ISSUE
15
OCTOBER 2013
Construction Update Newsletter
New Views Spectrum Health - Gerber Memorial
SAFETY SPOTLIGHT Utility shutdowns in buildings that never close are extremely difficult and sensitive to handle. Hospitals must maintain utility services for its patients and staff 24/7, so utility shutdowns are literally a life or death situation! Due to its critical nature, many hours, days and weeks of preparation go into each shutdown. Communication and cooperation are the key components to maintaining high quality healthcare while the facility expands.
Upcoming Milestones »» ED Floor Slab Complete P »» Drywall Installation Complete on the 2nd Floor »» 2nd Floor Painting Complete
Executive Summary Taking Shape…
We had another wet week at the project site, but it did not dampen our spirits or our progress. On the second floor, utility reroutes are nearing completion and drywall installation will follow close behind. In some areas of the floor, paint has been applied to the walls and preparations for cabinetry installation are being made. Firestopping is also receiving a lot of attention right now. Crews are working hard to make sure that every penetration in a fire rated wall or floor is sealed per very specific engineering standards. This work is critical to the overall safety of the building and the completion of the project. The ED addition, unfortunately, suffered a little bit with the wet weather. E&V crews, Cascade Cement, and Thompson Brothers managed to complete all the footing and foundations, which ties the new building
addition to the existing hospital. Cascade poured footings for both the drive-up entry canopy and the ambulance canopy. Steel for these canopies will be installed in the coming weeks. The rain affected scheduling for the concrete floor slab pour. The pour was scheduled for this Tuesday, but is delayed until early next week. While this is frustrating to the construction team, it is critical that concrete be installed under the right conditions. Proper installation will ensure that the building serves the community for decades to come. - John Parker, Project Manager jparker@elzinga-volkers.com
www.elzinga-volkers.com