Shore Front Parkway Reconstruction CRIA Statement Public Forum

Page 1

Shore Front Parkway Reconstruction CRIA Statement Public Forum January 17, 2024


Introduction  Closure of Shore Front

Parkway (formerly known as Edgemere Avenue) closed starting mid-July 2023 through beginning of 2025  NYCDOT, NYCHPD and

Applicant have been in communication with Community Board 14, elected officials, local organizations, PS 106Q and emergency services (FDNY, NYPD) prior to the closure


Need for the Project  Closure needed to implement

roadway widening and raising – Green infrastructure to increase resiliency and combat storm and nuisance flooding – Critical utility infrastructure upgrades – Elevate roadway from ~2 feet to 6 feet – Widen roadway to increase capacity

PS 106Q


Shore Front Parkway Facing East at Beach 38th Street

Shore Front Parkway Facing West at Beach 36th Street

Ponding along Shore Front Parkway


CRIA  CRIA Statement and Public

Forum needed for roadway closure exceeding 180 days  NYCDOT is lead agency for

preparation of the CRIA Statement


Maintenance and Protection of Traffic  MPT plans were reviewed and

approved by NYCDOT – Detour route signage and VMS implemented – Continued coordination with NYCDOT  PS 106Q

– Access maintain during construction – School crossing guard provided


PS 106Q

MPT Sign Signed Detour Route Alternative Detour Routes

Detour Routes and Signage


Traffic Study  Traffic analysis at 11 intersections

along detour routes during weekday AM, PM and Saturday peak hours  Increased delays during

construction: – Beach Channel Dr/Seagirt Boulevard – Eastbound Rockaway Freeway – Eastbound Shore Front Parkway left turns at Beach 41st Street  Safety analysis at traffic analysis

intersections


Traffic Improvements


Thank you. Questions?