Fault Analysis and Control of Grid Connected Wind Turbine Driving Squirrel Cage Induction Generator Mahmoud Essam M. Harby, Adel El Samahy, S.E. Elmasry All belong to Department of Electrical Power and Machines Engineering Faculty of Engineering, Helwan University, Egypt 1 Sherif Street, Helwan, P.O 11792 (Helwan, Egypt) ---------------------------------------------------------------------***---------------------------------------------------------------------

Abstract - This paper aims to simulate a wind turbine

created using MATLAB software that enables the dynamic and static simulations of electromagnetic and electromechanical systems where the three-phase squirrelcage induction generator is a standard model in MATLAB library. Table -1 and Table -2 show the main parameters of the proposed wind turbine and the three-phase squirrel-cage induction generator in this work respectively. The used gear box in this work was selected to extract the maximum power from the wind so all the results and analysis are taken at the rated wind speed 13 meter/sec.

model with three-phase squirrel-cage induction generator, the system is connected to the utility grid. It describes the simulation of a common fault (three phase fault) that occurs along the transmission line of the power system. The response of the wind turbine and the three-phase squirrel-cage induction generator are analyzed and discussed at different fault periods. Finally A transient fault ride through controller is designed to control and improve the system performance during and after fault occurrence, the controller is a simply PID controller tuned by genetic algorithm and is used to control the turbine blade pitch angle. Key Words: Transient fault, Wind turbine, Induction generator, Pitch angle controller.

1. INTRODUCTION Wind energy plays an important role in the world energy system nowadays and this role is going to be expanded due to the several benefits of the wind energy [1]. Before the accomplishment of a wind power project many pre-studies are required in order to verify the possibility of integrating of the wind power plant in the electrical network. In many countries the renewable energy plants especially the wind ones are going to be the alternative for the conventional power plants so they have to take over many of the control tasks to keep the power system stable [2]. One of these control tasks is to ride through the transient faults in the power system. This means that the generation mustn’t be lost due to the voltage excursions caused by transient faults. This paper introduces a survey of one of the most common line faults (three phase to ground fault) that may occur in the power system and the effect of the three phase to ground fault on the grid voltage and frequency.

Fig -1: Schematic Diagram of the System

2. WIND TURBINE MODELING Fig -1, Fig -2, and Fig -3 show schematic diagram of the system, the wind turbine model, and the three-phase squirrel-cage induction generator respectively [3]. The system is connected to the utility grid [4]. The model is

Š 2016, IRJET

|

Impact Factor value: 4.45

Fig -2: Matlab simulink model for the proposed wind turbine.

|

ISO 9001:2008 Certified Journal

|

Page 15


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.