CONSTRUCTION LAW

fied in accordance with the terms of the contract, and if the contract is silent in rela on thereto, sec on 6(b) provides that the said en tlement is to be quan fied on the basis of the value of the work done or goods or services supplied. • Clause 31(2)(a) of the SIA Form Contract states that the basis of a contractor’s payment claim shall comply with the valua on rules set out in sub-clause (4), which subclause goes on to prescribe the method with which the architect is to value the works. Simply put, this clause cons tutes the “terms of the contract” referred to in sec on 6 of the SOP Act. • Clause 31(2)(a) of the SIA Form Contract also requires the contractor to serve a copy of its payment claim on the architect. The Court of Appeal highlighted that the wording of clause 31(2)(a) en tled a contractor to serve a payment claim on the developer, but required (by using the word “shall”) the contractor to forward a copy of the same to the architect. • Clause 31(3) of the SIA Form Contract requires the architect to issue an interim cer ficate within 14 days a er the architect’s receipt of the payment claim. Put another way and read with clause 31(2)(a), the mandatory wordings in the SIA Form Contract in rela on to a contractor’s forwarding of a copy of its payment claim to the architect, together with the architect’s issuance of an interim cer ficate within 14 days of its receipt thereof, rendered the issuance of an architect’s cer ficate in rela on to a payment claim a condi on precedent to the claimant’s en tlement to the said payment claim. In Far East, it was no longer possible for the architect to issue such a cer ficate. This was because the architect had, in accordance with the SIA Form Contract, issued a final cer ficate and therefore lost the ability to issue any further cer ficates therea er. As such, in Far East, the requirement prescribed by clause 31(2) (a) of the SIA Form Contract was no longer capable of being fulfilled, with the consequence that the contractor’s en tlement to progress payments under sec on 5 of the SOP Act could no longer be quan fied, as mandatorily required by secon 6 of the SOP Act, in accordance with the “terms of the contract”. As a result, since the contractor could not establish an en tlement to payment, the Court of Appeal held that the contractor was not en tled to apply for adjudica on under the SOP Act and that the respondent was accordingly not under the duty to speak specifically referred to in Audi Construc on.

Takeaways from the Court of Appeal’s decision for construc on contracts incorpora ng the SIA Form Contract Contractors should note that a construc on contract that incorporates the terms of the SIA Form Contract has the effect of precluding them from being en tled to payment under a payment claim unless and un l the project architect has issued an interim cer ficate in rela on to the said payment claim. As a contractor, you can go on to

accept the architect’s cer fica on and interim cer ficate or choose to dispute the same (by, for example, filing for adjudica on under the SOP Act). Further, you should also note that under the SIA Form Contract, the architect’s final cer ficate is just that - final - and that the architect cannot cer fy any payment claims you issue therea er because the SIA Form Contract does not allow the architect to do so. Any such cer fica on will no doubt be challenged by your employer, and in the light of the Court of Appeal’s decision in Far East, such a cer ficate is likely to be meaningless in any event. You may therefore wish to nego ate for an amendment to your construc on contract for more flexibility, by, for example, expressly providing for an alterna ve mechanism under which you can claim payment even a er a final cer ficate has been issued, if you are of the view that such an alterna ve mechanism is necessary for your scope of work. Alternatively, if you have already entered into a construction contract which incorporates the SIA Form Contract and which does not provide for such an alternative mechanism, you may wish to explore whether it is viable for you to bring your claim against your employer before the courts or, if there is an arbitration agreement (as is the case in the SIA Form Contract), commencing arbitration with your employer on other bases, eg a common-law entitlement to recover a reasonable sum for work done (also known as quantum meruit).

Key takeaways from the Court of Appeal’s decision for other construc on contracts The factual matrix of the case in Far East precluded the contractor in that case from having recourse to adjudication under the SOP Act. The outcome of the case is a lesson learnt on the part of the contractor. Simply put, a contractor that is not entitled to receive payment under their construction contract is similarly not entitled to apply for an adjudication of its payment claim under the SOP Act. As a contractor, you must take note of the terms of your entitlement to payment under the construction contract and act in accordance therewith in order to establish a right to be paid for the work you have done. If, as a contractor, you have taken the posi on that an outstanding amount is due to you for work done under a construc on contract which incorporates the terms of the SIA Form Contract a er the project architect has issued a final cer ficate, you will not be able to apply for adjudica on under the SOP Act and will have to commence arbitra on instead. In other words, where, as a contractor, your construc on contract imposes upon you addi onal requirements or condi ons precedent to your en tlement to payment, ensure that you comply with these strictly. If you are unable to do so for reasons out of your control, try nego a ng with your employer for a waiver of your compliance with that requirement or condi on immediately in wri ng. THE SINGAPORE ENGINEER January 2020

25


Turn static files into dynamic content formats.

Create a flipbook

Articles inside

Sweden’s biggest road and tunnel project A 21 km motorway bypass is being constructed to relieve traffi c in Stockholm

19min
pages 43-52

Winning projects represent supreme global engineering feats The InsƟ tuƟ on of Structural Engineers (IStructE) announced the winners in November last year

18min
pages 29-35

Enhancing standard test approach to beƩ er refl ect applicaƟ on requirements PracƟ cal adjustments to the specifi caƟ ons can lead to beƩ er outcomes

33min
pages 19-25

ConstrucƟ ng and fi nishing the new Istanbul airport A wide range of chemical products was used in the fi rst phase

6min
pages 40-42

Payment Claims - EnƟ tlements and LimitaƟ ons A brief summary of the decision by the Court of Appeal on a case relaƟ ng to the Building and ConstrucƟ on Industry Security of Payment Act, and key takeway points, are provided

13min
pages 26-28

The future of infrastructure will be smart With the changing urban landscape, ciƟ es must transform to be more accessible and producƟ ve

7min
pages 36-37

Technologies for the diff erent processing stages in asphalt recycling Reclaimed asphalt pavement (RAP), is a valuable resource

7min
pages 38-39

Singapore’s construcƟ on demand for 2020 expected to remain strong The built environment sector is urged to look ahead, invest in digitalisaƟ on and innovaƟ on-driven growth, and groom local talent

8min
pages 16-18

Thomson-East Coast Line Stage 2 almost complete The 43 km Thomson-East Coast Line will open in fi ve stages starƟ ng from this year

7min
pages 13-15
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.
The Singapore Engineer January 2020 by The Singapore Engineer - Issuu