State Supplement sponsored by:
90 80 6 422
6 80 24
OHIO STATE EDITION
6
4
71
76
199
A Supplement to:
30 30 75
68
30 77
71 23 22 68
4
70 70
70
22 71
75
77
27 22 74
50
50 25
35
SHIP WITHIN 48 HOURS
52
SAME DAY PARTS AVAILABILITY
®
24 HOUR TECHNICAL SUPPORT BACKED BY A 75 YEAR BUSINESS
June 1 2019
Thousands in Service!
Vol. XIV • No. 11
“The Nation’s Best Read Construction Newspaper… Founded in 1957.”
Affordable Price. Premium Service.
CALL 800-367-4937
Your Ohio Connection: Ed Bryden, Strongsville, OH • 1-800-810-7640
*On approved credit • Financing Available
Large ODOT Contracts Focus on Mill Creek Expressway ODOT photo
ODOT photo
Work on the Mill Creek Expressway, parceled out into 11 separate phases, started in 2010 and is scheduled for completion in 2025.
By Irwin Rapoport CEG CORRESPONDENT
Following completion of the Phase 5A of its Mill Creek Expressway project, the Ohio Department of Transportation will award two more major contracts to general contractors to complete the 11-phase project in greater Cincinnati that started in 2010 and is scheduled for completion in 2025. The remaining phases of the $550 million to $650 million overall project are Phase 5B, currently
valued at $91 million, and Phase 8, currently valued at $121.6 million. Phase 5B is scheduled to start in the summer of 2022 and be completed in the fall of 2024. Phase 8 is scheduled to start in May 2022 and be delivered in September 2025. Walsh Construction was awarded the contract for Phase 5A, an $86.9 million project that is adding lanes and resurfacing I-75 between the Mitchell Avenue interchange and the Western Hills Viaduct, and also includes improvements to the interchanges at Hopple Street, I-74
The multiphase project will add lanes to I-75 and provide full-depth pavement reconstruction from the Paddock Road Interchange to the Western Hills Viaduct. It also will include improvements to the interchanges at Hopple Street, I-74, Mitchell Avenue, Norwood Lateral, and Paddock Road — a length of approximately 8 mi.
and Mitchell Avenue. ODOT is looking to let the Phase 5B project in July 2021 and Phase 8 in January 2022.
“The preliminary development of both phases continues to be on schedule and moving to construction in a couple of years,” said
ODOT District 8 Communications Manager Brian Cunningham. Phases 5A and 5B are widening see ODOT page 6
Ohio’s Shale Energy Industry Attracts $74B in Investment Total investment in Ohio’s resource-rich shale energy sector has reached $74 billion since tracking began in 2011, according to a Cleveland State University study. Prepared for JobsOhio, the report represents the most recent data available and covers shale investment through the first half of 2018. It comes just weeks after IHS Markit released estimates that by 2040, the Utica and Marcellus
shale region, of which Ohio is a significant part, will supply nearly half of all U.S. natural gas production. The study from CSU’s Energy Policy Center at the Maxine Goodman Levin College of Urban Affairs, showed that drilling activity slowed, but remained significant in Ohio from January to June 2018. During the first half of the year, investment in Ohio’s upstream, midstream, and downstream
energy ecosystem totaled $4.6 billion, the study showed. Upstream activities, such as drilling or royalties, accounted for more than $3.4 billion of this total. According to the Ohio Department of Natural Resources, 157 wells were listed as “drilled, drilling or producing” in Ohio, with Belmont, Monroe, and Jefferson counties representing the most active areas. see SHALE page 4