Skip to main content

TNA

Page 1

e e r

F

Wednesday, August 10, 2022

Schools see major summer renovations

Jeremy C. Ruark / The Chronicle

Demolition of a portion of St. Helens High School has been completed at this site on Gable Road.

Originally published in The Chronicle Vol. 140 August 3, 2022 JEREMY C. RUARK jruark@countrymedia.net

The $65 million renovations, including replacing aging portions of St. Helens High School, continue this summer. Demolition in the old A building section has been completed, according to the district’s facilities manager Jared Plahn. “The contractor is working on installing underground utilities and installing the fire lane,” he said. “Next, we will be building that section of the new building.” Plahn said while the renovations timeline is moving ahead, budget challenges are occurring. “We are currently tracking on time with a completion date of September 2024,” he said. “We are finding costs are increasing and adjusting the scope of the project to stay within budget.” St. Helens School District Superintendent Scot Stockwell said the district is facing challenges triggered by inflation and labor shortages. Stockwell said reports that inflation had hit a 40 year high at 9% is concerning. “A 9% inflation increase on a $65 million construction project gives you a $5.8 million increase in costs,” he said. “We’ve had to reduce the number of classrooms, limit the number of windows we wanted to add as well as reduce scope in some CTE programs. We are hopeful to see favorable bids and cost savings in the months to come to add back some of the reduced scope.” The renovations will continue into the new school year ahead. Building adjustments, including the addition of portable classrooms, have been established at the school site on Gable Road. Daily class schedules will reflect closely to last year, according to Plahn. Other projects The McBride Elementary front canopy, dry fire sprinkler line has been replaced. “We had nine patches on the piping and it had deteriorated to the point of replacement being the best option,” Plahn said. The district office and Family Resource Center were scheduled to be painted this summer. “The building is overdue by two years to be caulked

and painted,” he said. The St. Helens Middle School baseball field is undergoing work. “The field was installed with rocky soil,” Plahn said. “The rocks have come up over the winter. We will be installing more irrigation, topdressing and reseeding to cover up the rock.” The Middle School will have numerous site items built this summer and this fall. The Middle School has an electrical feeder to a breaker panel that has lost a leg and the feeder will be replaced. It is uncertain as to why the wire broke. “We will be adding a discus pad, shot put pad, football bleacher pad, football scoreboard, athletic storage shed, and additional crosswalk,” he said. “These items were found to be needed after the Middle School bond program concluded.” Also planned, will be new concrete and asphalt for the district’s maintenance shop sidewalk and apron. The sidewalk and apron have been patched numerous times and are at the point where it needs to be replaced, according to Plahn. The school building projects of $832,00 are being financed from bond and capital projects funding. Clatskanie School District Major building and security improvements at the Clatskanie School District are also underway this summer. The multiple projects are taking place at Clatskanie Middle/High School (CMHS) and at Clatskanie Elementary School (CES). CMHS Projects • Secure entrance and Phase 1 front office remodel • Mechanical rooftop unit replacement • Pumps and boilers system replacement • Locker room water heater replacement • Roof restoration • Media Center window replacement • Fire Alarm System replacement • 2nd Floor corridor flooring replacement • Restroom upgrades Phase I • Upper Commons renovation including hallway and flooring A new track surface is also being added at the high school athletic field. The major breakdown of the track surface was not included in the original bond plans and

Courtesy photo from the Clatskanie School District

Jeremy C. Ruark / The Chronicle

This photo shows the gutted front office looking out onto the existing courtyard at Clatskanie Middle/High School.

Rainier School District Superintendent Joseph Hattrick shows what the new bathrooms will look like, with individual private stalls, as workers in the background prepare the site.

is being financed outside the original $10 million. The replacement has begun and will be complete by mid-summer.

gendered bathroom and for those uncomfortable, there would be alternate bathrooms. • Hudson Park Elementary School will have one boys, one girls, and two single-stall bathrooms available for use. • Rainier Jr/Sr High School will have one boys, one girls, and three single stall bathrooms for use by staff and students. • The commons will have single stall restrooms for use and gendered bathrooms will remain available in locker rooms.

CES Projects • Secure entry upgrade • Roof replacement • Intercom/Switchboard upgrade • Cardiff Door replacement What is next •New blacktop at CES and CMHS –new blacktop has been postponed to summer 2023 in the hopes that oil prices will have dropped, and the cost will not be quite so exorbitant as today. •The complete division of the middle school and high school -Beginning in September 2022 all middle school classes will be on the second floor and all high school on the main floor other than science. In September 2023 that will permanently be reversed –all middle school classes will be on the main floor and high schoolers will have the second floor. • Lighting and sound upgrades to the auditorium • Bathroom Upgrades Phase 2 • Complete flooring upgrades • Completion of office and student services area Projects based on need Clatskanie School Board member Kathy Engel said the projects underway this summer are based on immediate need. “Such as roofs and our HVAC systems, as well as the very high priority of security, and costs,” she said. “We have postponed paving due to the huge inflation in cost of asphalt in the hopes it will be lower next summer if oil prices go down.” Engel said McKinstry, the school district’s contractor, is conducting the most intrusive projects during the summer months. “Work that must be done during the school year will be done with the least amount of interruption as possible and will make the needs of the staff and students a priority,” she said. “Most of it will not impact the classrooms.” Engel said new security measures are being established at the schools, including secure entries at both the middle/high school and at the elementary school. “During the initial arrival of students and staff in the morning the doors will be open as they always have

been, but once the school day begins the doors will be locked and visitors will need to come through the front entry and be buzzed in by staff,” she said, adding that currently the school doors can be locked from the inside. Funding for the school improvements is coming from a voter-approved $10 million bond and $4 million from the Oregon Department of Education. “We are constantly looking for more grants and avenues of paying for the current and planned upgrades,” Engel said. “Giving an ‘estimated cost’ is a luxury that no longer exists in the current building environment. As stated in the bond report, everything is running 30% higher than when this bond was passed. It remains to be seen how far we can stretch these dollars and the team is constantly prioritizing every penny spent.” Rainier School District renovations Significant building renovations are being conducted at the Rainier School District. The Chronicle talked with Rainier School District Superintendent Joseph Hattrick to gain insight into the why the projects are needed now and what the impact will be for students and staff at the schools. The Chronicle: What specific projects are being conducted this summer at Rainier schools? Joseph Hattrick: In June, we focused our efforts on reopening the Briarcliff pool and had a successful reopening. The facilities team is now working on remodeling two of our restroom areas in response to community concerns about equity. We are transforming our restrooms so students in the high school and the commons will have access to both gendered and non-gendered restrooms. • The bathroom discussion began last year through the Facility assessment and plan. • The facility team did a site visit to look at what single stall restrooms look like. • At a board meeting in May, there were public comments asking about how the district handles students using bathrooms who identify as a different gender than that which they were born. • At the June Board meeting I presented a facility plan and the board approved it which would ensure all students have access to their

We are also remodeling our wrestling room to ensure a safer learning and athletic space for our students. We are also re-installing three poles at our football stadium and replacing all lights with LED lights so that there is better lighting in the event of the need to have outdoor learning/ meeting spaces. We are also implementing the rules of HB 3294 which requires feminine products and dispensers in all restrooms. We will be working with a group to reorganize and ensure the woodshop is ready for students when they return in September. Finally, we are reviewing bids to re-roof some of our buildings and working with an envelope general consultant to determine the cause of the elementary gym floor damage and once we receive their report, we will be remediating the water and repairing the floor. All of this is in addition to the normal deep clean throughout our buildings and upkeep of our beautiful campus. We owe a huge debt of gratitude to the facilities team (which includes maintenance and custodial) for all of their hard work! The Chronicle: Why those specific projects? Hattrick: All of the projects we have identified were prioritized through a collaborative effort last year. Through our Facility Assessment which was conducted by Soderstrom Architects and worked with a Facility Committee to determine campus priorities. Additionally, through public forums, board meetings, and advisory council meetings, additional priorities were identified, and we are doing our best to determine those projects that could be accomplished this summer that will have a positive impact on students and safety in the fall. The Chronicle: What projects will be continuing

during the upcoming school year, why those projects and how will students and staff work around those projects? Hattrick: All of the projects listed above are projected to be completed before students return. We have not yet identified the fall projects but any we choose to address will not interfere with students and learning.

The Chronicle: What new security measures are being established at the schools and how will those measures alter how students, staff and visitors enter and exit the school buildings? Hattrick: This summer we are also revising all safety plans at all of our schools to ensure all of our drills and procedures are done in a way to ensure all are aware of safety protocols. Additionally, we are installing cameras and a buzz-in system at each of the main entrances, so visitors will be required to have access granted rather than leaving external doors unlocked. This is an incredible improvement from the past. The Chronicle: Are the school doors throughout the buildings able to be locked from inside? If not, is that part of the new security system? Hattrick: Yes, they are able to be locked from the inside and will be to ensure access from the outside is limited. The Chronicle: What is the total estimated cost of all the summer projects planned at the schools, and how will that cost be funded? Hattrick: While the total costs are still unknown as we are awaiting bids, those projects that we have initiated will cost above $300,000 so it is reasonable to assume all projects will cost somewhere in the neighborhood of $500,000 - $600,000. We are using a combination of grant funds as well as general funds. The Chronicle: What projects are planned for the district after this summer? Any new schools? Hattrick: We are in the planning phase to further review our facility assessment and plan. The goal of the facility committee would be to remodel buildings with the possibility of building a new elementary building and remove all portable structures. We are unsure of how we will proceed at this time.

Below is a list of WHERE to pick up a FREE copy of the print edition of the News-Advertiser. Also available every week at: thechronicleonline.com and at thechiefnews.com CLATSKANIE • CLATSKANIE SAFEWAY • HI SCHOOL PHARMACY IN CLATSKANIE • CLATSKANIE MARKET

• SMOKE SHOP • NELSON NEIGHBORHOOD MARKET • ACE • GROCERY OUTLET

SCAPPOOSE • ROAD RUNNER GAS & GROCERY • JACKPOT 76 • ENGSTROM CHEVRON • B&B MARKET • FRED MEYER

ST. HELENS • CHUBB’S CHEVRON • SHERLOCK’S • YANKTON STORE • ZATTERBURG’S • MARKET FRESH

• WALGREENS • BEST WESTERN • MOLLY’S MARKET • WALMART • ACE • DON’S RENTAL DEER ISLAND • DEER ISLAND STORE COLUMBIA CITY

• COLUMBIA CITY GROCERY & GAS RAINIER • ALSTON STORE • DOLLAR GENERAL • GROCERY OUTLET WESTPORT • THE BERRY BATCH RESTAURANT • WEST MART STORE


News Advertiser Columbia County

Classifieds

Page 2

Wednesday, August 10, 2022

Listings are updated daily at thechronicleonline.com and thechiefnews.com

301

502

502

702

702

706

750

Health & Nutrition

Help Wanted

Help Wanted

Garage Sales

Garage Sales

Estate Sales

Misc for Sale

Alcoholics Anonymous Info-line, (503) 366-0667 www.pdxaa.org

hiring a Field Engineer I/II Salary: Field Engineer I: $32.21-$45.94/ Hr DOQ Field Engineer II: $36.18$51.61/Hr DOQ Deadline: Open Until Filled. If you are interested in becoming a part of the Columbia River PUD team, please visit our website at www.crpud.net to view and apply for open positions or call us at (503) 3971844 to have an application packet mailed to you.

PUD team, please visit our website at www.crpud.net to view and apply for open positions or call us at (503) 3971844 to have an application mailed to you.

water jug, propane stove, fridge, coffee table, plantar boxes and more.

in box) ALL ELSE $1 Baby, Clothes, Books, CD, Toys, Camping Equipment, Tools. 52364 SE 2nd St. in Scappoose.

Help Wanted Looking for person with chainsaw to help cut dry peach wood at 2365 Columbia Blvd, St. Helens in the morning. Will pay. Please call 503964-0275.

Moving Sale It All Has To Go! No reasonable offer will be refused. Hardy R Cave 503-396-2665, at 225 S 13th St., St. Helens, Friday - Sunday from 9 am - 6 pm.

Kunekune pigs available after Sept 2022 Prefer to sell in pairs, as meat pigs best butchered around 20 months. Located off Pittsburg Rd, starting at $150, email happy hollowhomestead. hogs@gmail.com.

and equipment and are sold on a first come, first serve basis. Items are sold as is on site without representations or warranties. Buyer responsible for moving items prior to the conclusion of the sale. Cash or Cashier Checks only.

Columbia River PUD is hiring Position name: Vegetation Management Operator Salary: $33.66/hr 1st 6 mos, $37.40/ hr thereafter. Deadline: Thursday, August 25, 2022 by 5:30 pm. If you are interested in becoming a part of the Columbia River

Garage Sales

702

MOVING SALE Too much to list. FRI & SAT. 9 - 3. Cash Only. 35266 Firlok ParK Blvd. Behind Dollar Tree.

502

Help Wanted

Building Official Columbia County, OR EOE Deadline 8/17/2022 Apply at ColumbiaCounty OR.gov. CHIEF FINANCIAL OFFICER Columbia 9-1-1 Communications District (C911CD) is conducting a hiring process for a Chief Financial Advisor. Apply online at www.col u m b i a 9 11 . c o m / careers. Additional information can be found on our website or by calling 503-366-6972. Columbia River PUD A CommunityOwned Utility is

2-Family Sale 34364 NE Raenna Ln, Scappoose. 2-Family Sale. Sat 7/13 & Sun 7/14 from 10-5. 5-pc queen bedroom set, secretary desk, couch tables, end tables, lamps, collectables, cobalt blue & green glass,

Garage Sale 8/13 & 8/14 from 9 am- 4pm at 444 S 16th St.

Multi-Family Garage Sale Saturday 13th 9am-3pm Tires, Table, Couch, Overstuffed Chair 2 lawnmowers (1

For Sale 6 ft Cedar fence boards, 4x4x8 posts, 2x4x8 ft rails and 2x6x8 ft boards. Please call 503-396-1884.

706

Estate Sales

Estate Sale Fri-Sun from 9-4. Large amount of tools, including Proto sets, chain saws, large safe, large amount of golf clubs, including Golfsmith tools, furniture, kitchenware, refrigerators, freezers, washer & dryer, 1988 Chevy 2500 truck, clothing and much more. 33257 Stone Rd, Warren, Oregon.

750

Misc for Sale

St. Helens School District Surplus Sale Friday, August 12th, 2022 - 8:00 AM to 11:00 AM Lewis & Clark Elementary - 111 South 9th Street, St. Helens. The St. Helens School District will conduct a surplus sale on Friday, August 12th to dispose of district equipment declared as surplus. Items include furniture

Hosting a garage sale?

Let everyone know with an ad in the paper. Call 503-397-0116 to advertise with us!

ASPHALT PAVING Offering Quality Asphalt Paving Services to Columbia County and surrounding areas.

FREE Estimates

COMMERCIAL • RESIDENTIAL • INDUSTRIAL Driveways • Roadways • Subdivisions • Parking Lots • City, County, State Specification Products

Call Jim today at

(503) 509-8657

Quality Workmanship At Affordable Prices

Columbia County

BUSINESS & SERVICE DIRECTORY

www.thechronicleonline.com

Waterman Garage Doors

CCB#204858

SALES, SERVICE INSTALLATION

Scott Waterman Owner

Garage Sale Special!

503.819.6715 St. Helens, OR 97051

YOUR AD HERE

Advertise your business in the Business & Service Directory. Call 503-397-0116 for more information

Advertise your garage sale in the paper and online for only $10 for up to 14 lines!

Email chronicleclassifieds@countrymedia.net to advertise!

Get your ad in the paper and reach out to potential customers. Call 503-397-0116 to place your ad in the newspaper and online.

SUBSCRIBE TO YOUR FAVORITE LOCAL COUNTY NEWSPAPER Subscribe me to the:

The Chronicle

The Chief

Enclosed is my check for $60.00 Bill my VISA/Mastercard Card No. __________________________________________ Exp. Date _________________ Name ______________________________________________________________________ Address ____________________________________________________________________ City __________________________________ State ________________ Zip _____________

ONLY $60 a year!* *In Columbia County. Outside County $80.00/year

Phone Number ______________________________________________________________

Send subscription info to PO Box 1153, St. Helens OR 97051

Let us know what YOU think EMAIL YOUR LETTERS TO: CHRONICLENEWS@COUNTRYMEDIA.NET


News Advertiser Columbia County

Wednesday, August 10, 2022

Page 3

11th Annual 2022 Columbia County

Business

Guide 10th Annua l 2021 Colum bia Co

Business

unty

Guide FREE

Published b

y The Chronic

le & The Chief

The 2022 Columbia County Business guide is a full color, glossy magazine that showcases local business and highlights current news events. It is the go-to reference for visitors, newcomers, residents, and potential customers of Columbia County.

For space reservation or more information, contact us at: 503-397-0116 or chronicleads@countrymedia.net

The Chronicle

The Chief


News Advertiser Columbia County

Page 4

Wednesday, August 10, 2022

Follow me to Berry Global in St. Helens for

Big Pay, Big Career, and Big Success $1,000-$1,500 SIGN-ON BONUS It’s not a myth…it’s the real thing. Berry Global offers competitive pay starting at $18.00/hr. ➢ 4-Tier Pay Progression within first 2yrs. ➢ Monthly Bonus Programs ➢ Full-Benefit Package after 30-days A unique team environment, and a workplace culture with career advancement that makes me even want to come out of hiding to join their team. Apply online at: www.berryglobal.com/careers

Advertise in the paper and reach out to local customers

Berry Global is an equal opportunity employer

Call 503-397-0116 to advertise in The Chronicle & The Chief Quality Bark at Competitive Prices

BEAVER BARK

Sold by yard or Unit for pick up or Delivery • Variety of Fir & Bark Dust • Mulch & Potting Soil • Cedar Chips & Trail Mix

Clean Woodwaste Recycling Yard Debris & Woodwaste Recycling

Yard Debris & Clean Wood Waste Recycling $15 per yd. Clean = No pressure treated, paint or stain Wood Waste = Lumber, branches, small stumps and logs. We do not accept trash, plastic, dirt or sod.

$6 yard with $8 minimum charge

BEAVER BARK

We Deliver 1 Unit Minimum!

54000 West Lane Rd 503-543-3000 Scappoose Oregon Mon-Fri (503) 8-5 543-3000 Call for weekend deliveries

www.beaverbarkllc.com 54000 West Lane Rd. Scappoosethru Friday 8am to 4pm Open Monday

Local news online visit thechiefnews.com for daily updates on current events

The Chief 1805 Columbia Blvd, St. Helens www.thechiefnews.com 503-397-0116


Turn static files into dynamic content formats.

Create a flipbook
TNA by C.M.I. - Issuu