Inside Scoop
Construction Update Newsletter November 2017
Coldwater Board of Public Utilities
Updated Exterior
Siding removal and new window installation
PM Update Hello All, It’s time again for the Inside Scoop on the Coldwater BPU project. It’s been another busy month and crews are working hard to get all of the exterior scope done quickly to beat the fast approaching winter. The StormTech stormwater chamber system is complete. The sitework and site concrete have been completed. Grass seeding, underground irrigation and the first coat of paving is complete. The top coat of paving, and planting of the trees & bushes will be done in the spring. The new transformer has been set and the building power has been switched over to the new panels and service. The exterior windows and storefront openings have been installed and the exterior metals panels are currently being installed.
Curt Hielke curth@elzinga-volkers.com
For the interior work, door frames are in with drywall mostly completed and painting well underway. Ceiling grid is being installed and vinyl flooring has started. Electrical wiring is in progress and light fixtures are starting to be installed. The mezzanine metal railing is in place. Now we are on the final stretch of activities with about a month of construction left before furniture starts to go in place. This project has remained on schedule and the move-in is targeted for the end of the year! Enjoy the project photos and highlights. Curt Hielke Project Manager
www.elzinga-volkers.com www.elzinga-volkers.com