

The Boost Center
by Blue Federal Credit Union
The Boost Center is a community resource center and hub in Cheyenne, Wyoming enhancing the efforts of local non-profits and serving as a safe space for the community. This project will provide resources to those in need, assist to improve housing stability, provide educational development, and widen economic opportunities. My role was to design the space, produce construction documents, create renderings and design presentations, select finishes, lead design and client meetings, and follow the project through the CA phase.
Scale: 1,325 sqft
Completed: October 2024, Opened: December 2024
Team: Abbie Reece, supervisor


= 1'-0"
GENERAL NOTES - NEW CONSTRUCTION:
1. REFER TO SHEET A0.20 FOR INTERIOR PARTITION TYPE INFORMATION
3.
2. REFER TO SHEET
DETAIL
4. PARTITION TYPES CONTINUE AT OPENINGS AND AROUND CORNERS U.N.O.
5. REFER TO INTERIOR FINISH DRAWING SHEETS FOR INTERIOR FINISH INFORMATION.
6. REFER TO ARCHITECTURAL FINISH PLANS FOR FLOOR FINISHES
GENERAL NOTES - CONCRETE SLAB ON GRADE:
1. SLAB-ON-GRADE TO BE 4" TOTAL THICKNESS, TYPE I/II PORTLAND CEMENT, NORMAL WEIGHT CONCRETE WITH 28-DAY COMPRESSIVE STRENGTH OF f'c = 3,500 PSI, 1" MAX AGGREGATE SIZE, WATER/CEMENT RATIO = 0.45. REINFORCE WITH #3 REINF AT 16" O.C. EACH WAY OR WITH 6x6 10/10 WWF CENTERED IN SLAB.
2. SLAB TO BE PLACED OVER CONTINUOUS VAPOR BARRIER, 6" MINIMUM COMPACTED GRANULAR AGGREGATE BASE AND PROPERLY COMPACTED/PREPARED SUBGRADE.
3. PROVIDE 1" CONTROL JOINTS AT 12'-0" MAX EACH WAY (MAX ASPECT RATIO 1:1.5). LOCATE AT ABRUPT CHANGES IN THICKNESS AND LOCATIONS PRONE TO CRACKING. COORDINATE LOCATIONS WITH FLOOR FINISHES AND INTERIOR WALLS. PROVIDE TOOLED JOINT OR SAW CUT AS SOON AS THE CONCRETE HAS HARDENED SUFFICIENTLY TO PERMIT CUTTING WITHOUT CHIPPING, SPALLING, R TEARING (NOT MORE THAN 12 HRS AFTER CASTING).
4. VAPOR BARRIER TO BE INSTALLED PER RECOMMENDATIONS OF PCA AND ACI 302.7R-04. VAPOR BARRIER BASIS OF DESIGN STEGO WRAP VAPOR BARRIER BY STEGO INDUSTRIES (15 MIL MINIMUM THICKNESS). ALTERNATE : PERMANATOR HP BY W.R. MEADOWS.
5. AT EDGES, PROVIDE 1/2" PREFORMED JOINT FILLER, FULL SLAB DEPTH WITH JOINT SEALANT. FILLER SHALL NOT PROTUDE ABOVE SLAB.
6.VERIFY ALKALINITY OF CONCRETE SURFACE, SLAB VAPOR TRANSMISSION AND SLAB FLATNESS/LEVELNESS ARE COMPATIBLE WITH FLOORING SYSTEM AND ADHESIVES PRIOR TO INSTALLING FLOORING.
7. TAKE PRECAUTIONS TO MINIMIZE SLAB CURLING.
KEYNOTES - CONSTRUCTION PLANS
1JOINT BETWEEN EXISTING AND NEW CONCRETE SLABS ON GRADE; TEST EXISTING CONCRETE SLAB TO DETERMINE IF MOISTURE MITIGATION IS REQUIRED IN AREAS THAT ARE RECEIVING NEW FLOOR FINISH
2WOOD SLIDING BARN DOOR, RE: DOOR SCHEDULE
3FIREPLACE;
Foundation Boost Center
3/8"




Porsche Denver West
Porsche Denver West is a state-of-the-art dealership for Porsche enthusiasts. The project is located in Lakewood, Colorado and features a showroom, service center, designer lounge, boutique, and sale areas, new and classic cars on display, and a two-story parking garage. It offers a new standard for luxury, innovation and performance. My role was to oversee all CA processes, be a main point of contact for project concerns, and complete ASI packages, RFI’s, and submittals.
Scale: 46,000 sqft
Completed: November 2024, Opened: November 2024
Team: Jon Bassett, Roman Gershkovich








The Mighty Argo
The development of a cable car, adjacent to the Argo Mill and Tunnel in Idaho Springs, Colorado. The car will climb 1300’ up Rosa Gulch to the Argo Landing, featuring a bar and restaurant, saloon, amphitheater, viewing decks, an observation trestle, and pedestrian plazas. My role was help produce construction documents and ASI packages, assist in renderings, and create presentations for client meetings.through the DD, CD, and CA phases of the project.
Scale: 1,241,460 sqft
Progress: Ongoing, CA phase
Team: Trevor Carrasco, Jenni Lane, Patri Romo


KEYNOTES - PLAN-SECTION DETAILS
125OMITTED 126OMITTED
127OMITTED
128FOAM CLOSURE
129ROOF ASSEMBLY; RE: ROOF PLANS
130LOUVER; RE: MECHANICAL
131PRIMED EXTERIOR GYPSUM SHEATHING
132IMPERMEABLE LINER, PER CIVIL
133FILTER FABRIC WRAPPED GRAVEL CONTAINES PERIMETER DRAIN, PER CIVIL
134FRP PANEL
135NATIONAL GYPSUM "EXP TILE BACKER BOARD"; 5/8"; TAPE JOINTS WITH ROLL APPLIED "LATICRETE" HYDROBAN OR EQUAL AT WASH BAY WALLS BEHIND FRP
1362 X 2 COLD FORM STEEL ANGLE
1372X4 STEEL ANGLE, COUNTERSUNK FASTENER TO FACE OF DECK
138SLOPE TOP OF WALL AT 1/4" PER 1'-0" TO DRAIN
139STEEL STOP PLATE WELDED TO DOOR FRAME
140SEALANT
141MANHOLE COVER; RE: PLUMBING
142T-CLEAR WALL PROTECTION BOARD
143 CONCRETE SEALER
144VAPOR BARRIER
145COUNTERSUNK FASTENER, PAINTED TO MATCH BRAKE METAL
146CUSTOM SHAPE METAL PANEL FASCIA
147IN WALL COUNTERTOP SUPPORT BRACKET, SPACED AS REQ'D. BLOCKING AS REQ'D.
1481/2" MARINE GRADE PLYWOOD
149STEEL COLUMNS SUPPORTING 1 HR FIRE BARRIER TO BE 1 HR RATED WITH SPRAY APPLIED FIRE PROOFING PER UL X790, TYP; RE: SHEET G1.03 FOR STEEL FIREPROOFING DIAGRAMS
1CONTINUOUS BED OF SEALANT
2SELF ADHERING FLASHING
3VAPOR PERMEABLE WEATHER BARRIER
4TAPE SEAMS OF WRB
5PREFORMED HEAD FLASHING W/ DRIP EDGE AND WEEPS
6DISCONTINOUS BEAD OF SEALANT; ALLOWS DRAINAGE
7FLEXIBLE SILL FLASHING
8PREFORMED METAL SILL FLASHING WITH DRIP EDGE
9DOW FOAM SEALANT
10TERMINATION BAR
11BENT PLATE, RE; STRUCTURAL
12CLIP FOR METAL STUD ASSEMBLY TO SLAB
13RE: STRUCTURAL
146" HALF ROUND GUTTER. INSTALL PER MANUF SPEC
15GUTTER SUPPORT & ATTACHMENT STRAP
16FASCIA PLATE TRIM PIECE. INSTALL PER MANUF SPEC
17FASCIA TOP CAP TRIM PIECE. INSTALL PER MANUF SPEC
18HIPPED RIDGE TRIM PIECE. INSTALL PER MANUF SPEC
19GABLE TRIM PIECE. INSTALL PER MANUF SPEC
20SLOTTED DEEP LEG TRACK AT SLIP CONNECTION
21GYP BOARD J-CASING TRIM PIECE
22WINDOW FRAME, INSTALL PER MANUFACTURER, RE:TO GLAZING ELEVATIONS
23STRUCTURAL FRAMING, RE: STRUCTURAL
24PREFINISHED BRAKE METAL FLASHING
25DRAINAGE MAT
26RUBBER SPACER TO FILL CORRUGATION GAP
27COLD FLUID APPLIED WATERPROOFING
MEMBRANE
28CRICKET & BACKER FLASHING, INSTALL BACKER FLASHING UP ROOF SLOPE 18" MIN
29VERTICAL SLIP JOINT
30VERTICAL SLIP CONNECTION, RE: STRUCTURAL
31CORRUGATED METAL PANELS OVERLAP AT VERTICAL SLIP
32SNOW LINE, AVOID PLACING GUTTERS ABOVE THIS LINE
33PREFINISHED ALUMINUM BRAKE METAL FLASHING AT CURB. SLOPE TO DRAIN.
HATCH WITH DASHED EXTENTS INDICATES LOCATION OF SPRAY APPLIED INSULATION ON UNDERSIDE OF DECK ABOVE LINEAR TAPE LIGHT
34"WALL GUARD" CONCRETE FACED INSULATED PANEL
35STRUCTURAL STEEL COLUMN, RE: STRUCTURAL
36BENT PLATE DOOR FRAME, PAINTED
37JAMB TRACK PER MANUF. STANDARDS
38MOTORIZED ALUMINUM SECTIONAL DOOR W/ MOTOR AND ANGLED TRACK
39STUD FRAME INFILL IN WIDE FLANGE CAVITY, RE: STRUCTURAL
40ADJUSTABLE POLYPROPYLENE DECK PEDESTAL
412X4 WOOD DECKING WITH CONCEALED FASTENERS
4260 MIL TPO
435/8" FRTW PLYWOOD SHEATHING
4460 MIL FULLY ADHERED TPO ROOF MEMBRANE WRAPPED UP AND OVER
45OMITTED
46BLOCKING AS REQUIRED
472X2 ANGLE EDGE SUPPORT, ATTACHED TO COMPOSITE DECK
48INSECT SCREEN
49CONTINUOUS TRACK; RE: STRUCTURAL
50TPO STRIP FLASHING
51SIMPSON ANGLE BRACKET; RE: STRUCTURAL
522X6 CURB
53DOOR; RE: DOOR SCHEDULE
54STAY ROLLER BEYOND; RE: PLAN DETAIL
55EPDM SEAL
56STAY ROLLER AT BASE OF DOOR
57OMITTED
58SLIDING DOOR TRACK AND HANGER
59SPRAY APPLIED INSULATION
60INSIDE CORNER TRIM, BY MANUFACTURER
61OUTSIDE CORNER TRIM, BY MANUFACTURER
62LIGHT FIXTURE, RE; ELEC
634"X4" LUMBER MILLED TO 2.5" X 2.5". 4" LONG SPACED @ 24" OC ALONG LENGTH OF RAMP OR WHERE RECESSED TAPE LIGHT OCCURS AT DECK EDGE
642"X4" LUMBER
65WEEP HOLES SPACED 18" MAX
66PREFORMED HEAD TRACK FLASHING WITH DRIP EDGE
67DAMPROOFING
68HOT FLUID APPLIED WATER PROOFING AND DRAINAGE COURSE, RETURN WATER PROOFING UP CURB
70BRAKE METAL CLOSURE
71STRUCTURAL STEEL ANGLE SUPPORT
ATTACHMENT FROM FACADE SUPPORT TO STRUCTURAL COLUMN
72BACKER ROD AND SEALANT
73STEEL PLATE WELDED TO COLUMN AS JAMB FOR
SECTIONAL DOOR
74MINERAL WOOL INSULATION
75COLD FORM METAL FRAMING
76PLYWOOD
77SHIPLAP WOOD SIDING
78BLACKENED


SFWTC
This project re-imagines the afterlife of the largest and oldest water treatment plant in San Francisco. The treatment plant is located in the poorest and most marginalized neighborhood in San Francisco. Through our proposal, the phases of the cleansing process become a gestural and interactive exhibition, in effort to communicate the severity of waste and pollution. A constructed wetland connects the treatment plant to the Bay as an additional step to the process, which also provides numerous environmental benefits. Along with educational purposes, the project houses a laboratory and solutions center, thermal baths, open green space, and provides visibility to this industrial, marginalized area within San Francisco.
Issued: August 2021, Reviewed December 2021
Team: Rafael Jimenez Camacho, Samantha Rohlfsen







Phase 1: Waste and Sewage Separation
Phase 2: Sludge Sedimentation
Phase 3: Sludge Separation and Aeration




The day in the life of a frequent visitor starts through them using the Park n Ride as a parking. in the case the person has children, they would drop their child at the Daycare facility before taking the bus or walking to work. During or on their way back from work they would order grocries through the app on their phone.

GROW
Existing industrial agriculture supports food insecurity, creates and amplifies climate threats, and enforces inequality amongst groups of people. Through this project, we are critiquing these issues, to propose a holistic approach that addresses nearly every avenue of food systems, into one design model. Our goal is to nurture close relationships between people and where their food is grown. This will bring production directly to where the demand is, putting control back into the hands of people, and in, turn increasing access and reducing food miles. The best building typologies for these new systems are centered around the concept of transportation as a hub, specifically Park and Rides, because these are spaces people already frequent to. This project utilitizes an existing Park and Ride in Des Moines, Iowa to house vertical gardens for growth, purchase, distribution, and exhibition of food, and serves as a learning model for the system to be copied throughout the country.
Issued: January 2022, Reviewed May 2022
Team: Reid Snell, Ana Sofia Ramos, Ehsan Ghaderi


After ordering, they go to the front desk at GROW where someone confirms their order and brings their purchase from the refrigerators over in a crate. The visitor has to transfer their produce from the crate to a reusable bag. Finally, the parent picks up their child from the Daycare and head home for the day.
PARK i N CENTER
DAYCARE DROF OFF
TAKE BUS TO WORK
FRONT DESK P i CK UP
PERSONEL CONF i RMS ORDER AND BR i NGS i T TO FRONT DESK
DAYCARE P i CK UP
HEAD HOME FOR THE DAY








Graphic Visualization Concept Work










PERIMETER AND INTERNAL GARAGE WALLS: 4 COLOR
CUSTOM PAINTED CONCRETE AND CMU WALLS
COLUMNS: 1 COLOR SOLID PAINT
CEILINGS: 1 COLOR SOLID PAINT, MEP ITEMS EXCEPTED
FLOOR: NO FINISH PAINT
1 2 3 4
LEVELS B2 & B1
