CIRCULATE 02
LOCATION: FINANCIAL DISTRICT, BOSTON, MA
YEAR: SPRING 2022
INSTRUCTOR: JAY SIEBENMORGEN
COLLABORATOR: AMELIA SHELTON
Circulate is an adaptive reuse project using a structural grid that enables flexibility of spaces over time. By keeping the original front facade of the building we were able to re-program the building in a way that emphasizes circulation and create personal discovery of the building. The transitional gasket space along High Street becomes the main entrance to promote new social interactions within the building as a place of circulation and collaboration. To further promote these different interactions, the building splits into half levels to reveal a glimpse of program between levels.
Cantilevers on each corner of the existing roof create new outdoor space along High Street allowing for scenic views between the old and new architecture allowing the user to experience the building in a new spacial quality that is unique to the area.
The double skin system allows mechanical servicing to be incorporated between the structure and dispersed as necessary. To take advantage of the sunlight, fritted triangulated glass panels are used in the double skin system to control light and views. The steel triangulated frame provides structural support to the facade.
08
UP 0 6 12 24 IN FEET 6 6 D 5 3 High St. Batterymarch St. 1 5 4 3 2 A A C B C D +1’-0” 8 7 5 5 5 5 6 2 1 3 +0’-0” 4 9 10 A A B B 6 6 5 4 1 F D E A C 1 3 2 A B C D E 2 11 12 13 DN. UP +18’-4” +18’-4” +21’-4” 2 4 4 8 9 10 8 8 5 5 5 5 5 5 A A B B SOUTH ELEVATION 0 3 9 15 IN FEET WEST ELEVATION 0 3 9 15 IN FEET SECOND FLOOR PLAN GROUND FLOOR PLAN 1 2 3 4 5 6 7 8 9 10 Lobby Lounge Cafe Conference Office Baseline Collaborative Collaborative Lounge Nook Think Space KEY 1 2 3 4 5 6 7 8 9 10 11 12 13 Lobby Lounge Cafe Conference Office Baseline Collaborative Collaborative Lounge Nook Think Space Kitchenette Auditorium Outdoor Terrace KEY 09
6 6 5 3 1 D A B C 1 5 4 3 2 A B C D 11 12 8 8 8 2 5 5 5 5 5 5 +32’-4” DN. UP UP 4 4 8 9 10 A A B B 12'-0" 10'-0" 3'-5" 6 6 5 5.1 D E F A C 1 5 4 3 2 A B C D E 3/8” Finish Flooring 5 1/2” Site Cast Concrete Slab on 3” Corrugated Metal Deck W16x36 Steel Structural Beam 4” Metal Stud Floor Assembly Floor Assembly 2” x 3” Steel Mullions 1” Glass Channel 1“ Tension Wire 4” x 2” Steel Tube 2“ x 3” Steel Members (Catwalk) 2” x 3” Steel Mullions 1” Glass Channel Metal Furring 8” x 8“ x 4” CMU Outer Wythe 2“ Air Cavity 2” Rigid Insulation 8” x 16” x 12” CMU Inner Wythe Wall Assembly Wall Assembly Connection to Mechanical Room Beyond WALL SECTION THIRD FLOOR PLAN SEVENTH FLOOR PLAN KEY PLAN 0 6 12 24 IN INCHES 3/8” Finish Flooring 5 1/2” Site Cast Concrete Slab on 3” Corrugated Metal Deck W16x36 Steel Structural Beam 4” Metal Stud 2’ x 2’ Pavers Hot rubberized ashpalt membrane with fabric reinforcement Rigid Insulation (Sloped to Drain) 5 1/2” Site Cast Concrete Slab on Composite Metal Deck W 12x16 Beam Roof Assembly 1 2 3 4 5 6 7 8 9 10 11 12 13 Lobby Lounge Cafe Conference Office Baseline Collaborative Collaborative Lounge Nook Think Space Kitchenette Auditorium Outdoor Terrace KEY UP +88’-6” +94’-6” 4 4 4 4 12 4 4 7 9 9 10 5 10 A A B B 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 Lobby Lounge Cafe Conference Office Baseline Collaborative Collaborative Lounge Nook Think Space Kitchenette Classroom Outdoor Terrace Buffet Kitchen Bar KEY 10
3’-0”
Parapet
Parapet wall on roof provides continuity and support in terms of water, air, vapor, and thermal control
Double-Envelope
A double-skin glass facade allows for services to run in between the inner and outer glass-work, such as heat pumps.
The outer steel triangulated framework allows for structural support and helps to control natural daylight with the integration of fritted glass
I-Beams
I-Beams are beneficial due to their wide flange and large lateral stiffness which create strong bending resistance
Metal Decking
Concrete slabs with composite metal decking allow for extra strength in the floor system without extra weight
Steel Cross Brace
Steel cross bracing to support cantilever, using same grid as outside skin
12’-0”
Tension Cables
Tension cables help strengthen the structure so they can hold higher amounts of service load
Heat Pump
Heat pumps are located between the double-skin facade and placed throughout as needed
Framing
Light steel framework helps with structural support along the exterior and amongst floors and cantilevers
Triangulated fritted glass panels help control the diffusion of daylight dependent on program and views Fritted Glass
MODEL PHOTO MODEL PHOTO DETAIL MODEL PHOTO SYSTEM DETAIL REFERENCE KEY 0 3 6 12 IN FEET 11
DETAIL
FRONT FACADE RENDER
MODEL PHOTO
12
FRONT FACADE RENDER
13
BED-STUY ARTS 03
LOCATION: BEDFORD STUYVESANT, BROOKLYN, NY
YEAR: FALL 2020
INSTRUCTOR: ANNETTE LECUYER
COLLABORATOR: DOMINIC SAMORAJ
BED-Stuy ARTS is a live-work residential complex geared towards art students and young local artists. The live-work element is portrayed in our form as the building splits into two buildings, one residential, the other studio, creating an open air terrace above a double height public gallery space. Interior and exterior bridges cut through the interstitial space and connect the studio spaces with the residential.
Brooklyn has become a magnet for young artists and unfortunately there are not enough studio spaces to keep up with the demand. By incorporating housing and studio into the same building, young artists and art students will be able to enjoy a generous shared studio and their own living unit.
The shared studios receive diffused northern daylight while the residential units sit on the southern side facing the street. The northern facade utilizes a mix of channel glass and typical tempered glass to control the diffusion of light into the studio spaces
Bed-Stuy ARTS provides the perfect live-work experience by providing generous shared studio space along with housing accommodations.
14
GALLERY WORKSHOP ENTRANCE STUDIO LOFT CAFE WORKSHOP LOBBY GROUND FLOOR PLAN 0 6’ 12’ 24’ 36’ MEZZANINE LEVEL 0 6’ 12’ 24’ 36’ FIRST FLOOR PLAN 0 6’ 12’ 24’ 36’ SECTION B 0 6’ 12’ 24’ 36’ 15
The exterior and interior bridging and the circular stair that flows up through the terrace space connecting to the larger circulation bridge at every level. Circulation through the building comes from single loaded corridors on the terrace-facing ends of both the residential and studio block with the bridging connecting the two.
VIEW OF INTERIOR BRIDGE
16
RESIDENTAL
STUDIO STUDIO LIBRARY TRIPLE UNIT PLAN 0 6’ 12’ 15’ DOUBLE UNIT PLAN STUDIO UNIT PLAN
SECOND FLOOR PLAN TYPICAL FLOOR PLAN
RESIDENTAL BLOCK
BLOCK
STAIR TYPOLOGY
A large curved stair with stair seating brings users to a mezzanine level on the northern side then continues up to the first studio space with immediate access to the terrace. The central terrace space on the roof of the plinth is overlooked by a cafe.
CIRCULATION
STAIR TYPOLOGY
SECTION A 0 6’ 12’ 24’ 36’
STUY ARTS BROOKLYN, NY
BED
VIEW OF GALLERY
17
FRONT FACADE RENDER
STREET VIEW RENDER
18
REAR FACADE RENDER
19
LOCATION: GALLAGHER BEACH, BUFFALO, NY
YEAR: FALL 2019
INSTRUCTOR: JON SPIELMAN
COLLABORATOR: NICHOLAS BLACKWELL
We started our exploration of buoyancy with our dugout vessel. To begin our vessel, we used a single tree trunk which we then began to form and carve in a way that would decrease the weight while still achieving buoyancy. In our vessel we were able to have structure and programs in a single fluid system.
The inspiration of our buoyant pavilion came from the same adaptive system as used in the vessel to respond to the conditions of the Buffalo Outer Harbor. For our structure we used Glu-Lam members for all of our walls. This was to shape the pavilion in a similar way our vessel was crafted. For our skin system we used wood cladding to represent the solidness that our vessel represents. We also used a glass skin to close certain areas of our pavilion that would respond programmatically. Additionally, the glass is representative of the resin coat used to seal our vessel. We chose to have areas in our pavilion dip down to water level to represent the seat in our vessel which also gradually dips down to the core of the vessel.
Just like our vessel, under what appears to be a heavy and solid structure is a hollow structural frame used in a single fluid system.
20
VACUITY 04
21 PLAN SECTION ELEVATION COLLABORATORS: NICHOLAS BLACKWELL,
ZIEGLER AND
VIGLIOTTI
CAMERON
MICHAEL
22
MODEL PHOTO
MODEL PHOTO
MODEL PHOTO
PERSPECTIVE
0’
23 COLLABORATORS: NICHOLAS BLACKWELL
CENTER COURTYARD OFFICES WORK AREA
VACŪITY SECTION
FIRST FLOOR PLAN
5’ 10’ 20’ SECOND FLOOR PLAN
KITCHEN AERA MULTI-USE EVENT SPACE WATER ACCESS
MODEL PHOTO
MODEL PHOTO
24
MODEL PHOTO
1. BASEMENT & MECHANICAL
ROOM
FOUNDATION
•1’x2’ grade beam running flush with top of pile cap
•4 #5 Reinforcement bars bottom and 3 #5 reinforcement bars connecting pile cap
RETAINING WALL
wide R-10 insulation at perimeter
1/2” Structure concrete slab on grade beams on pilecaps
•10” Thick cast in place concrete wall with 2 #5 vertical reinforcement bars @ 12” O.C.
INTERIOR WALL •5/8“ Gypsum board •4” Metal stud
•Hot rubber asphalt membrane at exterior
•Drainage mat
•5/8“ Gypsum board
•R-10 Rigid Insulation
2. EXTERIOR BICYCLE PARKING GARAGE
•Footing drainage pipe
FLOOR
•4” Concrete topping slab
FLOOR
•R-21 rigid insulation (sloped to drain)
•Hot rubberized asphalt membrane with fabric reinforcement
•5 1/2” Site cast concrete slab on composite metal deck
•Granular fill to 8.0’
•W10x45 steel column
•Vapor retarder Sheeting
3. MAIN LEVEL-OFFICE ROOM
•2’ wide R-10 insulation at perimeter
•6 1/2” Structure concrete slab on grade beams on
FLOOR
•Floor finishing carpet
•5 1/2“ tick site cast concrete slab on 3” corrugated metal deck
•W12x16 steel beam
INTERIOR WALL
EXTERIOR WALL
•5/8“ Gypsum board
•6“ Metal stud (8” at braced frame) @ 16“ O.C.
•4” Metal stud
•R-13 batt insulation fill
•Breathable wall membrane
•1/2” Plywood sheating
•5/8“ Gypsum board
•5/8” Gypsum board
•Aluminum wall metal siding
•Mechanic louver
2. EXTERIOR BICYCLE PARKING GARAGE
CEILING
•Acoustic ceiling tiles
FLOOR
4. UPPER LEVEL-STUDY ROOM
FLOOR
•4” Concrete topping slab
•Floor finishing carpet
•R-21 rigid insulation (sloped to drain)
•5 1/2“ thick site cast concrete slab on 3” corrugated metal deck
•W16x36 steel structural beam
•R-13 batt insulation
•Hot rubberized asphalt membrane with fabric reinforcement
•5/8“ Steel furring channel @ 16” O.C.
EXTERIOR WALL
•5 1/2” Site cast concrete slab on composite metal deck
•8” Metal stud @16“ O.C.
•3/8“ R3.8 insulation sheathing
•W10x45 steel column
•Vapor retarding primer
•5/8” Gypsum board
•Breathable wall membrane
•1” Channel
3. MAIN LEVEL-OFFICE ROOM
•Inverse chevron diagonal bracing W10x45
•Aluminum wall metal siding
CEILING
•Acoustic ceiling tiles
FLOOR
•Floor finishing carpet
5. LOWER ROOF ASSEMBLY
•Slopped W12x26 steel beam
•5 1/2“ tick site cast concrete slab on 3” corrugated metal deck
•R-21 rigid insulation
•W12x16 steel column pilecaps
•Single ply PVC membrane
•1 1/2” Corrugated metal deck
•Vapor Barrier
•1/4” overlayment board
EXTERIOR WALL
•6“ Metal stud (8” at braced frame) @ 16“ O.C.
•R-13 batt insulation fill
6. UPPER ROOF ASSEMBLY
•Breathable wall membrane
•Single ply PVC membrane
•1/4” overlayment board
•1/2” Plywood sheating
•R-21 rigid insulation
•5/8” Gypsum board
•Vapor Barrier
•1/4“ underlayment board
•Aluminum wall metal siding
•Mechanical louver
•1 1/2” perforated metal deck
•W10x15 steel beam
CEILING
•Acoustic ceiling tiles
25 2 ELEVATION 1/2"=1' Date: 04/16/2020 Drawn by: Gregg Schuster Key Plan Construction Technology Architecture &Planning Arch 442 Gregg Schuster Conibear Shellhouse Miller Hull Architects TA: Soham Mehta Project 2 W1 1 SECTION 1/2"=1'-0" A DETAIL 3/8"=1' B DETAIL 1/2"=1' Cam Ziegler Jess Rote Allen Long A B C C DETAIL 3/8"=1' 1. BASEMENT & MECHANICAL ROOM
•1’x2’ grade beam running flush with top of pile cap •4 #5 Reinforcement bars bottom and 3 #5 reinforcement bars connecting pile cap
•10” Thick cast in place concrete wall
2 #5 vertical reinforcement bars
12” O.C. •Hot rubber asphalt membrane
exterior •Drainage
•Footing
•2’
•6
FOUNDATION
RETAINING WALL
with
@
at
mat •R-10 Rigid Insulation
drainage pipe FLOOR •Granular fill to 8.0’ •Vaper retarder Sheeting
OUTLINE SPECIFICATIONS
2 ELEVATION 1/2"=1' Date: 04/16/2020 Drawn by: Gregg Schuster Key Plan Construction Technology Architecture &Planning Arch 442 Gregg Schuster Conibear Shellhouse Miller Hull Architects TA: Soham Mehta Project 2 W1 1 SECTION 1/2"=1'-0" A DETAIL 3/8"=1' B DETAIL 1/2"=1' Cam Ziegler Jess Rote Allen Long A B C C DETAIL 3/8"=1' 1. connecting reinforcement 2. 3. 4. 5. 6. SECTION ELEVATION DETAIL DETAIL DETAIL 1 2 A A B C B C 0’ 1’ 5’ 10’ KEY PLAN
4. UPPER LEVEL-STUDY ROOM
FLOOR
•Floor finishing carpet
•5 1/2“ thick site cast concrete slab on 3” corrugated metal deck
•W16x36 steel structural beam
•R-13 batt insulation
•5/8“ Steel furring channel @ 16” O.C.
EXTERIOR WALL
•8” Metal stud @16“ O.C.
•3/8“ R3.8 insulation sheathing
•Vapor retarding primer
•5/8” Gypsum board
•Breathable wall membrane
•1” Channel
•Inverse chevron diagonal bracing W10x45
•Aluminum wall metal siding
CEILING
•Acoustic ceiling tiles
5. LOWER ROOF ASSEMBLY
•Sloped W12x26 steel beam
•R-21 rigid insulation
•Single ply PVC membrane
•1 1/2” Corrugated metal deck
•Vapor Barrier
•1/4” overlayment board
6. UPPER ROOF ASSEMBLY
•Single ply PVC membrane
•1/4” overlayment board
•R-21 rigid insulation
•Vapor Barrier
•1/4“ underlayment board
•1 1/2” perforated metal deck
•W10x15 steel beam
YEAR: SPRING 2020
INSTRUCTOR: ANNETTE LECUYER
The objective of these drawings was to analyze and develop the ability to extract details from a set of construction documents.
I was assigned a small section of Conibear Shellhouse designed by architect Miller Hull. We were to develop a set of detailed drawings based on the current set of drawings on the building. The importance was focused around on understanding the details of the project and to represent the drawings clearly and efficiently.
26
CONSTRUCTION TECHNOLOGY 05
YOU
THANK