Berwick Waters | Quarterly Update - March 2023

Page 1

New road upgrade to connect Soldiers Road to Bells Road (Bells Road Extension)

Status as at 07 March 2023

Frasers Property Australia Works have continued on the construction of a new section of road through our property running between Soldiers Rd (where it bends) and Bells Road (where it currently terminates at Thompsons Road).

We have completed bulk earthworks, sewer, gas and water installations and a significant drainage crossing under the new road.

We are three months behind schedule due to frequent rainfall last winter and spring but are still hopeful of completing this work before Christmas 2023, weather permitting.

Frasers Property Australia

The final 150 metres of this road still remains to be completed.

Last week we responded to further questions from the Department of Environment, Land, Water and Planning (DELWP) on our final design and are awaiting further feedback. If a permit is received these works could be completed by June 2023.

This part of the road is complex from an approvals process as it crosses the Victorian Desalination Pipeline. DELWP must give approval before work can begin around this sensitive piece of infrastructure.

When completed ownership of the roads will be transferred to City of Casey Council.

Upper Banks & Promenade Village and final Wetlands

Frasers Property Australia,

Multiple stakeholders are responsible for various sections of these roadworks. The range of parties involved is due to land ownership boundaries and the separate planning permit requirements.

Work continues on FPA’s section. We’ve constructed base layers of the road including a base layer of asphalt, installed drainage and have completed the gutters.

We anticipate completion of this section by mid-2023.

Mondous Property and Circa Estate are responsible for the other two final sections of the road that will connect back into Como Parade and Huckerby Drive/Soldiers Road. . We are aware Mondous has submitted its plans to Council but is yet to receive approvals.

We have no update at present on Circa’s planned completion for their component.

College Green Conservation Reserve

Sporting ovals (located at Springleaf Avenue between Waterfront and Heritage Hill precincts)

Frasers Property Australia

There are three different wetland areas: Upper Banks, Promenade Village and a third in a precinct still to be released.

At Upper Banks, we’re still awaiting City of Casey formal approval of our final landscape construction drawing package for the shared path network with seating and small fitness areas dotted along the first section of wetlands adjacent to Stages 1 and 3.

We are also working through the tender process with contractors for plants at both Upper Banks and Promenade Village.

Bulk earthworks of the third and final wetland section is now likely to commence next month.

Frasers Property Australia Together with our landscape architect we have developed a revised design proposal for Council to submit to Melbourne Water that we hope will resolve their competing interests. We are awaiting the outcome and will seek the earliest possible works commencement date from our appointed contractor as soon as we’re successful.

City of Casey

Proposed primary school Victorian Government (Department of Education and Training Victoria/ Victorian School Building Authority)

The Waterside Centre (next to McDonalds)

Mondous Island Wetlands

Mondous Property Australia

The City of Casey is continuing with their detailed design of the sporting ovals/sports courts in this location.

They have advised that construction of these facilities is subject to future annual budget processes and competing infrastructure priorities.

Residents can contact the City of Casey’s Recreation & Open Space Planning Team on 03 9705 5200 if they have a specific question.

There are two landowners of the primary school site. Mondous Property owns the smaller area, and the developer of Aspen on Clyde owns the remainder.

While we are aware discussions have been continuing we have not been informed of any material progress since our last quarterly update from either Mondous or Aspen.

Mondous Property has appointed an additional leasing agency to help secure businesses for the centre.

Final landscape construction documentation is expected to be submitted to the City of Casey in April. The Town Centre Mondous Property Australia

Mondous Property Australia

Community Project
Who is responsible for delivery?
New road connection – Honour Avenue through to Riverstone Boulevard and Macumba Drive New road connection – Honour Avenue from Macumba Drive to Soldiers Road Mondous Property Australia and Circa Estate/ City of Casey
A
significant milestone for the Town Centre was reached in January with Council issuing a planning permit for phase 1. Bulk earthworks for the stage 1 Town Centre site are about to commence with civil and building design work continuing.
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.