Risk Management in Cost Engineering[39457]

Page 1

Risk Management in Cost Engineering 1.0 Introduction Risk management is defined as the identification, evaluation, and prioritization of uncertainty on objectives. All novel engineering activity involves a degree of risk and the professional cost engineer is well-placed to be involved in initiating, developing and carrying out processes to ensure effective risk management. This paper is based on methods used on large oil & gas projects and may be useful in other industries, where budget, schedule, health, safety and the environment are critical. Risk management should be applied in the control of costs, from establishing the control estimate, the project schedule and change control, to delivery and lessons learned. Risks are not only negative: positive risks or opportunities should also have emphasis. The risk management process must involve all project stakeholders at all levels. Risk can be minimised by the use of decision gates. Prototypes are used in product development to develop ideas at low cost. In large project development, a Front End Engineering Design is often completed before commitment to detailed design. Subsequent decision gates are approved for distinct project phases, for example, before start of manufacture or construction. There are two main risk management evaluation approaches: Qualitative and quantitative methods. Qualitative methods are used for identifying and assigning priorities for health, safety and environmental risks and project risk registers (see fig.1). They are easier for non-experts to understand and thereby encourage participation. Quantitative methods are used for determining the size of cost and schedule contingencies using statistics. 2.0 The Control Estimate Cost control starts with the estimate and the consideration of risk. For small or repetitive projects of which the estimator has reasonable experience, a standard percentage may be applied to cover contingency. For large or critical projects a quantitative risk process, with a band of values for each estimate item, could be used to determine the contingency A typical issue at this stage, when limited time is available, is that priority has to be given to technical input from engineering, leaving insufficient time for the estimator’s work and proper checking procedures. Corporate management will have its own risk appetite depending on corporate policy, conditions of contract, and external market competition, which will affect the estimator’s approach. The estimator should be aware of this systemic or organisational risk, particularly if it is perceived by corporate management that the estimate is too high for the project to go ahead, or that it will be lost to a lower bidder. Unless this risk is properly considered, it may be interpreted as undue pressure on the estimator to reduce the estimate.


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.