Upper Balephi Hydropower Project

Page 1

UPPER BALEPHI HYDROPOWER PROJECT

SALIENT FEATURES SN

FEATURES

CHARACTERISTICS

GENERAL 1 2 3 4

Name of Project Type Install Capacity Progress

Upper Balephi Hydropower Project Run of River 46 MW Infrastructure Development (Access Road, Labor camp) construction work on progress

PROJECT LOCATION 1 2 3

Latitude of Project Area Longitude of Project Area Project Area

27° 58’ 59’’ N and 28° 01’ 23’’ N 85° 46’ 46’’E and 85° 48’ 03’’ E Jugal Rural Municipality, Sindhupalchowk, Province 3

TECHNICAL INFORMATION 1 2 3

Hydrology Catchment Area Design Discharge (Q 40 %) Weir and Intake No. of Intake Type of Weir Length Desanding Basin Type

270.38 km2 12.72 m3/s

Diversion weir with side intake 42 m Hopper Type, Single bay with Bypass channel