TRANSMISSION LINE RE-RATING PROGRAM BY THE NUMBERS IMPCO
»» 22 circuits studied
OPCO
»» 40 line assets studied
»» 57 circuits studied
»» 70%: line assets with potential LOCs
»» 114 line assets studied
»» 467 miles studied
»» 62%: line assets with potential LOCs
(left). Crew installs
»» 2,476 spans studied
»» 956 miles studied
suspension clamps to
»» 1,551 MVA: estimated capacity increase to system*
»» 4,631 spans studied
282 new steel poles. Steel pole readied to replace lattice tower
PHOTOS: POWER ENGINEERS
finish installation (right).
»» 5,196 MVA: estimated capacity increase to system*
»» 1949: the average year the studied lines were built
RE-RATING AEP
»» 1956: the average year the studied lines were built
POWER helps add 9,000 megawatts of capacity to AEP’s grid
WPCO
»» 4 circuits studied
By Kate Wutz
I
»» 8 line assets studied
magine improving a portion of an interstate highway to allow more traffic to flow through more efficiently. Now, instead of asphalt and cars, imagine conductors and current, and lengthen the distance of that “portion” to about 2,000 miles—the equivalent of driving from Columbus, Ohio, to Tulsa, Oklahoma, and turning around and heading back to Roanoke, Virginia. That analogy should give you some idea of the vast challenges POWER faced when it embarked on a four-year re-rating effort for client American Electric Power (AEP) in 2011.
Suddenly, the newly christened Transmission Line Re-Rating Program became what AEP referred to as the “biggest and most complicated transmission project of its kind in AEP history,” involving 2,000 miles of transmission line alone, plus distribution and communication circuits.
...the “biggest and most complicated transmission project of its kind in AEP history,” involving 2,000 miles of transmission line alone...
»» 36 miles studied »» 139 spans studied
KPCO
»» 295 MVA: estimated capacity increase to system*
»» 7 circuits studied
»» 1945: the average year the studied lines were built
»» 15 line assets studied Identifying LOCs
POWER Engineers and IJUS, an engineering firm based in Ohio, partnered to perform the re-rating studies and identify specific “locations of concern,” referred to as LOCs. Once specific LOCs were identified, POWER set to work to find solutions for raising load Modest beginnings capacity. This effort soon included Except, it didn’t start as a 2,000-mile project. It started when AEP POWER’s Environmental and GIS divisions as well, who racked up identified roughly 244 miles of line that needed to be re-rated, or 148,000 labor hours over the course of the next four years. modified to carry a greater load. POWER used LiDAR survey data provided by AEP to created However, the project was boosted to a new level by PJM 3-D computer models of 237 line segments and then studied those Interconnection, the regional transmission operator that coordinates models to evaluate future load increases. POWER’s team identified the movement of wholesale electricity in 13 states, including Ohio, 302 LOCs, most of which involved ground or distribution line Virginia, West Virginia, Kentucky, Michigan and Indiana— clearance issues—giving rise to the colloquial name for this project, including AEP’s service area. the “AEP Sag Study.” PJM identified approximately 1,600 miles of AEP transmission lines that needed to be modified by 2015 in order to meet a pro- POWER’s solutions jected increase in load—widening the electric highway in order to AEP already knew that remediating these LOCs would increase deal with an expected rise in traffic. This load increase would be the capacity of their grid and allow them to meet PJM’s increased spurred by the retirement of coal-fired generation in the region. load-rating projections. POWER’s team identified and categorized The circuits carrying the replacement power needed to be rated potential LOCs according to the type of remediation necessary, to handle it. then developed tailored solutions for each one. 10 Surges January 2016
»» 50%: line assets with potential LOCs
»» 53%: line assets with potential LOCs identified »» 87 miles studied »» 400 spans studied »» 336 MVA: estimated capacity increase to system* »» 1968: the average year the studied lines were built
APCO
»» 26 circuits studied »» 60 line assets studied »» 45%: line assets with potential LOCs »» 484 miles studied »» 2,225 spans studied »» 1,650 MVA: estimated capacity increase to system* »» 1960: the average year the studied lines were built
KEY Transmission lines included in the Re-Rating Program Transmission lines owned by AEP, but not part of the Re-Rating Program
*MVA calculations note The estimated system capacity increases were calculated by summing the anticipated rating increase for each circuit. It was assumed that the starting maximum operating temperature for each line asset was 203°F, which was used in conjunction with the re-rated maximum operating temperature to determine an increased ampacity (MVA) for each segment. January 2016 Surges 11