INTERESTING NEWS Canada’s Oldest First Nations Newspaper - Serving Nuu-chah-nulth-aht since 1974 Canadian Publications Mail Product Vol. 47 - No. 02—January 30, 2020 haas^i>sa Sales Agreement No. 40047776
Highway 4 mishap wreaks havoc on traffic flow In the aftermath of the most challenging closure, the highway 4 project is still on schedule, says the province By Denise Titian Ha-Shilth-Sa Reporter Kennedy Lake, BC – A controlled blast caused a rockslide larger than expected, taking out a section of road at the Kennedy Hill Construction Project. The accident occurred late at night on Wednesday, Jan. 22, closing off road access to Clayoquot Sound’s communities for days. According to the Ministry of Transportation and Infrastructure, the damage to Highway 4 was caused by an unexpectedly large volume of rock falling on rain-saturated ground during a scheduled blast, as part of the Highway 4 - Kennedy Hill Safety Improvement project. The highway was closed to traffic at the time of the blast. The Kennedy Hill Construction Project is located adjacent to Kennedy Lake approximately 14 kilometres northeast of the Tofino/Ucluelet Highway 4 junction. The project starts at the bottom/south end of Kennedy Hill and continues up the hill towards Port Alberni for a distance of approximately 1.5 kilometres. The $38.1 million project began September 2018 and is scheduled for completion in September of this year. When finished, the notoriously dangerous section of highway will be wider, corners will be less sharp and the hill section will be regraded, making it less steep. In order to achieve this, the rocky hillside requires extensive blasting to remove and relocate rock and fill. The road is closed almost daily at regular intervals to accommodate the blasting. But on Jan. 22, for the fourth time, a scheduled blast damaged the road to the extent that it affected traffic flow. “Overnight during a scheduled blast the rock that came down onto the road compromised an existing retaining wall along the highway. A section of the highway has failed and we have lost a travel lane,” said the Ministry of Transportation and Infrastructure in a Jan. 23 press release. The road was closed for the day while construction crews and engineers assessed the damage and made plans for an immediate repair. Later that afternoon the Ministry announced that the road would remain closed but a plan was in place. “The workplan is to restore highway access by excavating the damaged road bed and replacing with a drivable surface,” they wrote. Crews worked throughout the night hauling fill to the damaged section of road, but by Saturday morning the
Photo by Curt McLeod
Crews install a temporary bridge by Kennedy Lake, where a Jan. 22 rockfall severely damaged the road bed. Ucluelet junction and at Sproat Lake near later this year. But more needs to be done road still was closed to most traffic. with the bridge. Port Alberni to marshal the traffic and Joenella Frank of Tla-o-qui-aht was “The bridge is a temporary fix for the turn away larger vehicles that could not waiting for an opening early Saturday area, and a more permanent fix will be remake it through the repaired section of morning so that she and her sons could quired during construction to support the highway. attend a funeral in Ahousaht. By then, ongoing blasting operations above that A new plan to bring in a Bailey Bridge a precariously narrow, rough road was immediate area,” they said in an email. (portable, pre-fab bridge) was made. The in place to allow single lane alternating “The ministry and contractor are workroad was to be closed for 24 hours while traffic through. Only small, passenger ing on plans on performing the project the bridge was installed. But the work vehicles and pickup trucks were allowed works around the temporary bridge. This took much less time than expected and through. bridge and slide area will ultimately be an the road was open to all traffic on Satur“It’s bad, really bad; oh my God, anxiabandoned segment of the road once the day, Jan. 25. ety, I almost cried,” she told Ha-Shilthproject is complete.” “Specialized bridge crews worked Sa. Drivers are encouraged to check throughout the day to install a pre-fabriFrank said the construction crews were allowing funeral-goers through a few at a cated 20-metre single-lane bridge,” stated DriveBC for the Kennedy Hill project closure schedule, along with current road time with an escort vehicle. a ministry press release. “Installation of conditions. the bridge was quicker than expected be“They wouldn’t let me record, or post,” The project team is evaluating how cause bedrock was deeper than expected. said Frank, adding that they were told by construction will progress around the new site workers that the ministry didn’t want This allowed for the bridge to be inset bridge. into the road grade, rather than above images of the area on social media. “The Ministry of Transportation and it, which would have required a subMeanwhile, grocery shelves in the Infrastructure thanks motorists and resiTofino and Ucluelet Co-ops were cleared stantial amount of approach ramp work. dents on both sides of the closure for their of fresh produce and dairy as customers Construction time was also reduced by patience. The ministry also recognizes the stocked up, fearing that delivery trucks bringing in additional bridge crews and crews who worked around the clock to would not get through for a few more equipment.” open the highway as quickly as possible,” days. They went on to say that all vehicles On the morning of Friday, Jan. 24, the are now able to safely travel the corridor, they wrote in their press release. When completed later this year, the Ministry of Transportation announced which remains under single lane alternatHighway 4 - Kennedy Hill Safety Imthat Highway 4 at Kennedy Hill would ing traffic conditions through the project provement Project pledges to provide reopen to essential travel only between site. a safer and more reliable connection noon and 8 p.m. that day. Travel was The Ministry of Transportation and between Port Alberni and the west coast restricted to passenger vehicles and light Infrastructure says while this event has of Vancouver Island. pickups only. delayed the project for a couple of days, work is still on track to be completed Flaggers were stationed at the Tofino/
Inside this issue... Indian hospital class action lawsuit............................Page 3 Plans to upgrade Bamfield road continue...................Page 4 Teaching with wolves..............................................Page 8-9 Ahousaht sends two teams to All Native..................Page 12 Blasting begins at Big Bar.................. .....................Page 15
If undeliverable, please return to: Ha-Shilth-Sa P.O. Box 1383, Port Alberni, B.C. V9Y 7M2