Specification of a Space Project Management Handbook

Page 52

32

Literature Review

The current working schedule identifies the most realistic view of the project status given by the supplier to the customer, and reflects the following information: ∗ up-to-date status of activities; ∗ up-to-date status of key milestones; ∗ supplier’s procurement status. The comparison between the current working schedule an the baseline schedule forms the basis for the overall project progress assessment. • Performance evaluation The commonly used project schedule presentation is the Gantt chart, in this type of bar chart each activity is represented by a bar, the length of which corresponds to the duration of the activity. The links between the bars are shown with arrows as illustrated below. The critical path is typically highlighted.