Project News
Phase 1 Progress The building has a new look now that the stucco and windows are installed! Phase 1 interior walls have all the mechanical, electrical, and plumbing roughed-in and have passed inspections. Drywall, painting, and tile finishes in Phase 1 are now well underway. The new elevator has recently been installed as well. Overall, our trade partners have been doing a great job and the project is on schedule. Mark W. Nanninga MarkN@elzinga-volkers.com
Wall and Floor Tile
SPOTLIGHT Holm Electric Holm Electric has been a great trade partner during this project. We are thankful for their willingness to help, work hard, and understand what it takes to get the job done right.
Flooring