Precios de Partidas CÓD. OE.2.2.7.81
OE.2.2.9
OE.2.2.9.11 OE.2.2.9.12 OE.2.2.9.21 OE.2.2.9.22
PARTIDA ENCOFRADO Y DESENCOFRADO NORMAL GRADAS Y RAMPAS
FALSO PISO
OE.2.2.9.81
FALSOPISO DE 3" CON MEzC.1:6 C:H FALSOPISO DE 3" CON MEzC.1:8 C:H FALSOPISO DE 4" CON MEzC.1:6 C:H FALSOPISO DE 4" CON MEzC.1:8 C:H CONCRETO PREMEzCLADO F'C 100 KG/CM2 - FALSO PISO CONCRETO PREMEzCLADO F'C 120 KG/CM2 - FALSO PISO CONCRETO PREMEzCLADO F'C 140 KG/CM2 - FALSO PISO ENCOFRADO Y DESENCOFRADO DE FALSO PISO
OE.2.3.1
CIMIENTOS REFORZADOS
OE.2.2.9.52 OE.2.2.9.53 OE.2.2.9.54
OE.2.3 OBRAS DE CONCRETO ARMADO OE.2.3.1.34 OE.2.3.1.35 OE.2.3.1.36 OE.2.3.1.55 OE.2.3.1.56 OE.2.3.1.57 OE.2.3.1.58 OE.2.3.1.59 OE.2.3.1.60 OE.2.3.1.61 OE.2.3.1.81
OE.2.3.2
OE.2.3.2.34 OE.2.3.2.35 OE.2.3.2.36 OE.2.3.2.37 OE.2.3.2.81 OE.2.3.3 OE.2.3.3.34 OE.2.3.3.35 OE.2.3.3.36 OE.2.3.3.55 OE.2.3.3.56 OE.2.3.3.57 OE.2.3.3.58 OE.2.3.3.59 OE.2.3.3.60 OE.2.3.3.61 OE.2.3.3.81
OE.2.3.4
OE.2.3.4.34 OE.2.3.4.35 OE.2.3.4.36 OE.2.3.4.55 OE.2.3.4.56 OE.2.3.4.57 OE.2.3.4.58 OE.2.3.4.59 OE.2.3.4.60 OE.2.3.4.61 OE.2.3.4.81
OE.2.3.5 OE.2.3.5.34 OE.2.3.5.35 OE.2.3.5.36 OE.2.3.5.37 OE.2.3.5.55 OE.2.3.5.56 OE.2.3.5.57 OE.2.3.5.58 OE.2.3.5.59 OE.2.3.5.60
CONCRETO F'C 140 KG/CM2 CIMIENTO REFORzADO CONCRETO F'C 175 KG/CM2 CIMIENTO REFORzADO CONCRETO F'C 210 KG/CM2 CIMIENTO REFORzADO CONCRETO PREMEzCLADO F'C 175 KG/CM2 - CMTO REFORzADO CONCRETO PREMEzCLADO F'C 210 KG/CM2 - CMTO REFORzADO CONCRETO PREMEzCLADO F'C 245 KG/CM2 - CMTO REFORzADO CONCRETO PREMEzCLADO F'C 280 KG/CM2 - CMTO REFORzADO CONCRETO PREMEzCLADO F'C 315 KG/CM2 - CMTO REFORzADO CONCRETO PREMEzCLADO F'C 350 KG/CM2 - CMTO REFORzADO CONCRETO PREMEzCLADO F'C 420 KG/CM2 - CMTO REFORzADO ENCOFRADO Y DESENCOFRADO NORMAL CIMIENTO REFORzADO
ZAPATAS
UND
P.U.
M.O.
MAT.
EQU.
39,84
19,51
19,35
0,98
CONCRETO F'C 175 KG/CM2 MURO SOSTENIMIENTO CONCRETO F'C 210 KG/CM2 MURO SOSTENIMIENTO CONCRETO F'C 245 KG/CM2 MURO SOSTENIMIENTO CONCRETO F'C 280 KG/CM2 MURO SOSTENIMIENTO ENCOFRADO Y DESENCOFRADO NORMAL MURO DE OE.2.3.6.1.81 SOSTENIMIENTO ENCOFRADO Y DESENCOFRADO CARAVISTA MURO DE OE.2.3.6.1.82 SOSTENIMIENTO
M3 M3 M3 M3
447,10 460,67 499,71 525,16
204,67 204,67 204,67 204,67
208,82 222,39 261,43 286,88
33,61 33,61 33,61 33,61
M2
47,38
26,01
20,07
1,3
M2
52,38
31,21
19,61
1,56
13,83 13,83 13,83
OE.2.3.6.2.35 OE.2.3.6.2.36 OE.2.3.6.2.37 OE.2.3.6.2.38
M3 M3 M3 M3
537,47 551,04 590,08 615,53
281,40 281,40 281,40 281,40
209,86 223,43 262,47 287,92
46,21 46,21 46,21 46,21
1,27
OE.2.3.6.2.55
CONCRETO F'C 175 KG/CM2 TABIQUE Y PLACA CONCRETO F'C 210 KG/CM2 TABIQUE Y PLACA CONCRETO F'C 245 KG/CM2 TABIQUE Y PLACA CONCRETO F'C 280 KG/CM2 TABIQUE Y PLACA CONCRETO PREMEzCLADO F'C 175 KG/CM2 - TABIQUE Y PLACA CONCRETO PREMEzCLADO F'C 210 KG/CM2 - TABIQUE Y PLACA CONCRETO PREMEzCLADO F'C 245 KG/CM2 - TABIQUE Y PLACA CONCRETO PREMEzCLADO F'C 280 KG/CM2 - TABIQUE Y PLACA CONCRETO PREMEzCLADO F'C 315 KG/CM2 - TABIQUE Y PLACA CONCRETO PREMEzCLADO F'C 350 KG/CM2 - TABIQUE Y PLACA CONCRETO PREMEzCLADO F'C 420 KG/CM2 - TABIQUE Y PLACA ENCOFRADO Y DESENCOFRADO NORMAL TABIQUE Y PLACA ENCOFRADO Y DESENCOFRADO CARAVISTA TABIQUE Y PLACA
M3
315,71
44,54
268,11
3,06
M3
320,81
44,54
273,21
3,06
M3
332,03
44,54
284,43
3,06
M3
343,25
44,54
295,65
3,06
M3
359,57
44,54
311,97
3,06
M3
377,42
44,54
329,82
3,06
M3
403,60
44,54
356,00
3,06
M2
56,53
31,21
23,76
1,56
M2
58,17
36,72
19,61
1,84
M3 M3 M3 M3 M3
447,44 471,20 484,77 523,81 549,26
225,13 225,13 225,13 225,13 225,13
185,34 209,10 222,67 261,71 287,16
36,97 36,97 36,97 36,97 36,97
M3
307,77
37,12
268,11
2,54
M3
312,87
37,12
273,21
2,54
M3
324,09
37,12
284,43
2,54
M3
335,31
37,12
295,65
2,54
M3
351,63
37,12
311,97
2,54
M3
369,48
37,12
329,82
2,54
M3
395,66
37,12
356,00
2,54
OE.2.3.7.81 OE.2.3.7.81
CONCRETO F'C 140 KG/CM2 COLUMNA CONCRETO F'C 175 KG/CM2 COLUMNA CONCRETO F'C 210 KG/CM2 COLUMNA CONCRETO F'C 245 KG/CM2 COLUMNA CONCRETO F'C 280 KG/CM2 COLUMNA CONCRETO PREMEzCLADO F'C 175 KG/CM2 - COLUMNAS CONCRETO PREMEzCLADO F'C 210 KG/CM2 - COLUMNAS CONCRETO PREMEzCLADO F'C 245 KG/CM2 - COLUMNAS CONCRETO PREMEzCLADO F'C 280 KG/CM2 - COLUMNAS CONCRETO PREMEzCLADO F'C 315 KG/CM2 - COLUMNAS CONCRETO PREMEzCLADO F'C 350 KG/CM2 - COLUMNAS CONCRETO PREMEzCLADO F'C 420 KG/CM2 - COLUMNAS ENCOFRADO Y DESENCOFRADO NORMAL COLUMNA ENCOFRADO Y DESENCOFRADO CARAVISTA COLUMNA
M2 M2
57,51 74,88
31,21 47,86
24,74 24,63
1,56 2,39
OE.2.3.8.34 OE.2.3.8.35 OE.2.3.8.36 OE.2.3.8.37 OE.2.3.8.38 OE.2.3.8.55 OE.2.3.8.56 OE.2.3.8.57 OE.2.3.8.58 OE.2.3.8.59 OE.2.3.8.60 OE.2.3.8.61 OE.2.3.8.81 OE.2.3.8.82
CONCRETO F'C 140 KG/CM2 VIGA CONCRETO F'C 175 KG/CM2 VIGA CONCRETO F'C 210 KG/CM2 VIGA CONCRETO F'C 245 KG/CM2 VIGA CONCRETO F'C 280 KG/CM2 VIGA CONCRETO PREMEzCLADO F'C 175 KG/CM2 - VIGAS CONCRETO PREMEzCLADO F'C 210 KG/CM2 - VIGAS CONCRETO PREMEzCLADO F'C 245 KG/CM2 - VIGAS CONCRETO PREMEzCLADO F'C 280 KG/CM2 - VIGAS CONCRETO PREMEzCLADO F'C 315 KG/CM2 - VIGAS CONCRETO PREMEzCLADO F'C 350 KG/CM2 - VIGAS CONCRETO PREMEzCLADO F'C 420 KG/CM2 - VIGAS ENCOFRADO Y DESENCOFRADO NORMAL VIGAS RECTAS ENCOFRADO Y DESENCOFRADO CARAVISTA VIGAS RECTAS
M3 M3 M3 M3 M3 M3 M3 M3 M3 M3 M3 M3 M2 M2
314,84 338,60 352,17 391,21 416,66 287,94 293,04 304,26 315,48 331,80 349,65 375,83 65,31 66,24
112,56 112,56 112,56 112,56 112,56 18,56 18,56 18,56 18,56 18,56 18,56 18,56 33,19 39,01
183,79 207,55 221,12 260,16 285,61 268,11 273,21 284,43 295,65 311,97 329,82 356,00 30,46 25,28
18,49 18,49 18,49 18,49 18,49 1,27 1,27 1,27 1,27 1,27 1,27 1,27 1,66 1,95
CONCRETO F'C 140 KG/CM2 LOSA MACIzA CONCRETO F'C 175 KG/CM2 LOSA MACIzA CONCRETO F'C 210 KG/CM2 LOSA MACIzA CONCRETO F'C 245 KG/CM2 LOSA MACIzA CONCRETO F'C 280 KG/CM2 LOSA MACIzA CONCRETO PREMEzCLADO F'C 175 KG/CM2 - LOSA MACIzA CONCRETO PREMEzCLADO F'C 210 KG/CM2 - LOSA MACIzA CONCRETO PREMEzCLADO F'C 245 KG/CM2 - LOSA MACIzA CONCRETO PREMEzCLADO F'C 280 KG/CM2 - LOSA MACIzA CONCRETO PREMEzCLADO F'C 315 KG/CM2 - LOSA MACIzA CONCRETO PREMEzCLADO F'C 350 KG/CM2 - LOSA MACIzA CONCRETO PREMEzCLADO F'C 420 KG/CM2 - LOSA MACIzA ENCOFRADO Y DESENCOFRADO NORMAL LOSA MACIzA ENCOFRADO Y DESENCOFRADO CARAVISTA LOSA MACIzA
M3 M3 M3 M3 M3
314,84 338,60 352,17 391,21 416,66
112,56 112,56 112,56 112,56 112,56
183,79 207,55 221,12 260,16 285,61
18,49 18,49 18,49 18,49 18,49
M3
287,94
18,56
268,11
1,27
M3
293,04
18,56
273,21
1,27
M3
304,26
18,56
284,43
1,27
24,62 22,83 30,10 30,53
10,97 10,97 12,46 15,07
11,40 9,61 15,09 13,08
2,25 2,25 2,55 2,38
M3
258,54
37,12
218,88
2,54
M3
249,78
37,12
210,12
2,54
M3
263,69
37,12
224,03
2,54
M2
34,03
19,51
13,54
0,98
M3 M3 M3
268,37 292,13 305,70
71,05 71,05 71,05
183,49 207,25 220,82
M3
254,94
18,56
235,11
OE.2.3.6.1.35 OE.2.3.6.1.36 OE.2.3.6.1.37 OE.2.3.6.1.38
OE.2.3.6.2 MUROS DE CONCRETO, TABIQUES DE CONCRETO Y PLACAS
M3
260,04
18,56
240,21
1,27
M3
271,26
18,56
251,43
1,27
OE.2.3.6.2.57
1,27
OE.2.3.6.2.58
M3
298,80
18,56
278,97
1,27
OE.2.3.6.2.59
M3
316,65
18,56
296,82
1,27
OE.2.3.6.2.60
M3
342,83
18,56
323,00
1,27
OE.2.3.6.2.61
M2
30,84
15,60
14,46
0,78
OE.2.3.6.2.81 OE.2.3.6.2.82
M3 M3 M3 M3 M2
268,37 292,13 305,70 344,74 63,39
71,05 71,05 71,05 71,05 39,01
183,49 207,25 220,82 259,86 22,43
13,83 13,83 13,83 13,83 1,95
M3 M3 M3
289,93 313,69 327,26
88,84 88,84 88,84
183,79 207,55 221,12
17,3 17,3 17,3
M3
254,94
18,56
235,11
1,27
M3
260,04
18,56
240,21
1,27
CONCRETO F'C 140 KG/CM2 LOSA CIMENTACION CONCRETO F'C 175 KG/CM2 LOSA CIMENTACION CONCRETO F'C 210 KG/CM2 LOSA CIMENTACION CONCRETO PREMEzCLADO F'C 175 KG/CM2 -LOSA CIMENTACION CONCRETO PREMEzCLADO F'C 210 KG/CM2 -LOSA CIMENTACION CONCRETO PREMEzCLADO F'C 245 KG/CM2 -LOSA CIMENTACION CONCRETO PREMEzCLADO F'C 280 KG/CM2 -LOSA CIMENTACION CONCRETO PREMEzCLADO F'C 315 KG/CM2 -LOSA CIMENTACION CONCRETO PREMEzCLADO F'C 350 KG/CM2 -LOSA CIMENTACION CONCRETO PREMEzCLADO F'C 420 KG/CM2 -LOSA CIMENTACION ENCOFRADO Y DESENCOFRADO NORMAL LOSA DE CIMENTACION
M3
271,26
18,56
251,43
1,27
M3
282,48
18,56
262,65
1,27
298,80
18,56
278,97
1,27
OE.2.3.7
OE.2.3.7.34 OE.2.3.7.35 OE.2.3.7.36 OE.2.3.7.37 OE.2.3.7.38 OE.2.3.7.55 OE.2.3.7.56 OE.2.3.7.57 OE.2.3.7.58 OE.2.3.7.59 OE.2.3.7.60 OE.2.3.7.61
M3
316,65
18,56
296,82
1,27
M3
342,83
18,56
323,00
1,27
M2
54,50
39,01
13,54
1,95
M3 M3 M3
280,13 303,89 317,46
80,75 80,75 80,75
183,66 207,42 220,99
15,72 15,72 15,72
M3
253,42
17,14
235,11
1,17
M3
258,52
17,14
240,21
1,17
M3
269,74
17,14
251,43
1,17
M3
280,96
17,14
262,65
1,17
M3
297,28
17,14
278,97
1,17
M3
315,13
17,14
296,82
1,17
M3
341,31
17,14
323,00
1,17
M2
54,50
39,01
13,54
1,95
OE.2.3.9.01.34 OE.2.3.9.01.35 OE.2.3.9.01.36 OE.2.3.9.01.37 OE.2.3.9.01.38
M3
360,01
146,45
184,82
28,74
OE.2.3.9.01.55
M3
383,77
146,45
208,58
28,74
OE.2.3.9.01.56
M3
397,34
146,45
222,15
28,74
OE.2.3.9.01.57
M3
436,38
146,45
261,19
28,74
OE.2.3.9.01.58
M3
272,61
35,21
235,11
2,29
OE.2.3.9.01.59
M3
277,71
35,21
240,21
2,29
OE.2.3.9.01.60
M3
288,93
35,21
251,43
2,29
OE.2.3.9.01.61
M3
300,15
35,21
262,65
2,29
OE.2.3.9.01.81
SOBRECIMIENTOS REFORZADOS
CONCRETO F'C 140 KG/CM2 SOBRECIMIENTO REFORzADO CONCRETO F'C 175 KG/CM2 SOBRECIMIENTO REFORzADO CONCRETO F'C 210 KG/CM2 SOBRECIMIENTO REFORzADO CONCRETO F'C 245 KG/CM2 SOBRECIMIENTO REFORzADO CONCRETO PREMEzCLADO F'C 175 KG/CM2 - SOBREC. REFORzADO CONCRETO PREMEzCLADO F'C 210 KG/CM2 - SOBREC. REFORzADO CONCRETO PREMEzCLADO F'C 245 KG/CM2 - SOBREC. REFORzADO CONCRETO PREMEzCLADO F'C 280 KG/CM2 - SOBREC. REFORzADO CONCRETO PREMEzCLADO F'C 315 KG/CM2 - SOBREC. REFORzADO CONCRETO PREMEzCLADO F'C 350 KG/CM2 - SOBREC. REFORzADO
OE.2.3.5.81
OE.2.3.6 MUROS REFORZADOS OE.2.3.6.1 MUROS DE CONTENCIÓN
OE.2.3.6.2.56
M3
M3
316,47
35,21
278,97
2,29
M3
334,32
35,21
296,82
2,29
Sin I.G.V. en S/ vigentes al 31/08/2016 Los espacios en blanco en las columnas M.O., MAT. y EQU. significa S/.0.00
EQU.
M2
M2 M2 M2 M2
262,65
MAT.
2,29
2,6
18,56
M.O.
323,00
12,39
282,48
P.U.
35,21
52,02
M3
UND
360,50
67,01
OE.2.3.5.61
PARTIDA CONCRETO PREMEzCLADO F'C 420 KG/CM2 - SOBREC. REFORzADO ENCOFRADO Y DESENCOFRADO NORMAL SOBRECIMIENTO REFORzADO
M3
M2
CONCRETO F'C 140 KG/CM2 zAPATA CONCRETO F'C 175 KG/CM2 zAPATA CONCRETO F'C 210 KG/CM2 zAPATA CONCRETO F'C 245 KG/CM2 zAPATA ENCOFRADO Y DESENCOFRADO NORMAL zAPATA VIGAS DE CIMENTACIÓN CONCRETO F'C 140 KG/CM2 VIGA CIMENTACION CONCRETO F'C 175 KG/CM2 VIGA CIMENTACION CONCRETO F'C 210 KG/CM2 VIGA CIMENTACION CONCRETO PREMEzCLADO F'C 175 KG/CM2 - VIGA CIMENTACION CONCRETO PREMEzCLADO F'C 210 KG/CM2 - VIGA CIMENTACION CONCRETO PREMEzCLADO F'C 245 KG/CM2 - VIGA CIMENTACION CONCRETO PREMEzCLADO F'C 280 KG/CM2 - VIGA CIMENTACION CONCRETO PREMEzCLADO F'C 315 KG/CM2 - VIGA CIMENTACION CONCRETO PREMEzCLADO F'C 350 KG/CM2 - VIGA CIMENTACION CONCRETO PREMEzCLADO F'C 420 KG/CM2 - VIGA CIMENTACION ENCOFRADO Y DESENCOFRADO VIGA DE CIMENTACION
LOSAS DE CIMENTACIÓN
CÓD.
OE.2.3.8
COLUMNAS
VIGAS
OE.2.3.9 LOSAS OE.2.3.9.1 LOSAS MACIZAS
OE.2.3.9.01.82
OE.2.3.9.2 LOSAS ALIGERADAS CONVENCIONALES OE.2.3.9.2.34 CONCRETO F'C 140 KG/CM2 LOSA ALIGERADA OE.2.3.9.2.35 CONCRETO F'C 175 KG/CM2 LOSA ALIGERADA OE.2.3.9.2.36 CONCRETO F'C 210 KG/CM2 LOSA ALIGERADA
M3
315,48
18,56
295,65
1,27
M3
331,80
18,56
311,97
1,27
M3
349,65
18,56
329,82
1,27
M3
375,83
18,56
356,00
1,27
M2
50,27
26,01
22,96
1,3
M2
56,20
31,21
23,43
1,56
M3 M3 M3
288,31 312,07 331,40
90,04 90,04 95,32
183,49 207,25 221,03
14,78 14,78 15,05
costos - 77