwhenthefacilityisnotgeneratingpowerandonlybackfeeding stationservicefromtheTransmissionOwner.Thismayrequiretheuseofhighaccuracyextendedrangecurrent transformers.

RequirementsforTransmission

ConnectedFacilitiesdocumentlocatedatthefollowinglinks:

www.firstenergycorp.com/feconnect

www.pjm.com/planning/design-engineering/to-tech-standards.aspx

TheserequirementsareinadditiontoanymeteringrequiredbyPJM.

TransmissionOwnerwillobtainreal-time,site-specific,generationdatafromPJM,viatherequired communicationlinkfromICtoPJM.TransmissionOwnerwillworkwithPJMandICtoensurethegeneration dataprovidedtoPJMmeetsTransmissionOwner'srequirements.

Communicationsfortransmissionlineprotectionbetweenthenewinterconnection generation

7.Environmental,RealEstateandPermitting

Thefollowingarepossibleenvironmental,realestateandpermittingissues: Thefollowingarepossibleenvironmental,realestateandpermittingissues:

Environmentalpermitting,RealEstateacquisition,andOhioPowerSitingBoard(OPSB)notifications vary,someuptotwelve(12)monthsafterpreliminaryengineeringiscompletedtosecuretherequired approvals

PriortoagreementbyICtopurchasetheproperty,aPhase1EnvironmentalAssessmentshouldbe conductedfortheentiresitetoavoidassumptionofenvironmentalliabilitiesbyICorTransmission Owner.

TheTransmissionOwnerinterconnectionsubstationmayinvolveenvironmentalsurveys,permits, approvalsandplanswithfederal,state,and/orlocalagencies.

AssumedICistoprovideallaccessrights,easements,ROWandpermitsnecessarytocompletethe ProjecttothesatisfactionofTransmissionOwner.Environmentalpermittingshallencompassall federal,stateandlocalrequirements,consultationsandagencycoordination.Confirmationofmeeting allpermittingrequirementsshallbeprovidedtoTransmissionOwner,priortostartofconstruction. Followingconstructionandenergization,confirmationofpermitcloseoutshallbeprovidedtothe satisfactionofTransmissionOwner,priortotransferofownership.Ifanyoftheseelementsarenot includedinthefinalagreementbetweenTransmissionOwnerandIC,twelve(12)-to-eighteen(18) monthsshouldbeaddedtotheProjectScheduletosecurenecessarypermits,andadditionalcosts wouldapply.

ICwillprovidecopiesofalloftherelativeenvironmentalpermitsandothernecessaryapprovalsto TransmissionOwnerbeforeTransmissionOwneracceptstheinterconnectionfacilities.

ICisrequiredtoinstallanaccessroadfromthenewinterconnectionsubstationtothenearestpublic road(mustbeapprovedbyTransmissionOwner),andobtainaccessrightsfor TransmissionOwner.ICisresponsibleformaintainingtheaccessroadandensuringunimpededaccess forTransmissionOwneratalltimes.

ICisresponsibleforallpropertyacquisition(includingeasements/rights-of-way(ROW))for transmission,distributionandcommunicationfacilitiesneededforthegeneratorinterconnection.

IfICownstheprojectproperty,infeetitle,TransmissionOwnerwillrequireafeepropertytransferfor theinterconnectionsubstationsitewhichmayrequiresubdivisionapproval,togetherwithpermanent accessrightstoandfromthesubstation,aswellasaperpetualeasementforanytransmissionlinesto thesubstation.ICisresponsibleforallcosts,includingbutnotlimitedtosubdivision,associatedwith thepropertytransfer.

IfICleasestheprojectproperty,theICwillberequiredtoobtainfeepropertyfromtheunderlyingfee propertyowner,onbehalfofTransmissionOwner,fortheinterconnectionsubstationsite,together withpermanentaccessrightstoandfromthesubstation,aswellasaperpetualeasementforany transmissionlinestothesubstation.

Allpropertyrightsmustbesurveyedandmetesandboundsdescriptionspreparedforincorporation

TheTransmissionOwnerinterconnectionsubstationandtransmissionlineloopwillinvolveOhio PowerSitingBoard(OPSB)notification/approval.

Allworkoccurswithinanexistingtransmissionlineright-ofexistingstructurespossibleviathatpropertyandtheright-of-wayfollowingestablishedaccessroutes thatdonotcrosswetlandsorstreams.

ICwilldevelop,andsecureregulatoryapprovalfor,allnecessaryErosionandSedimentControl (E&SC)plansandNationalPollutantDischargeEliminationSystem(NPDES)permitswithintheir scopeofwork.

ICwillobtainallnecessarypermitswithintheirscopeofwork.ICwillnotberesponsiblefor ICwillconductallnecessarywetlandsandwaterwaysstudiesandpermitswithintheirscopeofwork. ICwillnotberesponsibl

ICwillconductallnecessaryhistoricalandarchaeologicalstudieswithintheirscopeofwork.ICwill notberesponsibleforhistoricalandarchaeologicalstudiesofworkthatisi complete.

IftheICplanstocrossthetransmissionlinerightofwaywithfacilitiesoraccessroads,pleasereferto theTransmissionRights-of-WayRestrictionsinformationlocatedat: https://www.firstenergycorp.com/help/safety/real-estate-power-lines/transmission-rightofway.html#ROWform

8.SummaryofResultsofStudy

Thefollowingtableprovidesabreakdownofthecostsaccordingtothedescriptionofworkrequiredto accommodatetherequestedinterconnection.Theestimatedcostsarein2020dollars.Thiscostexcludes aFederalIncomeTaxGrossUpcharges(CIAC(ContributioninAidofConstruction)).Thistaxmay ormaynotbechargedbasedonwhetherthisprojectmeetsallqualificationsandrequirementsasset forthinSection118(a)and118(b)oftheInternalRevenueCodeof1986,asamendedandinterpreted byNotice2016-36,2016- atafuturedateitisdetermined thattheFederalIncomeTaxGrosschargeisrequired,theTransmissionOwnershallbereimbursedby theInterconnectionCustomerforsuchtaxes.

AF1-122GeneratorLead Termination:Installationofa69 kVlineexittake-offstructure, foundations,disconnectswitchand associatedequipmentto accommodatetheterminationofthe 69kVgen.leadline.

$379,620.31$168,463.35$112,717.82$61,340.68$722,142.16

AF1-122Interconnect:Constructa new69kV3breakerringbuson theCardington-Tangy69kVline (n8221.1). $3,036,962.49$1,347,706.77$901,742.56$490,725.46$5,777,137.28

Design,install,and test/commissionMPLSEquipment forSCADAtransport(n8221.2).

AF1-122:Loopthe CardingtonTangy69kVlineto createtheinterconnectionforthe newAF1-1223-breakerringbus, approximately1.1milesfromthe Cardingtonsubstation.Installfiber fromthenewAF1-1223-breaker ringbustotheCardington substation(n8221.3).

Tangy:RelaySettingsChanges, DrawingUpdates,andNameplates (n8221.4).

Cardington:Upgradelinerelaying (n8221.5).

$831,614.00$47,226.49$246,924.92$18,456.11$1,144,221.53

AF1-122Customer:Customer SubstationReview.

$48,433.35$0$14,380.95$0$62,814.30

$386,203.83$42,298.36$114,672.61$16,530.20$559,705.00

FirstEnergyreservestherighttochargetheInterconnectionCustomeroperationandmaintenanceexpenses tomaintaintheInterconnectionCustomerattachmentfacilities,includingmeteringfacilities,ownedby FirstEnergy.

9.SchedulesandAssumptions

Aproposedtwenty-seven(27)monthDirectConnectionscheduleisestimatedtocompletethe engineering,constructionandtheassociatedactivities,fromthedateofafullyexecutedInterconnection ConstructionServiceAgreement(CSA)andConstructionKick-OffMeeting.Thisscheduleassumesthat

resolved,andoutages(typicallynotgrantedfromJunethroughSeptember)willoccurasplanned. Constructioncannotbeginuntilafterallapplicablepermitsand/oreasementshavebeenobtained.

27monthSchedule

FEwillneedtoconductanenvironmentalsurveyfortheloopandproposedinterconnectsubstation.If permitsarenecessarytocompletetheproject,approximately3-6monthswillbeneededtodraftandreceive agencyapprovals.

Attachment#1:ProtectionStudy

ShortCircuitAnalysis

ShortCircuitValues

Thepreliminary69kVfaultvaluesattheAF1-122interconnectionlocationare:

Threephase=7.2kA

Singlelinetoground=6.8kA

Z1=(2.958+j10.837)%

Z0=(2.871+j13.076)%

Thesevaluesareprovidedforbolted,symmetricalfaultsunderanticipatednormalsystemconditions andareprovidedona71.07kV,100MVAbase.Futureincreasesinfaultcurrentsarepossibleanditisthe ilitytoupgradetheirequipmentand/orprotectiveequipmentcoordinationwhen necessary.

ProtectionRequirements

TheAF1-122facilityshallconsistof64MWsolarinterconnectiontotheCardington-Tangy69kVline. Constructa69kV3-breakerringbusbyloopinginCardington-Tangy69kVLineintonewgeneration interconnectionsubstationusing336ACSR26/7

Thedeveloperwillneedtoprovideinformationontheinvertersandshowthattheymeetthe requirementsofUL1741certificationforanti-islandingprotection.Anynecessaryintertiefunctionswill beincorporatedintothelinerelayingatthecustomerterminaloftheinterconnectingline.Thecustomer willnotsupplyfaultcurrenttotheFEsystem.

ScopeandcostestimatessuppliedassumethatthattheAF1-122facilitywillmeettherequirementsas statedabove,butdocumentationmustbesuppliedtoFirstEnergytoverifyinvertersmeetthesestandards.

AF1-12269kVStation

Main69/34.5kVTransformer

Theinterconnecting69-34.5kVtransformershallhaveadeltaorungroundedwyewindingonthe transmission(69kV)sideofthetransformer One69kV,three69/34.5kVdelta/wyegroundedtransformer. Thecircuitbreakershallbefullyratedtointerruptavailablefaultcurrentwhencalculatedaccording tothelatestANSIstandard.

oBypassswitchesshallNOTbeinstalledacrossthebreaker.Ifthecustomerdesiredthe addedreliabilitybenefitofbeingabletokeepthesubstationenergizedwhileperforming breakermaintenance,aringbusordedicatedsparingcircuitbreakerisrequired.

oIfthecircuitbreakerusesgasasaninterruptingmedium,thedeviceshallbeequipped withalowgaspressurealarming/tripping/lockoutscheme(asappropriateforthe particulardevice)inordertominimizethepossibilityofatransmissionfaultresultingfrom alossofinsulatinggas.

Theinterconnectingtransformerandall69kVfacilitiesatthecustomersubstationshallhave redundant,high-speedprotectioninclusiveofthe69kVbreakerandhigh-sidemeteringandshall trip,atminimum,thisbreaker.SeparateCTsandtrippingpathsarerequiredbetweentheprimary andbackuprelaying.

oOverallTransformerDifferentialProtectionRelayminimumfunctions:87OA.(FE standarddeviceisSEL-587orSEL-487E)

The69kVsourceforoveralltransformerdifferentialprotectionshallbeCTson theutilitysourcesideofthetransformerbreaker.Thelowsidesourceforprimary differentialprotectionshallbeCTsonthebussideofthelowsidetransformer breaker

SeparateTrippingpathsarerequiredforPrimaryandBackupdifferentialrelay.

oPrimaryTransformerDifferentialProtectiveRelay-minimumfunctions:87T.(FEstandard deviceisSEL-587orSEL-487E)

The69kVsourceforprimarytransformerdifferentialprotectionshallbeCTson theutilitysourcesideofthetransformerortransformerbreakerseparatefromthe overalldifferentialrelay.Thelowsidesourceforprimarydifferentialprotection shallbeCTsonthebussideofthelowsidetransformerbreakerseparatefromthe overalldifferentialrelay

SeparateTrippingpathsarerequiredforPrimaryandBackupdifferentialrelay

oBreakerFailure(BF)RelayDedicatedbreakerfailurerelaywithassociatedhand-reset lockoutrelay(LOR).WillbewiredtotripthetransformerlowsidebreakerandsendDTT totheringbustoisolatefromthetransmissionsystemifthereisafailuretotripoperation. (FEstandarddeviceisSEL-501).

Directtransfertripforbreakerfailure,anti-islanding,andotherfunctionsas neededshallbecommunicatedviafiberusingtheassociatedSEL-411Lprimary andbackuprelays.Triponlossofchanneltoboththeprimaryandbackup schemes.

shalluseC800relayaccuracyCTs.TheseCTsshouldnotsaturateforthemaximumthroughfault currentthatcanbeexperiencedbytherelayforthetapratioinuse.

Therelayingsystemshallhaveareliablesourceofpowerindependentfromorimmuneto disturbances/lossoftheACsystem(e.g.DCbatteryandcharger)toensureproperoperationofthe protectionschemesandtrippingofthecircuitbreakers.

responsibilitytoinstallanddesigntheirrelayingtoensureadequateprotectionoftheirequipment. Detailedone-linediagramswithproposedprotectionshouldbeprovidedwellinadvanceofdesign andengineeringtoallowforapprovaloftheprotectionschemeandpreliminarilyvalidate coordinationwithFEsystem.

Thelow-sideofthetransformershallhaveadedicatedcircuitbreakerwithCTsadequateforuse with,atminimum,thetransformerdifferentialrelaying.

69kVLineandIntertieRelaying

ThelinebetweenRingBusandAF1-122stationwillrequireredundantfiberopticbased communicationschannelstobeinstalledandmaintainedbetweenthefacilitiesforusewithhighspeed

linecurrentdifferentialprotection.(Note:Thefiberopticforthegenerationtielineisinstalledand maintainedbytheinterconnectioncustomer)

oSeparateprimaryandbackupSEL-411LrelaysattheAF1-122stationwillberequired.Separate primaryandbackupSEL-411LrelayswillalsoberequiredatRingbustotheinterconnection facilityAF1-122.

oIntertierelayfunctionality(e.g.overfrequency,underfrequency,phaseandgroundovervoltage, directionalovercurrent,anddirectionalpower)willbeincorporatedintotheSEL-411Lline relayingatAF1-122asnecessary.

oThesourceCTsforthelinecurrentdifferentialrelaysatthecustomerstationshallbeseparate setsof1200:5CTs(C800orbetter).Theseshallbelocatedinthetransformersidebushingsof -sidebreakers

Lineandtransformerzonesofprotectionoverlapthroughthebreaker.

oTheprimarySEL-411LrelaysshallbesourcedfromaninnersetofCTsandthebackup SEL-411LrelayssourcedfromanoutersetofCTsonthetransformersideofthe -sidebreakersuchthatthebackupSEL-411Lschemeencompassesthe primary.

oPTswithseparatesecondarywindingsonthehigh/transmission-sideoftheinterconnecting transformer.

oSeparateTrippingpathsarerequiredforprimaryandbackup69KVlinerelays.

Thegeneratorowner(GO)istodesigntheirprotectivesystemtoclearanyfaultwithintheirzonesof protectionwithoneormoreoftheirlocalbreakers.

TheConnectingPartyshallprovideutility-graderelaysforprotectionoftheFETransmissionSystem. FEshallapproveallrelaysspecifiedfortheprotectionoftheFETransmissionSystem,includingtimedelay andauxiliaryrelays.Relayoperationforanyofthelistedfunctionsthatarerequiredshallinitiateimmediate separationoftheparallelgenerationfromtheFETransmissionSystem:

Relay Function

Frequency

Todetectunderfrequencyandoverfrequencyoperation.

Overvoltage Todetectovervoltageoperation.

Undervoltage Todetectundervoltageoperation.

GroundFaultDetectorTodetectacircuitgroundontheFETransmissionSystem.

PhaseFaultDetectorTodetectphasetophasefaultsontheFETransmissionSystem.

TransferTripReceiverToprovidetrippinglogictothegenerationownerforisolationofthe generationuponopeningoftheFEsupplycircuits.

DirectionalPowerTodetect,underallsystemconditions,alossofFEprimarysource.The relayshallbesensitiveenoughtodetecttransformermagnetizingcurrent suppliedbythegeneration.

TheInterconnectionCustomerwillberequiredtocomplywithallFEGenerationProtection RequirementsforGenerationInterconnectionCustomers.TheGenerationProtectionRequirementsmaybe

thefollowinglinks:

www.firstenergycorp.com/feconnect

www.pjm.com/planning/design-engineering/to-tech-standards.aspx

FESystemModifications

Systemmodificationsmayberequiredtomakesettingschangesand/orreplaceexistingrelaysat FirstEnergyremotesubstation.Customerrelayingwillberequiredtocoordinatewithupstream transmissionsystemprotection.

RelayupgradesatTangy(Dual421and501)

Cardington(Dual411Land501)

FiberbetweenAF1-122andCardingtonSub

CircuitBreakerAdequacy

PJMdoesnotidentifyanynewbreakersasoverdutiedbythisproject

SettingsChanges

Tangy

Cardington

Attachment#2:One-LineDiagrams

ICOne-LineDiagram NotApprovedforConstruction

Attachment4:GenerationConnectionRequirements

GenerationConnectionRequirements

RequirementsforTransmissionConnectedFacilitiesdocumentslocatedateitherofthefollowinglinks:

www.firstenergycorp.com/feconnect

www.pjm.com/planning/design-engineering/to-tech-standards.aspx

requirementwillbeasfollows:

SynchronousNew>20MW0.95leadingto0.90lagging

SynchronousNew<=20MW0.95leadingto0.90laggingPointofInterconnection

WindorNonSynchronous NewAll0.95leadingto0.95laggingHighSideoftheFacility SubstationTransformers

SynchronousIncrease>20MW1.0(unity)to0.90lagging

SynchronousIncrease<=20MW1.0(unity)to0.90laggingPointofInterconnection

WindorNonSynchronous IncreaseAll0.95leadingto0.95laggingHighSideoftheFacility SubstationTransformers

TheabovetableisapplicabletoAF1-122.

AnydifferentreactivepowerrequirementsthatFEand/orPJMdeterminestobeappropriate forwind-poweredorothernon-synchronousgenerationfacilitieswillbestatedintheapplicable interconnectionagreement(s).

InductiongeneratorsandothergeneratorswithnoinherentVAR(reactivepower)control capability,orthosethathavearestrictedVARcapabilitylessthanthedefinedrequirements,must providedynamicsupplementaryreactivesupportlocatedatthegenerationfacilitywithelectrical characteristicsequivalenttothatprovidedbyasimilar-sizedsynchronousgenerator.

DesignRequirements

ICisresponsibleforspecifyingappropriateequipmentandfacilitiessuchthattheparallelgenerationis applicablefederal,state,andlocalcodes.

TransmissionDesignRequirements

DesignCriteria

FacilitiesownedandoperatedbyTransmissionOwnershallcomplywiththeapplicableTransmission OwnertechnicalrequirementsandstandardspostedonthePJMwebsiteperthePJMTariff,andthe followingcriteria.Wheretherearedifferentrequirementsforthesamecriterion,themorerestrictiveshall apply.ICmustabidebyanyPJM,RFCorNERCcriteriaimposedthatismorerestrictivethanthoseof TransmissionOwner.

GeneralDesignRequirements

Systemphasing(counterclockwise) X-Y-Z

Systemfrequency: 60hertz

Elevation,AMSL: Lessthan1000meters 40

Maximumambienttemperature: 40degreesC

Minimumambienttemperature: -40degreesC

Maximumconductoroperatingtemperature: ContactTransmissionOwner

WindLoading(roundshapes):

PerASCE7-98,perFig.6-1 dependingonlocation

IceloadingSubstations(nowind): 25mm

Seismiczone:

VoltageandCurrentRatings

PerASCE7-98,perFig. 9.4.1.1(a)and(b).Equipment qualificationperIEEE693-97

Nominalphase-to-phase: 69kV

Maximumphase-to-phase: 72.5kV

Basicimpulselevel(BIL): 350kV

Maximumcontinuouscurrentcarryingcapacity: 2000A

Designfaultcurrent:

ClearancesandSpacing 40kA

Recommendedrigidbuscenter-to-centerphasespacing:

Minimumphase-to-phase,metal-to-metaldistance:

Recommendedphase-to-ground:

Minimumphase-to-ground:

Minimumverticalclearancefromlivepartstograde: -

Minimumhorizontalclearancefromliveparts: -

Minimumbottomofinsulatortotopoffoundation: -

Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.