Jake Jabs College of Business & Entrepeneurship Montana State University
JAKE JABS COLLEGE OF BUSINESS & ENTREPRENEURSHIP This new academic building at Montana State University located in Bozeman, Montana, provides state-of-the-art teaching facilities, formal and informal meeting areas, interactive learning centers, smart flexibility, and social gathering spaces. It is a campus destination encouraging entrepreneurial interaction between students and faculty of all disciplines. The following guiding principles were established for the project by the University and Design Team: • • • •
2
Foster a “Community of Professionals” Make a place for “Creating Knowledge and Exchanging Ideas” Create a building that is “Of its Place in Montana” Provide for “Multiple, Smart Uses.”
Building approach from southwest
3
PROJECT BACKGROUND In October 2011, the College of Business at Montana State University received a $25 million gift from alumnus Jake Jabs to “advance the College of Business, to make it one of the best in the nation.� The Jabs gift funded the design and construction of a new academic building, scholarships, and new academic programs. The new building would provide ample space for advising, classrooms, one-on-one work with students, and informal learning spaces, all of which were insufficient and dated in the existing academic building, Reid Hall. The end goal was to foster cooperative work between business students and students in other disciplines, including engineering, the sciences, agriculture, architecture, and humanities.
Photo of donor and alumnus Jake Jabs
4
Reid Hall, constructed in 1959
5
6
GREATER CONTEXT Montana State University is in the city of Bozeman, Montana. Bozeman is the “Valley of Flowers,� the nickname given to the lush landscape that sits in between the Bridger Mountains, the Tobacco Root Mountains, the Big Belt Mountains, the Gallatin Range, and the Madison Mountain Range.
The Bridger Mountains
7
CAMPUS CONTEXT Montana State University is the largest university in the state and was founded in 1893 as the Agricultural College of the State of Montana, less than four years after Montana became a state.
Historic image of Bozeman, Montana and MSU campus
8
Campus aerial looking northeast
9
SITE SELECTION SUMMARY To include the university community in the programming, site selection, and design of the new College of Business (CoB) building, the Building Committee enlisted several workgroups consisting of faculty, students, and staff. The workgroups identified, reviewed, and analyzed key criteria, including CoB goals, institutional mission, campus planning concepts, access to campus infrastructure, and accessibility, and then narrowed several prospective sites to three best suited for the facility. The Building Committee recommended the top three sites to the University Facilities Planning Board (UFPB) for final selection and approval by the President of the University. The process included participation and comment from both university and local community members through the CoB website, three public forums, and email contributions. Early in the process, the President identified the “North of Wilsonâ€? site as one with strong potential. Although its selection was met with concern from some within the campus community due an existing grove of trees on the site, it was ultimately chosen. The design team conducted a comparative analysis of all sites being considered and evaluated the potential for added cost due to grading and other factors relevant to each site. While several trees were removed to construct the building, others, including an allĂŠe of trees on axis with Cleveland Street, were carefully retained. In the final analysis, site grading resulted in little cost premium, and the site, with expansive south exposure and wonderful proximity to historic Montana Hall, brought activity to a previously empty part of campus.
10
Increase density within core
Bike and pedestrian paths
Create well defined outdoor space
North of Wilson Hamilton site South of Grant
0
450
900
11
SITE PLANNING Key drivers impacting how the building addressed the site included taking advantage of its south exposure, connections to Montana Hall, and the main north-south campus circulation to the pedestrian mall. The planning effort also considered existing trees, future expansion, and existing utility tunnels serving the campus.
Building massing and orientation studies
12
Aerial photograph of site
0
75
150
13
45,395 Gross SF Faculty | Office | Research
39,747 Gross SF
Student Services | Staff | Institutes Classrooms | Community Miscellaneous | Undefined
13,633 13,138
4,433
4,272 18,130 Gross SF
21,220 Existing Hennebery Eddy Architects Portland, OR
REID HALL COLLEGE OF Comma-Q Architecture Bozeman, MT BUSINESS (EXISTING)
Existing and proposed building square footage comparison
14
25,167 Draft New JAKE JABS NEW BUILDING (PROPOSED)
16,333 Additional AUDITORIUM ADDITION College of Business | Programming & Site Selection Report 25 April 2012 (FUTURE)
14
13'13' - 6"- 6"
FULL HEIGHT STORAGE FULL HEIGHT STORAGE
AV CART
BREAKOUT ROOM - MEDIUM BREAKOUT ROOM - MEDIUM
CONFERENCE CONFERENCE ROOM - SMALL ROOM - SMALL
22' - 6" 22' - 6"
11' - 0" 11' - 0"
FULL HEIGHT STORAGE FULL HEIGHT STORAGE
10' - 0" 10' - 0"
16' - 0" 16' - 0"
STORAGE STORAGE
10' - 0" 10' - 0"
PROJECTION SCREEN 10'-0"
DEAN'S SUITE DEAN'S SUITE
FULL HEIGHT STORAGE FULL HEIGHT STORAGE
0 2’ 4’ 10' - 0" 10' - 0"
10' - 0" 10' - 0"
24' - 0" WHITEBOARD
FULL HEIGHT STORAGE FULL HEIGHT STORAGE
15
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
STORAGE STORAGE
AV CART AV CART
AV CART
AV CART AV CART
DEAN'S SUITE DEAN'S SUITE
20' - 0" 20' - 0"
WHITE BOARD WHITE 20'BOARD - 0" 20' - 0" 60"60" MONITOR MONITOR
60"60" MONITOR MONITOR
24' - 0" WHITEBOARD
WHITEBOARD WHITEBOARD
PROJECTION PROJECTION SCREEN SCREEN 10'10' - 0"-24' 0"24' - 0"- 0"
60"60" MONITOR MONITOR
60"60" MONITOR MONITOR
35'35' - 0"- 0"
31'31' - 0"- 0"
12'12' - 0"- 0" WHITE WHITE BOARD BOARD 12'12' - 0"- 0" WHITE BOARD WHITE BOARD
22' - 6" 22' - 6"
8’
OPTIONAL MOVEABLE WALL
31'31' - 0"- 0"
12'12' - 0"- 0" 27'27' - 0"- 0" WHITE WHITE BOARD BOARD
10'10' - 0"- 0" WHITEBOARD WHITEBOARD
PROJECTION SCREEN 10'-0"
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
WHITE WHITE BOARD BOARD 20'20' - 0"- 0"
60"60" MONITOR MONITOR
60"60" MONITOR MONITOR
60"60" MONITOR MONITOR
60"60" MONITOR MONITOR
27'27' - 0"- 0"
10'10' - 0"- 0" WHITEBOARD WHITEBOARD
60"60" MONITOR MONITOR
60"60" MONITOR MONITOR
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
60"60" MONITOR MONITOR
AVAV CART CART
AVAV CART CART
31'31' - 0"- 0"
60"60" MONITOR MONITOR
60"60" MONITOR MONITOR
60"60" MONITOR MONITOR
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
WHITE WHITE BOARD BOARD 20'20' - 0"- 0"
60"60" MONITOR MONITOR
60"60" MONITOR MONITOR
31'31' - 0"- 0"
12'12' - 0"- 0" 27'27' - 0"- 0" WHITE WHITE BOARD BOARD
10'10' - 0"- 0" WHITEBOARD WHITEBOARD
WHITEBOARD WHITEBOARD
35'35' - 0"- 0"
31'31' - 0"- 0"
12'12' - 0"- 0" WHITE WHITE BOARD BOARD 12'12' - 0"- 0" WHITE WHITE BOARD BOARD
24'24' - 0"- 0" WHITEBOARD WHITEBOARD
PROJECTION PROJECTION SCREEN SCREEN 10'10' - 0"24' - 0"24' - 0"- 0"
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0" PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
60"60" MONITOR MONITOR
60"60" MONITOR MONITOR
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
60"60" MONITOR MONITOR
60"60" MONITOR MONITOR
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
60"60" MONITOR MONITOR
WHITE BOARD WHITE 20'BOARD - 0" 20' - 0"
31'31' - 0"- 0"
12'12' - 0"- 0" 27'27' - 0"- 0" WHITE WHITE BOARD BOARD
10'10' - 0"- 0" WHITEBOARD WHITEBOARD
AVAV CART CART
20'20' - 0"- 0"
32' - 0" 32' - 0"
60"60" MONITOR MONITOR
60"60" MONITOR MONITOR
WHITEBOARD WHITEBOARD
60"60" MONITOR MONITOR
60"60" MONITOR MONITOR
PROJECTION SCREEN 10'-0"
PROJECTION PROJECTION SCREEN SCREEN 10'10' - 0"-24' 0"24' - 0"- 0"
35'35' - 0"- 0"
31'31' - 0"- 0"
12'12' - 0"- 0" WHITE WHITE BOARD BOARD 12'12' - 0"- 0" WHITE WHITE BOARD BOARD
35' - 0" 35' - 0"
12'12' - 6"- 6"
BREAKOUT ROOM - SMALL BREAKOUT ROOM WALL - SMALL WITH SLIDING WITH SLIDING WALL
AV CART
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
WHITE WHITE BOARD BOARD 20'20' - 0"- 0"
60"60" MONITOR MONITOR
60"60" MONITOR MONITOR
AV CART AV CART
13'13' - 6"- 6"
60"60" MONITOR MONITOR
SLIDING SLIDING WALL WALL
60"60" MONITOR MONITOR
60"60" MONITOR MONITOR
60"60" MONITOR MONITOR
PROJECTION SCREEN PROJECTION SCREEN 10'-0" 10'-0" PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
32' - 0" 32' - 0"
10'10' - 0"- 0" WHITEBOARD WHITEBOARD
PROJECTION SCREEN 10'-0"
AV CART AV CART
PROJECTION SCREEN 10'-0"
31'31' - 0"- 0"
12'12' - 0"- 0" WHITE WHITE BOARD BOARD
27'27' - 0"- 0"
10'10' - 0"- 0" WHITEBOARD WHITEBOARD
24'24' - 0"- 0" WHITEBOARD WHITEBOARD
24'24' - 0"- 0" WHITEBOARD WHITEBOARD
35'35' - 0"- 0"
12'12' - 0"- 0" WHITE WHITE BOARD BOARD
24'24' - 0"- 0" WHITEBOARD WHITEBOARD
AVAV CART CART
AVAV CART CART
32' - 0" 32' - 0"
8' -8'0"- 0"
10'10' - 0"- 0"
PROJECTION SCREEN 10'-0"
16' - 0" 16' - 0"
24' - 0" WHITEBOARD 60"60"MONITOR MONITOR
CONFERENCE CONFERENCE ROOM - SMALL ROOM - SMALL
35' - 0"
11'11' - 0"- 0"
8' -8'0"- 0" WHITE WHITE BOARD BOARD
31'31' - 0"- 0"
60"60" MONITOR MONITOR
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0" PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
60"60" MONITOR MONITOR
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
60"60" MONITOR MONITOR
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
60"60" MONITOR MONITOR
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
24'24' - 0"- 0" WHITEBOARD WHITEBOARD
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
OPTIONAL MOVEABLE WALL OPTIONAL MOVEABLE WALL
11'11' - 0"- 0"
CONFERENCE CONFERENCE ROOM - SMALL ROOM - SMALL
60"60" MONITOR MONITOR
60" MONITOR
27'27' - 0"- 0"
60"60" MONITOR MONITOR
AVAV CART CART
60"60" MONITOR MONITOR
60"60" MONITOR MONITOR
AVAV CART CART
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
24'24' - 0"- 0" WHITEBOARD WHITEBOARD
31'31' - 0"- 0"
12'12' - 0"- 0" WHITE WHITE BOARD BOARD
24'24' - 0"- 0" WHITEBOARD WHITEBOARD
35'35' - 0"- 0"
12'12' - 0"- 0" WHITE WHITE BOARD BOARD
60"60" MONITOR MONITOR
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
60"60" MONITOR MONITOR
AVAV CART CART
60"60" MONITOR MONITOR
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
60"60" MONITOR MONITOR
31'31' - 0"- 0"
12'12' - 0"- 0" WHITE WHITE BOARD BOARD
24'24' - 0"- 0" WHITEBOARD WHITEBOARD
35'35' - 0"- 0"
12'12' - 0"- 0" WHITE WHITE BOARD BOARD
60"60" MONITOR MONITOR
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
60"60" MONITOR MONITOR
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
AVAV CART CART
OPTIONAL MOVEABLE WALL OPTIONAL MOVEABLE WALL
FULL FULL HEIGHT HEIGHT STORAGE STORAGE
BREAKOUT ROOM - MEDIUM BREAKOUT ROOM - MEDIUM 11'11' - 0"- 0"
10' - 0" 10' - 0"
WHITE BOARD WHITE 20'BOARD - 0" 20' - 0"
60"60" MONITOR MONITOR
AV CART AV CART
PROJECTION SCREEN 10'-0"
24' - 0" 24' - 0" WHITEBOARD WHITEBOARD
31'31' - 0"- 0"
32' - 0" 32' - 0" 8' -8'0"- 0" WHITE WHITE BOARD BOARD
10' - 0" 10' - 0"
60"60" MONITOR MONITOR
12' - 0" WHITE BOARD
CONFERENCE CONFERENCE ROOM - SMALL ROOM - SMALL
11'11' - 0"- 0"
BREAKOUT ROOM - SMALL BREAKOUT ROOM - SMALL
12'12' - 0"- 0" WHITE WHITE BOARD BOARD
8' -8'0"- 0" WHITE WHITE BOARD BOARD
13'13' - 6"- 6"
10'10' - 0"- 0" WHITEBOARD WHITEBOARD
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0" PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
24' - 0" 24' - 0" WHITEBOARD WHITEBOARD
FULL FULL HEIGHT HEIGHT STORAGE STORAGE
50- Seat Flex Classroom 1250 35' - 0" SF 24' - 0" 24' - 0" WHITEBOARD WHITEBOARD
AV CART
BREAKOUT ROOM - SMALL BREAKOUT ROOM WALL - SMALL WITH SLIDING WITH SLIDING WALL
11' - 0" 11' - 0"
AV CART AV CART
WHITEBOARD
20' - 0" 20' - 0"
24'24' - 0"- 0" WHITEBOARD WHITEBOARD
OPTIONAL MOVEABLE WALL OPTIONAL MOVEABLE WALL
11'11' - 0"- 0"
10' - 0" 10' - 0"
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
28' - 0" 28' - 0"
60"60" MONITOR MONITOR
24' - 0" 24' - 0" WHITEBOARD WHITEBOARD
60" MONITOR
28' - 0" 28' - 0" 60"60" MONITOR MONITOR
AV CART AV CART
24' - 0" 24' - 0" WHITEBOARD WHITEBOARD
PROJECTION SCREEN 10'-0"
CONFERENCE CONFERENCE ROOM - SMALL ROOM - SMALL
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
28' - 0" 28' - 0"
60"60" MONITOR MONITOR
35' - 0" AVAV CART CART
32' - 0" 32' - 0"
12'12' - 6"- 6"
OPTIONAL MOVEABLE WALL
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
WHITE BOARD WHITE 20'BOARD - 0" 20' - 0"
10'10' - 0"- 0" WHITEBOARD WHITEBOARD
24'24' - 0"- 0" WHITEBOARD WHITEBOARD
35'35' - 0"- 0"
PROJECTION PROJECTION SCREEN SCREEN 10'10' - 0"- 0"
31'31' - 0"- 0"
12'12' - 0"- 0" WHITE WHITE BOARD BOARD
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
35' - 0" 35' - 0"
AV CART AV CART
PROJECTION SCREEN 10'-0" 24' - 0"
51 24'24' - 0"- 0" WHITEBOARD WHITEBOARD
28' - 0" 28' - 0"
24' - 0" 24' - 0" WHITEBOARD WHITEBOARD
24' - 0" WHITEBOARD
10' - 0" 10' - 0" 22' - 0" 22' - 0"
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
60"60" MONITOR MONITOR
WHITE WHITE BOARD BOARD
12'12' - 0"- 0" 20'20' - 0"- 0" WHITE BOARD WHITE BOARD
60"60" MONITOR MONITOR
24'24' - 0"- 0" WHITEBOARD WHITEBOARD
PROJECTION SCREEN PROJECTION SCREEN 10'-0" 10'-0"
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
24'24' - 0"- 0" WHITEBOARD WHITEBOARD
AV CART AV CART
35' - 0"
CONFERENCE CONFERENCE ROOM - SMALL ROOM - SMALL
24'24' - 0"- 0" WHITEBOARD WHITEBOARD
35' - 0" 35' - 0"
8' -8'0"- 0"
35' - 0" 35' - 0"
OPTIONAL MOVEABLE WALL OPTIONAL MOVEABLE WALL
60"60" MONITOR MONITOR
OPTIONAL MOVEABLE WALL
60" MONITOR
Early program organization and massing concepts
BREAKOUT ROOM - SMALL BREAKOUT ROOM - SMALL
60"60" MONITOR MONITOR
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
AV CART AV CART
35' - 0" 35' - 0"
AV CART AV CART
In comparison to existing space uses at Reid Hall, most program growth occurred in classroom and informal learning environments. A desire to wrap classrooms, faculty offices and student services around unprogrammed informal learning space generated the concept of a student forum. It was decided that a mix of classrooms and offices on each floor of the building would provide for greater interaction between faculty and students. OPTIONAL MOVEABLE WALL OPTIONAL MOVEABLE WALL
12' - 0" WHITE BOARD
BREAKOUT ROOM - SMALL BREAKOUT ROOM WALL - SMALL WITH SLIDING WITH SLIDING WALL 35'35' - 0"- 0"
PROJECTION PROJECTION SCREEN SCREEN 10'10' - 0"- 0"
60"60" MONITOR MONITOR
AVAV CART CART
60"60" MONITOR MONITOR
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
35' - 0" 35' - 0"
FULL FULL HEIGHT HEIGHT STORAGE STORAGE
11' - 0" 11' - 0"
WHITE BOARD WHITE 20'BOARD - 0" 20' - 0"
10'10' - 0"- 0"
20'20' - 0"- 0"
60"60" MONITOR MONITOR
WHITE WHITE BOARD BOARD 20'20' - 0"- 0"
31'31' - 0"- 0"
12'12' - 0"- 0" WHITE WHITE BOARD BOARD
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
35'35' - 0"- 0"
12'12' - 0"- 0" WHITE WHITE BOARD BOARD
24'24' - 0"- 0" WHITEBOARD WHITEBOARD
32' - 0" 32' - 0"
11'11' - 0"- 0"
AVAV CART CART
24' - 0" 24' - 0" WHITEBOARD WHITEBOARD
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
60"60" MONITOR MONITOR
12'12' - 0"- 0" WHITE WHITE BOARD BOARD
60"60" MONITOR MONITOR
24'24' - 0"- 0" WHITEBOARD WHITEBOARD
24' - 0" 24' - 0" WHITEBOARD WHITEBOARD
24'24' - 0"- 0" WHITEBOARD WHITEBOARD
28' - 0" 28' - 0"
35'35' - 0"- 0"
PROJECTION PROJECTION SCREEN SCREEN 10'10' - 0"- 0"
60"60" MONITOR MONITOR
60"60" MONITOR MONITOR
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
60"60" MONITOR MONITOR
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
24' - 0" 24' - 0" WHITEBOARD WHITEBOARD
10'10' - 0"- 0" WHITEBOARD WHITEBOARD
60"60" MONITOR MONITOR
AV CART AV CART
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
32' - 0" 32' - 0"
60"60" MONITOR MONITOR
WHITE WHITE BOARD BOARD 20'20' - 0"- 0"
31'31' - 0"- 0"
12'12' - 0"- 0" 27'27' - 0"- 0" WHITE WHITE BOARD BOARD
10'10' - 0"- 0" WHITEBOARD WHITEBOARD
AV CART AV CART
35'35' - 0"- 0"
32' - 0" 32' - 0"
12'12' - 0"- 0" WHITE WHITE BOARD BOARD
60"60" MONITOR MONITOR
60"60" MONITOR MONITOR
24'24' - 0"- 0" WHITEBOARD WHITEBOARD
60"60" MONITOR MONITOR
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
OPTIONAL MOVEABLE WALL OPTIONAL MOVEABLE WALL
13'13' - 6"- 6"
60"60" MONITOR MONITOR
60"60" MONITOR MONITOR
60"60" MONITOR MONITOR
AVAV CART CART
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
32' - 0" 32' - 0"
60"60" MONITOR MONITOR
60"60" MONITOR MONITOR
31'31' - 0"- 0"
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
24' - 0" 24' - 0" WHITEBOARD WHITEBOARD
60"60" MONITOR MONITOR
22' - 6" 22' - 6"
AV CART AV CART
11'11' - 0"- 0"
WHITE BOARD WHITE 20'BOARD - 0" 20' - 0"
8' -8'0"- 0" WHITE WHITE BOARD BOARD
35' - 0" 35' - 0"
SLIDING SLIDING WALL WALL
32' - 0" 32' - 0" 12'12' - 0"- 0" 27'27' - 0"- 0" WHITE WHITE BOARD BOARD
WHITEBOARD WHITEBOARD
PROJECTION PROJECTION SCREEN SCREEN 10'10' - 0"24' - 0"24' - 0"- 0"
35'35' - 0"- 0"
12'12' - 0"- 0" WHITE WHITE BOARD BOARD
24'24' - 0"- 0" WHITEBOARD WHITEBOARD
32' - 0" 32' - 0"
FULL FULL HEIGHT HEIGHT STORAGE STORAGE
OPTIONAL MOVEABLE WALL OPTIONAL MOVEABLE WALL
AV CART AV CART
11'11' - 0"- 0"
8' -8'0"- 0" WHITE WHITE BOARD BOARD
Alternate Configurations 10'10' - 0"- 0" WHITEBOARD WHITEBOARD
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
Alternate Configurations 35' - 0" 35' - 0"
12'12' - 0"- 0" WHITE WHITE BOARD BOARD
AV CART AV CART
60"60" MONITOR MONITOR
32' - 0" 32' - 0"
60"60" MONITOR MONITOR
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
OPTIONAL MOVEABLE WALL OPTIONAL MOVEABLE WALL
60"60" MONITOR MONITOR
51
60"60" MONITOR MONITOR
24'24' - 0"- 0" WHITEBOARD WHITEBOARD
WHITE BOARD WHITE 20'BOARD - 0" 20' - 0"
31'31' - 0"- 0"
AVAV CART CART
Note: Not to Scale
12'12' - 0"- 0" 27'27' - 0"- 0" WHITE WHITE BOARD BOARD
WHITE BOARD WHITE 20'BOARD - 0" 20' - 0"
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
AV CART AV CART
10'10' - 0"- 0" WHITEBOARD WHITEBOARD
WHITEBOARD WHITEBOARD
PROJECTION PROJECTION SCREEN SCREEN 10'10' - 0"-24' 0"24' - 0"- 0"
AV CART AV CART
60"60" MONITOR MONITOR
60"60" MONITOR MONITOR
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
35' - 0" 35' - 0"
PROJECTION SCREEN 10'-0"
32' - 0" 32' - 0"
13'13' - 6"- 6"
35' - 0" 35' - 0"
24' - 0" WHITEBOARD
32' - 0" 32' - 0"
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
60"60" MONITOR MONITOR
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
OPTIONAL MOVEABLE WALL OPTIONAL MOVEABLE WALL
60"60" MONITOR MONITOR
AVAV CART CART
60"60" MONITOR MONITOR
60"60" MONITOR MONITOR
35' - 0" 35' - 0"
60"60" MONITOR MONITOR
AV CART AV CART
24'24' - 0"- 0" WHITEBOARD WHITEBOARD
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
35'35' - 0"- 0"
31'31' - 0"- 0"
12'12' - 0"- 0" WHITE WHITE BOARD BOARD 12'12' - 0"- 0" WHITE WHITE BOARD BOARD
AVAV CART CART
AV CART AV CART
PROJECTION SCREEN 10'-0"
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
WHITEBOARD WHITEBOARD
PROJECTION PROJECTION SCREEN SCREEN 10'10' - 0"-24' 0"24' - 0"- 0"
60"60" MONITOR MONITOR
60"60" MONITOR MONITOR
WHITE WHITE BOARD BOARD 20'20' - 0"- 0"
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0" PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
AV CART AV CART
60" MONITOR
32' - 0" 32' - 0" PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
60"60" MONITOR MONITOR
60"60" MONITOR MONITOR
24'24' - 0"- 0" WHITEBOARD WHITEBOARD
35' - 0" 35' - 0"
10'10' - 0"- 0" WHITEBOARD WHITEBOARD
24' - 0" 24' - 0" WHITEBOARD WHITEBOARD
35' - 0" 35' - 0"
11'11' - 0"- 0"
24' - 0" 24' - 0" WHITEBOARD WHITEBOARD 35'35' - 0"- 0"
31'31' - 0"- 0"
12'12' - 0"- 0" WHITE WHITE BOARD BOARD 12'12' - 0"- 0" WHITE BOARD WHITE BOARD
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0" PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
AV CART AV CART
13'13' - 6"- 6"
60"60" MONITOR MONITOR
60"60" MONITOR MONITOR
WHITE WHITE BOARD BOARD 20'20' - 0"- 0"
AVAV CART CART
24' - 0" 24' - 0" WHITEBOARD WHITEBOARD
60"60" MONITOR MONITOR
60"60" MONITOR MONITOR
60"60" MONITOR MONITOR
PROJECTION SCREEN PROJECTION SCREEN 10'-0" 10'-0" PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
60"60" MONITOR MONITOR
24' - 0" 24' - 0" WHITEBOARD WHITEBOARD
OPTIONAL MOVEABLE WALL OPTIONAL MOVEABLE WALL
8' -8'0"- 0" WHITE WHITE BOARD BOARD
35' - 0" 35' - 0" 35'35' - 0"- 0"
31'31' - 0"- 0"
12'12' - 0"- 0" WHITE WHITE BOARD BOARD 12'12' - 0"- 0" WHITE WHITE BOARD BOARD
24'24' - 0"- 0" WHITEBOARD WHITEBOARD
24'24' - 0"- 0" WHITEBOARD WHITEBOARD
35'35' - 0"- 0"
12'12' - 0"- 0" WHITE WHITE BOARD BOARD
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
AV CART AV CART
12'12' - 6"- 6"
OPTIONAL MOVEABLE WALL OPTIONAL MOVEABLE WALL 24' - 0" 24' - 0" WHITEBOARD WHITEBOARD 60"60" MONITOR MONITOR
60"60" MONITOR MONITOR
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0" PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
60"60" MONITOR MONITOR
24'24' - 0"- 0" WHITEBOARD WHITEBOARD
OPTIONAL MOVEABLE WALL OPTIONAL MOVEABLE WALL
10'10' - 0"- 0" WHITEBOARD WHITEBOARD
BREAKOUT ROOM - SMALL BREAKOUT ROOM - SMALL
PROJECTION SCREEN 10'-0"
OPTIONAL MOVEABLE WALL OPTIONAL MOVEABLE WALL WHITE WHITE BOARD BOARD 20'20' - 0"- 0"
OPTIONAL MOVEABLE WALL OPTIONAL MOVEABLE WALL
60"60" MONITOR MONITOR
35' - 0" 35' - 0"
SLIDING SLIDING WALL WALL
AVAV CART CART
60"60" MONITOR MONITOR
OPTIONAL MOVEABLE WALL OPTIONAL MOVEABLE WALL
31'31' - 0"- 0"
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0" PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
24'24' - 0"- 0" WHITEBOARD WHITEBOARD
35'35' - 0"- 0"
12'12' - 0"- 0" WHITE BOARD WHITE BOARD
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
AV CART AV CART
24' - 0" WHITEBOARD 60"60"MONITOR MONITOR
12'12' - 0"- 0" WHITE WHITE BOARD BOARD
24'24' - 0"- 0" WHITEBOARD WHITEBOARD
60"60" MONITOR MONITOR
PROJECTION SCREEN PROJECTION SCREEN 10'-0" 10'-0"
35' - 0" 35' - 0"
13'13' - 6"- 6"
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0" PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
60"60" MONITOR MONITOR
24'24' - 0"- 0" WHITEBOARD WHITEBOARD
OPTIONAL MOVEABLE WALL OPTIONAL MOVEABLE WALL
60"60" MONITOR MONITOR
11' - 0" 11' - 0"
60"60" MONITOR MONITOR
AVAV CART CART
24'24' - 0"- 0" WHITEBOARD WHITEBOARD
35'35' - 0"- 0"
12'12' - 0"- 0" WHITE WHITE BOARD BOARD
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
OPTIONAL MOVEABLE WALL OPTIONAL MOVEABLE WALL
8' -8'0"- 0"
10'10' - 0"- 0"
AV CART AV CART
PROJECTION SCREEN 10'-0"
60"60" MONITOR MONITOR
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
10'10' - 0"- 0" WHITEBOARD WHITEBOARD
AV CART AV CART
24'24' - 0"- 0" WHITEBOARD WHITEBOARD
60"60" MONITOR MONITOR
OPTIONAL MOVEABLE WALL OPTIONAL MOVEABLE WALL
60"60" MONITOR MONITOR
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
60"60" MONITOR MONITOR
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
35' - 0" 35' - 0"
31'31' - 0"- 0"
AVAV CART CART
35'35' - 0"- 0"
12'12' - 0"- 0" WHITE WHITE BOARD BOARD
24'24' - 0"- 0" WHITEBOARD WHITEBOARD
OPTIONAL MOVEABLE WALL OPTIONAL MOVEABLE WALL
12'12' - 0"- 0" WHITE WHITE BOARD BOARD
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
60"60" MONITOR MONITOR
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0" AV CART AV CART
24'24' - 0"- 0" WHITEBOARD WHITEBOARD
60"60" MONITOR MONITOR
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0" AV CART AV CART
60"60" MONITOR MONITOR
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
35'35' - 0"- 0"
12'12' - 0"- 0" WHITE WHITE BOARD BOARD
24'24' - 0"- 0" WHITEBOARD WHITEBOARD
OPTIONAL MOVEABLE WALL OPTIONAL MOVEABLE WALL
13'13' - 6"- 6"
60"60" MONITOR MONITOR
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
Central Forum
60"60" MONITOR MONITOR
11' - 0" 11' - 0"
SLIDING SLIDING WALL WALL
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
Note: Not to Scale
60"60" MONITOR MONITOR
24'24' - 0"- 0" WHITEBOARD WHITEBOARD
Hinged Forum
60"60" MONITOR MONITOR
PROJECTION PROJECTION SCREEN SCREEN 10'-0" 10'-0"
Split Forum
10'10' - 0"- 0" WHITEBOARD WHITEBOARD
PROGRAMMING 35' - 0" 35' - 0"
24' - 0" 24' - 0" WHITEBOARD WHITEBOARD
32' - 0" 32' - 0"
24' - 0" 24' - 0" WHITEBOARD WHITEBOARD
32' - 0" 32' - 0"
35' - 0" 35' - 0"
28' - 0" 28' - 0" 24' - 0" 24' - 0" WHITEBOARD WHITEBOARD
32' - 0" 32' - 0"
28' - 0" 28' - 0"
35' - 0" 35' - 0" 32' - 0" 32' - 0"
28' - 0" 28' - 0" 24' - 0" 24' - 0" WHITEBOARD WHITEBOARD
32' - 0" 32' - 0"
OPTIONAL MOVEABLE WALL
WHITE BOARD WHITE 20'BOARD - 0" 20' - 0"
AV CART AV CART
22' - 0" 22' - 0"
28' - 0" 28' - 0" 24' - 0" 24' - 0" WHITEBOARD WHITEBOARD
32' - 0" 32' - 0"
32' - 0" 32' - 0"
AV CART
OPTIONAL MOVEABLE WALL
50- S
WH
16' - 0" 16' - 0"
STORAGE STORAGE
BREAKOUT ROOM - MEDIUM BREAKOUT ROOM - MEDIUM
22' - 6" 22' - 6" 11' - 0" 11' - 0"
11' - 0" 11' - 0"
FULL HEIGHT STORAGE FULL HEIGHT STORAGE
AV CART
DEAN'S SUITE DEAN'S SUITE
20' - 0" 20' - 0"
WH
THE FORUM The forum would become the key central open space around which the project is organized, providing the following opportunities: • • • • •
16
Unprogrammed, informal learning and gathering spaces Warmth of the hearth Connection between floors Transparency between active spaces and classrooms Frontage for Student services, Academic centers, and the M-Lab collaboration space.
17
18
DESIGN INSPIRATION Inspiration for the building was taken from the site, campus, surrounding landscapes, and geological features. Located in Big Sky Country, it was critical for the building to connect to nature, so the design strategically incorporates views to the Bridger, Gallatin and Tobacco Root Mountains. Classrooms, offices, and study spaces were carefully organized to offer visual connections not only of campus, but to Bozeman and the Gallatin Valley.
19
20
Massing model studies
21
22
23
FINAL PARTI A range of building forms were explored in sketch and study model form in search of a diagram benefiting both the program and site. The final parti – truly a napkin sketch – places classrooms at the south, a bar of faculty offices and administration at the north, and open forum spaces housing informal learning and gathering spaces in the middle. This organization is functional and environmental: deep, generously glazed classrooms on the south allow for sunlight and good temperature control, and smaller offices to the north with modest punched windows control heat loss while providing ample daylight in these shallower spaces. Widening the central forum space at the west created a generous and welcoming entry and dynamic spaces within.
24
0
81
6
32
Plan development from parti sketch
25
26
Design development study model
27
Concept renderings of forum hearth
28
FIREPLACE HEARTHS An early version of the hearths’ design included a porcelain tile surround, reminiscent of the building’s terracotta exterior, set in a playfully textured plaster backdrop. The design team later determined that these hearths needed to not only anchor the spaces they served programmatically, but physically. This realization spawned what would become a contemporary take on a traditional fireplace. Basalt stone sourced from Montana’s Flathead Valley forms the fire box and core of the hearths, while a field of rift cut white oak panels provides visual warmth to the overall space.
Material studies of forum hearth
29
SKETCHES & STUDIES After finalizing the formal parti for the building design, the design team studied a range of options for material distribution, solar shading and the configuration of the main building entry.
30
31
FRITTED GLASS While ample natural light, a dramatic connection and views to the west from the entry and forum spaces on upper floors were programmatic goals, reducing solar gain and glare at this frontage provided a comfortable learning environment. The CoB and University as a whole focus on serving students from Montana; in recognition, a large fritted glass map of the state flanks the main entry doors. At night, the glass wall glows from within, and allows filtered light into the building during the day. At the upper levels above the entry, deep blue glass (blue and gold are the school colors) helps reduce glare.
32
Concept rendering of main building entry
33
13
INTEGRATION INTO CAMPUS Jabs Hall (1) sits at the intersection of two important axial campus pathways. The north-south path, west of the project site, is bookended at the north by a principal campus entry point from Harrison Street and at the south by historic Montana Hall (2). The design team set the building back from this pathway the same distance as the Chemistry/Biochemistry building (4) to the west, maintaining the formal character of the north-south campus axis. The building also holds the northern edge of the east-west pedestrian path, reinforcing the connection between Herrick Hall (9) and Linfield Hall, both venerable historic buildings. A more contemporary addition to campus, “Spirit” the bobcat sculpture (15), sits at the intersection of the two axes. Lastly, the building screens the existing surface parking to the north when approached from the core of campus to the south.
5
4
LEGEND 1
Jabs Hall
2
Montana Hall
3
Leon Johnson Hall
4
Chemistry & Biochemistry Building
5
Chemistry Modular Building
6
Wilson Hall
7
Hamilton Hall
8
Hapner Hall
9
Herrick Hall
10 Danforth Chapel 11 Atkinson Quadrangle 12 Hannon Hall 13 Langford Residence Hall 14 Culbertson Hall 15 “Spirit” the Bobcat Sculpture
34
3
14
8
S. 7TH AVENUE
S. 8TH AVENUE
W. HARRISON STREET
11
W. CLEVELAND STREET
1
9
15
6 12
10
2
7
0
35
70
140
SUSTAINABLE DESIGN Jabs Hall is a LEED Gold® Certified building. It employs several energy saving strategies including daylight harvesting, low-flow plumbing fixtures, LED lighting, recycled materials, and locally sourced stone, and has a 100-year building skin. A geo-exchange field is made up of 52 wells, each consisting of 1,000 feet of tubing encased in concrete to a depth of 500 feet to take advantage of 50-60 degree subterranean temperatures. In summer, warm fluid is sent down the tubes to cool off, and in winter, cool fluid is sent down to be warmed. Additionally, a transpired passive solar wall preheats fresh air coming into the building, reducing the amount of energy needed to heat the building. Both the geo-exchange field and solar wall are integrated into a university district energy system including three other buildings. This enables Jabs Hall to share resources as well as harvest excess heat from adjacent lab buildings. The building’s concrete floors and shear walls provide thermal mass. When coupled with a night flush system, flooding the building with cool night air in the summer, it reduces the demand on the building’s mechanical cooling system during the day. Passive strategies include a combination of deep recesses and horizontal louvers along the south façade, providing protection from mid-day summer sun. Fixed sun-shades at the east and west facades allow these facades to selfshade when sun angles are low in the early morning and late afternoon.
36
Geo-exchange wells
chem/biochem bldg
jabs hall
Geo-exchange (heating and cooling) Heated water Chilled water wilson hall
Heat pump plant allows energy transfer
leon johnson hall
Campus steam 5
2
1
3
4
LEGEND 1 Passive solar wall 2 Night flush
ET 500 FE
3 Sun-shades 4 Geo-exchange wells 5 District energy
37
6 3
2
4
7
5
Fourth floor 2
3
2
3
2 6
7
4
2
5
Third floor 6
2
1
6
4
5
Second floor
38
3
3
3
3
3
3
3
3
3
4
3
4 7
1
4
4
5 5
LEGEND 1 Forum
L2 EVEL 1Room PLAN Conference forum 3 Office conference room 4 Support / Storage support/storage 5 Classroom classroom 6 Flex / Informal Space
7 Hearth 0'
4'
hearth
8'
16'
1 2 3 4 5 6 7 32'
First floor
0
8
16
32
39
West elevation
40
South elevation
41
42
Concept rendering viewed from Montana Hall
43
INTERIOR SPACES A grand stair connects the main entry, the two-story ground floor forum space, and hearth to another more modest two-story forum on the third and fourth floors. Classrooms, offices, academic centers, student services, and collaboration spaces are connected to the forum spaces through extensive glazing. Operable glass partitions allow the large ground floor classrooms to open to the forum for events like career fairs and university celebrations. Additionally, the “M-Lab� collaboration space on the second floor opens to the forum space increasing capacity and connectivity.
Concept renderings of main stair and forum
44
45
3
1
4
2
5
6
46
7
11
9
8
10
12
47
Terracotta installation on north side of building
48
OPERABLE WINDOW SYSTEM SILL FLASHING BENT STEEL PLATE
METAL FRAMING BATT INSULATION EXTERIOR SHEATHING WEATHER BARRIER THERMALLY BROKEN Z-GIRT
MINERAL FIBER INSULATION SUB-GIRTS AND CLIPS TERRACOTTA UNIT
Terracotta detail at window sill
49
50
51
South facade
52
Main entry plaza at southwest end of site
53
54
North facade
55
Approach from north, with Montana Hall beyond
56
NORTH BAR The office bar at the north side of the building is clad with terracotta panels in colors referential to the masonry of Montana Hall – the most iconic and historic structure on campus. The rich stratified pattern of the terracotta, offset by the classroom spaces clad in dark vertical zinc panels, emulates the geology of the Bridger Mountains, the greater Yellowstone region, and Gallatin basin.
57
The forum looking east
58
THE FORUM The forum spaces are the collaboration hub of the building. The forums offer informal seating at the hearth spaces and technology-driven collaboration spaces with ample power, strong WIFI and writable surfaces. The open grand stair knits all four floors of the building together.
Grand stair
59
SUNNY SOUTHWEST CORNER A student study area flanks the main building entry and is adjacent to the forum space. Sliding glass walls open to the sunny south-facing plaza, bringing the outside in and the inside out.
60
61
M-LAB Purposely located at the building’s most visible corner, the “M-Lab” takes advantage of the building’s transparency to show off inside activity. The M-Lab is technology rich, includes an overhead pipe grid to facilitate installations and projects, has flexible furniture and equipment for a variety of setups, and its operable, writable glass wall takes advantage of adjacent circulation space for larger informal events.
Operable wall in closed position
62
Operable wall in open position
63
ACADEMIC COLLABORATION Classrooms, in particular the M-Lab, are designed for active collaboration allowing multiple instructional arrangements, with loose furniture and access to technology. At the M-Lab, a pipe-gridded ceiling offers flexible lighting and sound enhancement for student projects.
M-Lab
64
Typical classroom
65
Third floor hearth
66
THIRD FLOOR HEARTH Like the first-floor forum space, the third floor also offers a warm fireplace hearth. Giving respite from Bozeman’s snowy winters, it is central to the informal learning environment.
Stone selection at local quarry
67
TRANSPARENCY & DAYLIGHT Yes, the big one is a skylight! The fourth floor is flooded with natural light, with transparency and translucency connecting all spaces.
68
69
70
STUDY NICHES & CLASSROOM PORCHES Quiet study niches, with generous views of the Bridger Mountains, and classroom “porches” offer spaces throughout the building for students and faculty to converse out of the way after classes dismiss.
71
OWNER President: Dr. Waded Cruzado Dean of School: Kregg Aytes Interim Dean/Associate Dean of School: Susan Dana Director of Campus Planning Design & Construction: Walt Banziger Construction Project Manager: Sam Des Jardins Assoc. V.P. for University Services: Bob Lashaway Assistant Director of Engineering & Utilities: Dan Stevenson HENNEBERY EDDY ARCHITECTS Principal-in-Charge: Timothy R. Eddy, AIA Project Manager/Architect: Jon McGrew, AIA Project Designer: Will Ives, AIA Project Architect: Robert Kroster, AIA Project Team: Alexander Lungershausen, AIA; Nick Byers; Angelique Nossa, NCIDQ; Laura Craig-Bennett; Kristy Hausladen COMMA-Q ARCHITECTS - ARCHITECT OF RECORD Principal-in-Charge: Ben Lloyd, AIA Project Manager: Kim Everts Project Architect: Tripp Lewton, Laura Landon CONSULTANTS Civil Engineer: Morrison Maierle Landscape Architect: Design 5 Structural Engineer: Morrison Maierle Mechanical, Electrical, Plumbing: Morrison Maierle LEED: Kath Williams Programming: Kathleen Kavanaugh Sustainability: ARUP - Cole Roberts CONTRACTOR Dick Anderson Construction Photography: Andrew Pogue Photography Photography: Ben Lloyd
72
73
74
PROJECT INFORMATION Client: Montana State University Location: Bozeman, Montana Building Use: College of Business & Entrepreneurship Site Area: +/- 2.30 Acres Building Area: 50,830 sf Construction Type: III-A (IBC 2009) Occupancy Type: A-3 Construction Cost: $13.8 M Cost/sf: $271.50 Completion Date: May 2015 HEA Project Number: 11106 AWARDS Engineering Excellence, ACEC Montana, 2015 Regional Best Project, Engineering News-Record, 2015 LEED Gold® Certified, USGBC, 2015 Sustainability Award, USGBC Montana, 2016 Merit Award, AIA Montana, 2016
75