1 minute read
Swing-away lattice 5.3 Checklists for rigging work
11. Swing the swing-away lattice until it comes free from the Front connection; à p.5-87.
12. Hold the swing-away lattice using the auxiliary crane.
13. Disconnect the slewing connection; à p.5-73.
14. Lift the swing-away lattice off the main boom and set it aside.
15. Remove the guide rope.
16. Fold in the run-up rail; à p.5-72.
17. Set the Front connection to the Locked position; à p.5-70.
18. Check that the swing-away lattice is secured for transport and secure it if necessary; à Transport condition – removed, p.5-8.
5.3.6 CHECKLIST: Rigging the swing-away lattice 1.8 + 9.4 m – in the operating position
HThis checklist is not a complete operating manual. There are accompanying instructions, which are indicated by cross-references. Observe the warnings and safety instructions there!
1. Prerequisite
–The truck crane is on outriggers and the superstructure is turned to the side or to the rear.
–The appropriate counterweight for the crane operation must be rigged; à GMK5150 / GMK5150L Operating Instructions.
–The main boom is fully retracted and locked. The telescoping cylinder must be locked in telescopic section V; à p.5-65.
The main boom is lowered to the horizontal position; à GMK5150 / GMK5150L Operating Instructions.
2. If necessary, mount the hose drum; à p.4-3
3. If necessary, check that the locking device has been released; à p.4-5.
4. If necessary, move the hoses into the position for working with the lattice extension; à p.4-6.
5. Check the transport condition of the swing-away lattice; à p.5-12.
6. Fold out the run-up rail;; à
7. For derricking swing-away lattice: –Connect the hand-held control; à p.3-13.
8. Fasten a guide rope to section2; à p.5-66.
9. For derricking swing-away lattice: Establish the hydraulic connection to the main boom; à p.5-89.
Swing-away lattice 5.3 Checklists for rigging work
10. Establish the electrical connection to the main boom; à p.5-91.
11. Disconnect the Folded connection between section1 and section2; à p.5-86.
12. Disconnect the electrical connection between section2 and section1; à p.5-99.
13. Separate the connection on the right-hand side between section1 and section2; à
16. For derricking swing-away lattice: –Lower the swing-away lattice to the end stop; à p.5-113.
20. For inclinable swing-away lattice: Set the angle position if necessary. –With auxiliary crane; à p.5-115, –Without auxiliary crane; à p.5-116.
21. Fold out the deflection sheaves. –On section2; à p.5-101. –On section4; à p.5-101.