CY 2009 COMPLETED PROJECTS


Project:

Rehab./ Reconstruction/ Upgrading of Damaged Paved National Roads Digos-Makar Road (Lagao Section), GSC

P 14,136,276.61 / 90 CD Vertical Builders Start Date: March 27, 2009 Date Expiry: June 26, 2009 Date Completed: June 30, 2009 Fund Source: Regular Infra. (Pump Priming) Amount: Contractor:

Project:

Road Upgrading (Gravel To Paved) Based on Gravel Road Strategies General Santos Circumferential Road (Western Section), GSC

P 17,358,469.85 / 120 CD T-Square Builders Start Date: March 27, 2009 Date Expiry: July 26, 2009 Date Completed: June 30, 2009 Fund Source: Regular Infra. (Pump Priming) Amount: Contractor:


s

Project:

Rehab./ Reconstruction/ Upgrading of Damaged Paved National Roads Makar-Tupi Road, Polomolok, South Cotabato

Amount: Contractor:

P 14,144,979.31 / 90 CD

Project:

Road Upgrading (Gravel To Paved) Based on Gravel Road Strategies Marbel-Makar Road, Tupi, South Cotabato

Amount: Contractor:

P 9,414,855.02 / 90 CD

CHL Construction Start Date: March 27, 2009 Date Expiry: June 26, 2009 Date Completed: June 30, 2009 Fund Source: Regular Infra. (Pump Priming)

Start Date:

Reydan Builders

March 27, 2009 Date Expiry: June 26, 2009 Date Completed: June 30, 2009 Fund Source: Regular Infra. (Pump Priming)


Project:

Rehabilitation of Two (2) Water Systems, Brgy. Bula, General Santos City

Amount: Contractor:

P 470,499.92 / 45 CD Sarex Builders

Start Date:

November 2, 2009 Date Expiry: December 17, 2009 Date Completed: December 9, 2009 Fund Source: VIILP

Project:

Partial Construction of Lined Canal, Brgy. Pagalungan, Polomolok, South Cotabato

Amount: Contractor:

P 960,999.71 / 60 CD

Start Date:

Reydan Builders

November 2, 2009 Date Expiry: January 1, 2010 Date Completed: December 9, 2009 Fund Source: VIILP


Project: Amount: Contractor:

Construction of 1-CL at Balite E/S, Brgy. Lagao, General Santos City

P 555,611.10 / 45 CD Jargon Construction

Start Date:

June 28, 2009 Date Expiry: August 12, 2009 Date Completed: July 13, 2009 Fund Source: School Buildings (1st Batch)

Project:

Construction of 1-CL at Pao-Pao E/S, Brgy. Sinawal, General Santos City

Amount: Contractor:

P 557,653.00 / 45 CD

Start Date:

Jargon Construction

June 28, 2009 Date Expiry: August 12, 2009 Date Completed: August 11, 2009


Fund Source:

School Buildings (1st Batch)

Project:

Construction of 2-CL at Lagao NHS Main, Prk. Malakas, Brgy. San Isidro, General Santos City

Amount: Contractor:

P 1,757,597.47 / 90 CD J.G. Oranza Construction

Start Date:

June 28, 2009 Date Expiry: September 27, 2009 Date Completed: July 20, 2009 Fund Source: School Buildings (1st Batch)

Project: Amount: Contractor:

Start Date:

Construction of 2-CL at Banisil H.S, Tambler, General Santos City

P 1,011,810.00 / 60 CD Hanna Via Design & Construction

June 28, 2009 August 27, 2009 Date Completed: July 16, 2009 Date Expiry:


Fund Source:

School Buildings (1st Batch)

Project:

Construction of 3-CL School Building, Polomolok NHS, Polomolok, South Cotabato

Amount: Contractor:

P 216,577.27 / 45 CD Sarex Builders

Start Date:

June 28, 2009 Date Expiry: August 12, 2009 Date Completed: June 30, 2009 Fund Source: School Buildings (1st Batch)

Project: Amount: Contractor:

Start Date:

Construction of 2-CL at Cebuano NHS, Tupi, South Cotabato

P 1,143,536.97 / 60 CD CEK Construction

June 28, 2009 Date Expiry: August 27, 2009 Date Completed: August 16, 2009 Fund Source: School Buildings (1st Batch)


Project: Amount: Contractor:

Construction of 2-CL at Sta. Cruz, Tampakan, South Cotabato

P 1,201,338.66 / 60 CD DACODECO

Start Date:

June 28, 2009 Date Expiry: August 27, 2009 Date Completed: July 23, 2009 Fund Source: School Buildings (1st Batch)

Project: Amount: Contractor:

Start Date:

Repair of 2-CL at Maltana, Tampakan, South Cotabato

P 539,979.19 / 45 CD Jargon Construction

June 28, 2009 Date Expiry: August 12, 2009 Date Completed: July 20, 2009 Fund Source: School Buildings (1st Batch)


CY 2008 CARRY-OVER COMPLETED PROJECTS


Project: Amount: Contractor:

Rehab. Of Junction Digos-Buayan Airport Road, General Santos City

P 9,432,961.74 / 120 CD MGBJ Rising & Land Developer

Start Date:

November 19, 2008 March 20, 2009 Date Completed: March 13, 2009 Fund Source: Regular Infra. Date Expiry:

Project:

Rehab./Reconstruction of Digos-Makar Road (Lagao-Ligaya Section), General Santos City

Amount: Contractor:

P 18,879,868.50 / 180 CD

Start Date:

Sarangani RockMixer

November 19, 2008 Date Expiry: May 20, 2009 Date Completed: April 30, 2009 Fund Source: Regular Infra.


Project:

Rehabilitation of Makar-Digos Road,Brgy. Katangawan, General Santos City

Amount: Contractor:

P 18,897,408.19 / 180 CD JV Lagon Construction

Start Date:

December 27, 2008 Date Expiry: June 25, 2009 Date Completed: September 22, 2009 Fund Source: Regular Infra.

Project:

Concreting of Road & Reblocking of Marbel-Makar Road, Matin-ao Silway 8 Section, Polomolok, South Cotabato

Amount: Contractor:

P 14,169,053.00 / 180 CD

Start Date:

MH Southern Construction

November 16, 2008 Date Expiry: May 15, 2009 Date Completed: June 30, 2009 Fund Source: Regular Infra.


Project:

Concreting of Road & Reblocking of Marbel-Makar Road, Glamang Section, Polomolok, South Cotabato

Amount: Contractor:

P 15,111,990.91 / 180 CD JV Lagon Construction

Start Date:

November 16, 2008 May 15, 2009 Date Completed: September 30, 2009 Fund Source: Regular Infra. Date Expiry:

Project:

Concreting of Road & Reblocking of Marbel-Makar Road, Matin-ao Silway 8 Section, Polomolok, South Cotabato

Amount: Contractor:

P 15,113,694.50 / 180 CD

Start Date:

CHL Const. Dev’t Corp.

November 16, 2008 Date Expiry: May 15, 2009 Date Completed: June 30, 2009


Fund Source:

Regular Infra.

Project:

Concreting of Road & Reblocking of Marbel-Makar Road, Crossing Rubber Section, Tupi, South Cotabato

Amount: Contractor:

P 11,332,020.08 / 120 CD

Start Date:

November 16, 2008 March 16, 2009

Date Expiry:

Reydan Builders

Date Completed: March 15, 2009 Fund Source: Regular Infra.

Project:

Concreting of Road & Reblocking of Marbel-Makar Road, Palian Section, Tupi, South Cotabato

Amount: Contractor:

P 15,101,620.72 / 180 CD

Start Date:

November 16, 2008 May 15, 2009

T-Square Builders

Date Expiry: Revise Exp. Date: May 30, 2009 Date Completed: May 29, 2009


Fund Source:

Regular Infra.

Concreting of Road, Brgy. Bula General Santos City P 1,887,115.88 / 90 CD T-Square Builders Start Date: January 23, 2009 Date Expiry: April 23, 2009 Date Completed: April 22, 2009 Fund Source: VIILP Project: Amount: Contractor:

Concreting of Roads, Nursey Roads, Brgy. Lagao, GSC P 1,887,115.88 / 90 CD T-Square Builders Start Date: January 23, 2009 Date Expiry: April 23, 2009 Revised Exp. Date: May 21, 2009 Date Completed: May 20, 2009 Fund Source: VIILP Project: Amount: Contractor:


Improvement/Repair of General Santos-Malungon-Digos National Road (Going to Davao del Sur and Davao City) Amount: P 18,884,926.45 / 90 CD Contractor: Grace Construction Start Date: January 23, 2009 Date Expiry: April 23, 2009 Date Completed: April 22, 2009 Fund Source: VIILP Project:

Improvement/Repair of General Santos-Apopong-Marbel Road (Going to South Cotabato, Sultan Kudarat and Maguindanao) Amount: P 18,890,675.78 / 90 CD Contractor: Grace Construction Start Date: January 23, 2009 Date Expiry: April 23, 2009 Date Completed: April 22, 2009 Project:


Fund Source:

VIILP

Construction of Multi-Purpose Building, Brgy. Buayan, GSC P 940,852.10 / 90 CD Vertical Builders Start Date: January 23, 2009 Date Expiry: April 23, 2009 Date Completed: April 7, 2009 Fund Source: VIILP Project: Amount: Contractor:

Construction of Multi-Purpose Building, Brgy. Upper Labay, GSC Amount: P 940,852.11 / 90 CD Contractor: Vertical Builders Start Date: January 23, 2009 Date Expiry: April 23, 2009 Date Completed: February 16, 2009 Fund Source: VIILP Project:


Construction of Water System, Brgy. Apopong, GSC P 1,886,819.98 / 90 CD KGD Builders Start Date: January 23, 2009 Date Expiry: April 23, 2009 Date Completed: April 22, 2009 Fund Source: VIILP Project: Amount: Contractor:


Concreting of Road, Brgy. Mabuhay, General Santos City P 1,413,427.75 / 90 CD KGD Builders Start Date: January 23, 2009 Date Expiry: April 23, 2009 Date Completed: April 22, 2009 Fund Source: Lower House Project: Amount: Contractor:

Construction of Water System, Dacville, Brgy. Mabuhay, GSC P 1,883,773.03/ 90 CD DACODECO Start Date: January 23, 2009 Date Expiry: April 23, 2009 Date Completed: April 22, 2009 Fund Source: Lower House Project: Amount: Contractor:


Construction of Multi-Purpose Building at Oval Plaza, GSC P 329,999.50 / 75 CD By Administration Start Date: November 16, 2008 Date Expiry: January 6, 2009 Date Completed: December 31, 2008 Fund Source: Lower House Project: Amount: Contractor:

Concreting of Road (Addt’l), Back of Iglesia Ni Cristo, Brgy. San Isidro, GSC Amount: P 564,010.24/ 60 CD Contractor: CEK Construction Start Date: January 23, 2009 Date Expiry: March 24, 2009 Date Completed: March 13, 2009 Fund Source: Lower House Project:


Construction of Multi-Purpose Building, Brgy. Crossing Palkan, Polomolok, South Cotabato Amount: P 658,418.61/ 60 CD Contractor: Vertical Builders Start Date: January 23, 2009 Date Expiry: March 24, 2009 Date Completed: February 20, 2009 Fund Source: Lower House Project:

Construction of Multi-Purpose Building, Brgy. Lamcaliaf, Polomolok, South Cotabato Amount: P 469,508.53/ 60 CD Contractor: Sarex Builders Start Date: January 23, 2009 Date Expiry: March 24, 2009 Date Completed: February 16, 2009 Project:


Fund Source:

Lower House

Construction of Multi-Purpose Building, Kinilis Elem. School, Brgy. Kinilis, Polomolok, South Cotabato Amount: P 942,030.07/ 75 CD Contractor: COFEJOK Construction Start Date: January 23, 2009 Date Expiry: April 8, 2009 Date Completed: March 16, 2009 Fund Source: Lower House Project:

Construction of Flood Control, Brgy. Buto, Tampakan, South Cotabato Amount: P 1,407,972.45 / 60 CD Contractor: Freden Construction Start Date: November 23, 2008 Date Expiry: January 22, 2009 Date Completed: January 16, 2009 Project:


Fund Source:

Lower House

Construction of Multi Purpose Building, Brgy. Danlag, Tampakan, South Cotabato Amount: P 660,018.77 / 60 CD Contractor: Sarex Builders Start Date: November 23, 2008 Date Expiry: January 22, 2009 Date Completed: January 10, 2009 Fund Source: Lower House Project:

Completion of Multi-Purpose Building, Brgy. Maltana, Tampakan, South Cotabato Amount: P 280,003.00 / 60 CD Contractor: Jargon Construction Start Date: November 23, 2008 Date Expiry: January 22, 2009 Date Completed: January 21, 2009 Project:


Fund Source:

Lower House

Completion of Multi-Purpose Building, Brgy. Kipalbig, Tampakan, South Cotabato Amount: P 753, 070.63/ 60 CD Contractor: J.G. Oranza Construction Start Date: January 21, 2009 Date Expiry: March 24, 2009 Date Completed: February 7, 2009 Fund Source: Lower House Project:


Construction/improvement of water supply for waterless Municipalities, Brgy. Lampitak, Tampakan, South Cotabato Amount: P 2,350,401.80 / 90 CD Contractor: Freden Construction Start Date: February 19, 2009 Date Expiry: May 20, 2009 Date Completed: February 3, 2009 Fund Source: Water Supply For Waterless Municipalities Project:


Opening of Sulit to Sumbakil Farm to Market Road, Polomolok, South Cotabato Amount: P 1,410,009.80 / 90 CD Contractor: Freden Construction Start Date: January 23, 2009 Date Expiry: April 23, 2009 Revise Exp. Date May 20, 2009 Date Completed: May 19, 2009 Fund Source: Comprehensive Agrarian Reform Program Project: