Fund Source:
School Buildings (1st Batch)
Project:
Construction of 2-CL at Lagao NHS Main, Prk. Malakas, Brgy. San Isidro, General Santos City
Amount: Contractor:
P 1,757,597.47 / 90 CD J.G. Oranza Construction
Start Date:
June 28, 2009 Date Expiry: September 27, 2009 Date Completed: July 20, 2009 Fund Source: School Buildings (1st Batch)
Project: Amount: Contractor:
Start Date:
Construction of 2-CL at Banisil H.S, Tambler, General Santos City
P 1,011,810.00 / 60 CD Hanna Via Design & Construction
June 28, 2009 August 27, 2009 Date Completed: July 16, 2009 Date Expiry: