DTMP 7.17.25 PC WS Presentation

Page 1


Boyd O. Sewe | LRP – Principal Planner

1. PROJECT BACKGROUND

• 2045 Comprehensive Plan

* Placemaking policy #13: Update the Downtown Master Plan.

• Council allocated $500,000 towards developing a downtown master plan.

• MKSK was selected for the contract at a total cost of $495,075.00

• This master plan will be considered by the Planning Commission as an amendment to the 2045 Comprehensive Plan.

2. PROJECT TIMELINE

TASK 0: STARTUP & COORDINATION

TASK 1: LAND USE ASSESSMENT (JUNE–SEPTEMBER)

TASK 2: HOUSING & MARKET ANALYSIS (AUGUST–DECEMBER)

TASK 3: PUBLIC ENGAGEMENT

TASK 4: PLAN DEVELOPMENT (OCTOBER–FEBRUARY)

TASK 5: DRAFT REPORT (FEBRUARY–MARCH)

TASK 6: FINAL DELIVERABLES (MARCH–MAY)

RECONNECTING TO OUR DOWNTOWN

3. PROJECT MILESTONES

OUTREACH & WEBSITE 08/11/2025 08/12/2025 STAKEHOLDER & ADVISORY COMMITTEE MEETINGS

JULY 4 EVENT

5. JULY 4 EVENT

6. JULY 4 EVENT

7. JULY 4 EVENT

 Tabled at Henry A. Tandy Park from 7:00 AM to 3:00 PM

 Consultants team from Columbus and Louisville in attendance

 LFUCG Staff helped out

123 Paper Surveys collected

 Over 100 web surveys completed  246 Web responses received

RECONNECTING TO OUR DOWNTOWN

8. JULY 5 EVENT

 Tabled at Castlewood Park

 Paper Surveys collected

 Web Cards distributed

RECONNECTING TO OUR DOWNTOWN

5. NEXT STEPS

• Biweekly Meetings with the Project Management Team

• August 10-12 Stakeholders meeting

• August 11 Project Advisory Committee meeting

• Community Meeting #1 (Early October)

• Public input and collaboration are crucial—we encourage all stakeholders to stay engaged and help shape the future of downtown Lexington.