Complete guide on substructure construction

Page 1

A Complete Guide On Construction Substructure

Tips for you and your team


Summary of Topics Building Substructure Functions Components Substages Types of foundation Keypoints


What is Substructure

The substructure or foundation is the part of the building that is built below the ground level and is hidden from view. The substructure is the first stage of the construction process. Substructure transfers the load of the superstructure to the ground beneath. Superstructure should be designed with proper technique because it assures the stability of the superstructure too.


FUNCTIONS OF SUBSTRUCTURE It provides stability to the structure as a whole

It distributes the loads from the superstructure from soil beneath Substructure is to support and anchor the superstructure safely into the Earth. It must be designed to accommodate both the form and layout of the superstructure.


COMPONENTS OF SUPERSTRUCTURE Foundations

Abutments

Retaining walls

Use of grouting

Use of semi-integral

Use of three-sided

methods for

and integral abutments,

precast wall culverts; use

improving foundation

with a single row of

of modular retaining

soil.

piles.

walls.


COMPONENTS OF SUPERSTRUCTURE Precast concrete

Piers:

sheeting

Bearings:

Goal is to prevent

It has been used as retaining

timber fender damage

Elastomeric, multi-

walls, wing walls, and

around piers from

components of the bridge

vessel collision.

abutment.

rotational, or isolation types.


Excavation

Levelling & P.C.C. for foundation

Substructure Stage R.C.C. for foundation

R.C.C. columns up to plinth level Backfilling of excavated earth


Excavation, Compaction & Levelling Substructure Stage

Excavation

Setting out of all columns should be carried out prior to excavation as per approved centreline drawings Proper Compaction of soil layer for foundation decreases settlement and prevents undesired accidents Compaction of soil improves shear strength and decreases soil permeability Foundation should always be placed on the levelled surface in order to uniformly distribute the loading into the ground and prevent uneven settlement Sometimes the surface is not levelled even after doing levelling activity. Hence, it is always recommended place P.C.C. in all footings


P.C.C. (Plain Cement Concrete) Substructure Stage

P.C.C. Casting

1.Main purpose of P.C.C. is to act as a levelled surface for footings and transfer the load evenly into the ground 2.Remove all the loose materials from the excavation pits and do the shuttering by planks and runners wherever possible 3.After concrete pouring the surface is to be rammed and finished smoothly

Levelling


Substructure Stage

Isolated Slope Footing

Isolated Footing Cober blocks should be placed above P.C.C. to prevent direct contact or reinforcement with the surface New shuttering material should be used while constructing footings Column reinforcement to be aligned vertically for proper transfer of loads into the footing Curing in footing should be carried out for a period of 7 days

Isolated Stepped Footing


Substructure Stage

Backfilling of Excavated Earth Recording initial ground level Approved samples should be used for backfilling. Big boulders are not advisable. Backfilling should be carried out in layers. The thickness of each layer should not exceed 300mm. Each layer should be properly compacted before starting backfilling of the second layer. Required watering, compaction should be done. While compacting due care should be taken to protect foundations, columns, plinth walls, etc. which have been already constructed. Trained operators or skilled labor shall be engaged for backfilling.


Types Of Foundation 1. Open Foundation 2. Shallow Foundation Types of shallow foundation 1.Stepped Foundation 2.Combined Foundation 3.Raft Foundation 3.Deep Foundation


Open Foundation

Types of foundation

This is simply a layer of foundation concrete provided at the base of a column, pedestal, or wall. This type of foundation is provided when a hard stratum is available at a very shallow depth or the work is unimportant e.g. Compound wall, pillars for barbed wire fencing, etc.


Shallow Foundation

Types of foundation

When the foundation is placed immediately below the lowermost part of the structure it is called a shallow foundation. It can also be defined as, when the depth of foundation is less than or less than equal to the width


Deep Foundation

Types of foundation

When the depth of foundation is more than its width the foundation is called a deep foundation. If the depth of foundation is more than 2.00 m, it is called a deep foundation.


Keypoints

Before commencement of project work make sure the site is clear. There are no trees, plants, bigger stones, etc. Roads should be wide so as to allow the truck for loading and unloading construction material. If the site ground is uneven it should be made plain. Substructure Construction should be preferably completed before the rainy season


LOOKING FOR GUIDANCE?

For free site visit by a Nuvoco expert Get in touch. Nuvoco Home Assist - A one step solution for all your construction guidance BEST HOUSE PLANS HOUSE CONSTRUCTION COST CALCULATOR STAGES OF HOUSE CONSTRUCTION


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.