Karangahape Station Early Works Erosion and Sediment Control Plan
CRL-KRD-RME-LKA-PLN-800010 Revision: Final Date: October 2019
Page 1
| Karangahape Station Early Works
Erosion and Sediment Control Plan – Karangahape Station
Erosion and Sediment Control Plan CRL-KRD-RME-LKA-PLN-800010
This document is uncontrolled when printed. This document should be printed in colour
Revision Status Revision
Date
Version details
Prepared By
Approved By
A
25/09/2019
Draft for Auckland Council Review
Joanna Miller, Ellen Chang
Peter Roan
0
21/10/19
Final for submission to Auckland Council
Joanna Miller, Ellen Chang
Peter Roan
Approval Status Name/Title Prepared by:
Joanna Miller, Ellen Chang Professional Civil Engineer
Reviewed by:
Caroline Secretin Principal Environmental Scientist
Verified by:
Duane Rollo Associate Director
Approved by:
Peter Roan Consents Lead – Link Alliance
Page 2
| Karangahape Station Early Works
Signature
Date
Erosion and Sediment Control Plan – Karangahape Station
Table of contents 1. Introduction ................................................................................................ 5 1.1
Karangahape Station ......................................................................................................... 5
1.2
ESCP Staging ...................................................................................................................... 6
1.3
Purpose of the ESCP .......................................................................................................... 6
1.4
Relevant Conditions .......................................................................................................... 6
1.5
Sustainability ..................................................................................................................... 9
1.6
ESCP Review and updates.................................................................................................. 9
2. Karangahape Early Works ......................................................................... 10 2.1
Overview of Works .......................................................................................................... 10
2.2
Earthworks ...................................................................................................................... 10
2.3
Topography and Drainage ............................................................................................... 11
3. Erosion and Sediment Control and Management ..................................... 14 3.1
Key Principles .................................................................................................................. 14
3.2
Erosion and Sediment Control Measures......................................................................... 14
3.2.1.
General ESC Measures .............................................................................................. 14
3.2.2.
Asphalt Works and Concrete Pumping / Pouring....................................................... 15
3.2.3.
Erosion and Sediment Source Control ....................................................................... 16
3.2.4.
Beresford Square / Pitt Street ................................................................................... 17
3.2.5.
Mercury Lane ........................................................................................................... 19
3.3
Monitoring During Construction ...................................................................................... 21
3.4
Heavy Rainfall Response & Contingency Measures ......................................................... 21
3.5
Other Environmental Management Considerations ........................................................ 21
3.5.1.
Contamination.......................................................................................................... 21
3.5.2.
Dust Control ............................................................................................................. 22
3.6
Site Reinstatement .......................................................................................................... 22
4. Roles and Responsibilities, Training and Complaints Response ............... 23 4.1
Roles and Responsibilities ............................................................................................... 23
4.2
Training ........................................................................................................................... 23
4.3
Complaints ...................................................................................................................... 23
Appendix A: ISCA Requirements ..................................................................... 24 Appendix B: ESCP Drawings ............................................................................ 25 Page 3
| Karangahape Station Early Works
Erosion and Sediment Control Plan – Karangahape Station
Appendix C: Record of CLG and Auckland Council Comments ........................ 26 C1. CLG Comments .......................................................................................... 26 C2. Auckland Council Comments ..................................................................... 26
Page 4
| Karangahape Station Early Works
Erosion and Sediment Control Plan – Karangahape Station
1.
Introduction
The City Rail Link (CRL) project comprises the construction, operation and maintenance of a 3.4 km underground passenger railway, running between Britomart Station and the North Auckland Rail Line in the vicinity of Mt Eden Station. The CRL also involves the construction of two new underground stations at Aotea and Karangahape and a redeveloped Mt Eden Station (refer to Figure 1-1). The design and construction of the CRL infrastructure between the Aotea and Mt Eden Stations is being delivered by the Link Alliance. This Erosion and Sediment Control Plan (ESCP) has been prepared in relation to construction of the new Karangahape Station (the Station).
Figure 1-1: CRL Route and Location
1.1
Karangahape Station
The Karangahape Station consists of two entrances, one at Beresford Square / Pitt Street and the other at Mercury Lane, linked together by platforms with two mined tunnels approximately 32m below Pitt Street. The Station will also comprise equipment rooms, ventilation systems and emergency egress at both Mercury Lane and Beresford Square / Pitt Street. Given the nature and scale of the Karangahape Station construction, works will be undertaken in a staged manner, involving:
Page 5
Early works (demolition, network utility relocation and site establishment works)– to be undertaken from October 2019 through to early 2020; Main construction works (construction of the station and mined tunnels for the rail tracks) – to be undertaken from early 2020 through to late 2023; and Public realm reinstatement – likely to be undertaken from late 2022 to late 2024.
| Karangahape Station Early Works
Erosion and Sediment Control Plan – Karangahape Station
1.2
ESCP Staging
To reflect the staged construction approach for the Karangahape Station, ESCPs will be developed in stages. This ESCP addresses the Karangahape Station early works, which are described in detail in the Construction Environmental Management Plan (CEMP) and summarised in section 2 of this ESCP. ESCPs will also be prepared for the main construction works and the public realm reinstatement.
1.3
Purpose of the ESCP
This ESCP has been prepared to identify measures that will be implemented to mitigate and manage the potential adverse effects on the receiving environment from any erosion and sediment generation during the early works. This ESCP has been prepared in accordance with Conditions 53-58, 65-73 and 166 of the CRL regional resource consent (land use consent R/LUC/2016/1890). This ESCP forms part of the CEMP for the Karangahape Station early works. The ESCP shall be read in conjunction with other relevant early works Delivery Work Plans (DWP) and Management Plans (MP) required by the designation and land use consent conditions. The ESCP has been developed to enable consultation with and feedback from the Karangahape Community and Business Liaison Group (CLG) (as per resource consent Condition 19). A record of the consultation outcomes is provided in Appendix C of this ESCP.
1.4
Relevant Conditions
Table 1-1 identifies the resource consent conditions relevant to this ESCP and where they are addressed in the document. Table 1-1 Relevant ESCP conditions and location in the Plan
Condition No.
Condition
Relevant ESCP section Land use consent R/LUC/2016/1890 conditions
53
At least 20 working days prior to the commencement of construction within a Construction Support Area (CSA) or ACZ, the Consent Holder shall submit to the Council (Team Leader Central Monitoring) for certification an ESCP which provides for the management of all bulk earthworks to minimise any discharge of debris, soil, sediment or sediment-laden water beyond the site to either land and/ or stormwater drainage systems.
This ESCP
54
The Consent Holder shall request the Council's (Team Leader Central Monitoring) determination as to whether the ESCP can be certified, in writing, within 10 working days of receipt of the ESCP. No construction activity shall commence until certification from Council is provided.
Noted
55
An ESCP shall include, but is not be limited to, the following matters:
Page 6
identification of construction zones and construction support areas;
2.1 and 2.2
specific erosion and sediment control works for each Active Construction Zone (location, dimensions, capacity supporting
3
| Karangahape Station Early Works
Erosion and Sediment Control Plan – Karangahape Station
Condition No.
Condition
Relevant ESCP section
calculations and design drawings), which should be in line with Industry Best Practice that will meet or exceed the performance of measures detailed in TP90; catchment boundaries;
2.3
the timing and duration of construction and operation of control works (in relation to the staging and sequencing of earthworks);
3 (and CEMP)
details relating to the management of exposed areas;
3.2.3
reference to the Flocculent Treatment Management Plan and confirmation of erosion and sediment control measures necessary to give effect to that plan;
Not required for early works
reference to the Contaminated Soils Management Plan and confirmation of erosion and sediment control measures necessary to give effect to that plan; and
1.3 and 3.2.3
monitoring and maintenance requirements, including information on complaint investigation and response procedures, training, and roles and responsibilities.
3.3, 3.4, 3.5, 4 (and CEMP)
56
Any change to an ESCP shall be submitted to the Council (Team Leader Central Monitoring) for certification.
1.6
57
The Consent Holder shall request the Council's (Team Leader Central Monitoring) written determination as to whether the proposed change can be certified, to be provided within 10 working days of submission of the change. No activity reliant upon a change to the ESCP can be undertaken until the change has been certified.
Noted
58
The Consent Holder shall comply with the ESCP for the duration of the earthworks associated with the Project.
Noted
65
Prior to the commencement of bulk earthworks, a certificate signed by a Senior Qualified Person shall be submitted to the Council (Team Leader Central Monitoring) to certify that the erosion and sediment controls (including diversion bunds, silt fences and sumps) have been constructed in accordance with the certified ESCP(s) as required by Condition 53 of this consent.
Noted
66
The certification from the Senior Qualified Person for these measures shall be supplied to the Council (Team Leader Central Monitoring) immediately upon completion of construction of those measures. Information supplied, if applicable, shall include:
Noted
The contributing catchment area; The shape of structure (dimensions of structure); The position of inlets/outlets; and The stabilisation of the structure. 67
Page 7
The Consent Holder shall ensure that there shall be no deposition of earth, mud, dirt or other debris on any road or footpath resulting from bulk earthworks on the subject site. In the event that such deposition does occur, it shall immediately be removed. In no instance, shall roads or footpaths be washed down with water without appropriate erosion and | Karangahape Station Early Works
3.2
Erosion and Sediment Control Plan – Karangahape Station
Condition No.
Condition
Relevant ESCP section
sediment control measures in place to prevent contamination of the stormwater drainage system, watercourses or receiving waters. 68
The operational effectiveness and efficiency of all erosion and sediment control measures specifically required as a condition of resource consent, including the certified ESCP referred to in Condition 53, shall be maintained throughout the duration of earthworks, or until the Project site is permanently stabilised against erosion.
3.3, 3.4, 3.5 and 3.6
69
The site shall be progressively stabilised against erosion at all stages of earthworks activity and shall be sequenced to minimise the discharge of contaminants to groundwater or surface water.
3.1 and 3.2
70
The Consent Holder shall ensure that the erosion and sediment control measures are constructed and maintained in accordance with TP90, except where a higher standard is detailed in an ESCP/FTMP, in which case the higher standard shall apply.
3
71
Sediment control measures shall be inspected on a weekly basis and after a significant storm event to ensure effective operation.
3.3
72
The Consent Holder shall ensure that all material removed from or delivered to the Project site shall be covered during transportation.
3.2.3
167
In the event that any CSA requires an increase in area, the following information shall be provided to the Team Leader – Central Monitoring whose certification shall be requested prior to implementation:
Noted
a. Plans and drawings outlining the details of the modifications; and b. Supporting information that confirms how the proposal does not affect the capacity or performance of the existing structural and procedural controls. 168
Page 8
The Consent Holder shall ensure that the following structural controls are constructed for the following catchment areas and design standards and they are completed prior to discharges commencing from the site: Works/ Controls Device Catchment Design Requirements Area 2 x Settlement Tanks located on CSA 4
Activity area of grout plant (400m2), and segment storage yard (2660m2) on CSA 4
Settlement Tanks sizing to be based on 2% of the contributing catchment
Inlet protection measures
On all catch pits within CSA areas
2 x Settlement Tanks located in CSA 1, CSA 2, CSA 3, CSA 4 and CSA 5 Bunding of Environmentally
All Active Construction Zone (ACZ)
Design in accordance with Auckland Council Best Management Practice: Catch pit Protection Area (AC 2015). Settlement Tank sizing to be based on 2% of the contributing catchment
As required
110% largest container
| Karangahape Station Early Works
3.2.1, 3.2.4 and 3.2.5
Erosion and Sediment Control Plan – Karangahape Station
Condition No.
Condition
Relevant ESCP section
Hazardous Substances 169
In the event that any minor modifications to the structural system are required, the following information shall be provided to the Team Leader – Central Monitoring whose certification shall be requested prior to implementation: a. Plans and drawings outlining the details of the modifications; and
Noted
b. Supporting information that confirms how the proposal does not affect the capacity or performance of stormwater management system.
1.5
Sustainability
The Link Alliance is seeking an Infrastructure Sustainability Council of Australia (ISCA) Infrastructure Sustainability (IS) Rating. Further details can be found in the CEMP and Sustainability Rating Management Plan. Project sustainability requirements that relate directly to this ESCP are included in Appendix A. These requirements are imbedded within this ESCP to ensure that sustainability is a key focus and ‘the way we do things’. In some cases, the IS requirements and sustainability goals enhance the designation and consent requirements. Further detail on sustainability is provided in section 1.7 of the CEMP.
1.6
ESCP Review and updates
This ESCP is a live document that will be reviewed at least annually, or as a result of a material change to the project, or to address unforeseen erosion and sediment runoff effects arising from construction, or unresolved complaints. Any material changes to this ESCP must be certified by Auckland Council prior to any on-site activity reliant upon the change commencing (as per conditions 42 and 43 of resource consent). Refer to the CEMP for further detail on the review and updating process.
Page 9
| Karangahape Station Early Works
Erosion and Sediment Control Plan – Karangahape Station
2.
Karangahape Early Works
2.1
Overview of Works
Early works will be undertaken at the new Karangahape Station site to enable and provide for the subsequent main construction works. The early works are detailed in the CEMP. An overview of the works is provided in Table 2-1. Table 2-1: Overview of Karangahape Early Works
Works location
Overview of construction activities
Beresford Square / Pitt Street
Relocation of network utilities located within the footprint of the new Karangahape Station in Beresford Square / Pitt Street; Removal of street trees and the demolition of the café / toilet in Beresford Square; Establishment of the Beresford Square Construction Support Area to provide site offices, construction vehicle parking, laydown areas and storage of plant and equipment etc.; Closure of Beresford Square to vehicle traffic (other than construction traffic) while retaining pedestrian and cycle access; and Removal of existing street furniture where required, such as seating and street lighting (to be replaced with temporary lighting).
Mercury Lane
Relocation of network utilities located within the footprint of the new Karangahape Station in Mercury Lane; and Establishment of the Mercury Lane Construction Support Area to provide site offices, construction vehicle parking, laydown areas and storage of plant and equipment etc.
It should be noted that the demolition of buildings and above ground structures within the Mercury Lane Construction Support Area is authorised by the CRL Enabling Work Outline Plan – Karangahape Road Demolition Works (Auckland Council reference OPW60339200), confirmed in June 2019, and does not form part of this ESCP.
2.2
Earthworks
Earthworks associated with the Karangahape Station early works will largely comprise:
Excavation associated with network utility relocations (involving open trenching using excavators and hydro vac trucks) and directional drilling; Contouring to establish the two Construction Support Areas (CSAs); and Construction of the temporary working platform in the Mercury Lane CSA.
The approximate earthwork areas and volumes required for the early works are outlined in Table 2-2.
Page 10
| Karangahape Station Early Works
Erosion and Sediment Control Plan – Karangahape Station Table 2-2 Approximate Earthwork Areas and Volumes
Construction Works Area
Approx. Area m2
Approx. Volume m3 350 m3
Pitt Street Stage 1
250 m2
Pitt Street Stage 2
100 m2
150 m3
Pitt Street Stage 3
410 m2
820 m3
Pitt Street Stage 4
100 m2
150 m3
Beresford Square CSA establishment
1,880 m2
1,800 m3
Total Beresford Square / Pitt Street
2,740 m2
3,270 m3
Mercury Lane Stage 1 Mercury Lane Stage 1A Mercury Lane Stage 2 Site Establishment (including retaining wall and temporary working platform construction) within CSA Mercury Lane CSA (including offices, laydown areas, temporary retaining structure, spoil surge piles and settlement pond) Total Mercury Lane Total for Karangahape Station early works
80 m2 50 m2 320 m2 1,590 m2
400 m3 300 m3 1,600 m3 3,090 m3
5,120 m2
9,870 m3
7,160 m2 9,900 m2
15,260 m3 18,530 m3
Beresford square / Pitt Street
Mercury Lane
Refer to section 2.2.1 of the CEMP for a detailed breakdown of the earthwork areas and volumes.
2.3
Topography and Drainage
Karangahape Station contributes to two separate catchments, with Karangahape Road forming the boundary between the two catchments. Pitt Street and Beresford Square drain to north of Karangahape Road into an existing stormwater system, eventually discharging to the Waitemata Harbour by the Central Business District area. There are no flood sensitive areas or major overland flow paths identified in the early works area (refer Figure 2-1). The slopes in this area range from 1.5% to 2.7%. Mercury Lane drains to a different catchment south of Karangahape Road and into an existing stormwater system, eventually discharging to the Waitemata Harbour by Meola Reef Reserve. There are no flood sensitive areas identified in the early works area, but overland flow paths are located along Mercury Lane (refer Figure 2-2). The slope in this area is approximately 9.5%.
Page 11
| Karangahape Station Early Works
Erosion and Sediment Control Plan – Karangahape Station
Karangahape Rd
Figure 2-1 Overland Flow Paths and Flood Sensitive Areas in Beresford Square and Pitt Street (Source: Auckland Council Geomaps)
Page 12
| Karangahape Station Early Works
Erosion and Sediment Control Plan – Karangahape Station
Figure 2-2 Overland Flow Paths and Flood Sensitive Areas in Mercury Lane (Source: Auckland Council Geomaps)
Page 13
| Karangahape Station Early Works
Erosion and Sediment Control Plan – Karangahape Station
3.
Erosion and Sediment Control and Management
Erosion and sediment control measures will be designed, installed and maintained in accordance with Auckland Council “Erosion and Sediment Control Guide for Land Disturbing Activities in the Auckland Region”, Guideline Document 005 (GD05). It is noted that GD05 has superseded Auckland Council Technical Publication 90 (TP90) “Erosion and sediment control guidelines for land disturbing activities in the Auckland Region”, which is referred to in the consent conditions.
3.1
Key Principles
Key erosion and sediment control principles applicable to the early works are as follows:
Selection of construction methodologies and staging of construction to limit the duration and area of earthworks exposed to erosion at any given time. Minimise the total area of disturbance by keeping the area of earthworks to a minimum and progressive stabilisation of exposed areas. Avoidance of overland flow paths where practicable. Protection and stabilisation of steep slopes using clean water diversion bunds (CWD), and vegetative covers. Stabilisation of exposed surface areas as soon as practicable. This may include one or more of the following measures:
Application of granular material, straw mulch, hydro-seeding or grassing (either temporarily or permanently). Installation of downslope perimeter controls or diversions around and within the construction area, to detain and treat sediment laden runoff and prevent contamination of the existing stormwater system and receiving environment. Use of silt fences around the construction area as required to trap sediment laden runoff. Adoption of specific construction practices within the construction area to minimise sedimentation generation during trenching.
Regular inspection and maintenance of sediment control devices.
3.2
Erosion and Sediment Control Measures
3.2.1.
General ESC Measures
Erosion and sediment control measures (ESCM) will be installed by the Contractor prior to the start of any vegetation clearance, site set up or earthworks. The mitigation measures will remain in place until reinstatement of active working areas is complete. ESCM identified in Table 3-1 can be implemented throughout the construction area. All ESCMs shall be designed and maintained in accordance with GD05. Table 3-1 General Erosion and Sediment Control Measures
ESCM
Application
Catchpit/ Stormwater inlet protection
Page 14
Cover catchpit grates and inlets with geotextile to filter sediment laden runoff before discharge into the stormwater network; or Other proprietary catchpit protection systems, such as silt/filter sock, sand logs, coir logs and hay bales.
| Karangahape Station Early Works
Erosion and Sediment Control Plan – Karangahape Station ESCM
Application
Diversion channel/bund
Filter socks
Sand logs/coir logs/hay bales
Dewatering (if required)
Settlement Tanks
Truck Wash and/or Shaker Ramp
3.2.2.
Filter socks can be used to intercept and impound runoff before it enters a catchpit or other stormwater inlet. Can be used to reduce the velocity of runoff flows within a channel, as a check dam. Contain and impound discharges from pumped stormwater or concrete washwater (as a turkey nest to promote settlement). Use in carriageway to divert clean water from construction site where there is steep terrain uphill or unfavourable carriageway crossfall.
Dewatering devices will be used to pump out any water that collects within open trenches or excavation areas or for sediment control devices for maintenance. A minimum of 100mm water clarity is required to pump out of the works area. The water shall be pumped to settlement tanks or to a tanker and removed offsite. Refer to the Groundwater and Settlement Monitoring and Contingency Plan (GSMCP) for further detail on groundwater levels within the early works area.
Stabilised entrance and surface
Install to divert runoff from external catchments entering construction areas or for conveyance of sediment laden runoff within construction areas. Hotmix diversion bunds can be used where kerb and channels have been removed or on impervious surfaces. Diversion bunds must have sufficient capacity to carry the flow safely from a 5% annual exceedance probability (AEP) storm, with 300mm freeboard, in accordance with GD05.
Settlement tank sizing is based upon 2% of the exposed area. Water quality standards must be met before discharging to an existing stormwater inlet, where by pH ranges is between 5.5 to 8.5 and clarity is greater than 100mm. Use available machinery to hydrovac the settlement tanks when full, then the sediment-laden runoff is to be disposed offsite. Install at egress points for construction outside of the carriageway. Any cut or exposed surfaces within the construction area can be stabilised with aggregates. All aggregates should comply with minimum thickness of 150mm with 50-150mm washed aggregate sizing. Any shaker ramps installed should be 5m in length (minimum) to allow for at least one full revolution of a truck tyre. Shaker ramps will need to be placed at the exit and any runoff from the shaker ramp area (including or excluding wheel-wash system) must pass through an appropriate sediment retention device. Localised wheel wash shall be provided where impracticable to install entry and exit stabilised entrances. Truck wash shall connect to a settlement tank or similar retention device to be disposed offsite.
Asphalt Works and Concrete Pumping / Pouring
The environmental risk of concrete or asphalt works is high, and it is recommended that drainage channels are completely isolated during these works. If this is not practicable, careful placement of sandbags or bunds should be implemented.
Page 15
| Karangahape Station Early Works
Erosion and Sediment Control Plan – Karangahape Station Other recommended controls are: Delay concreting works when bad weather is forecast, if practicable. Minimise the volume of water used on site (e.g. in dust suppression, concrete cutting) so there is less to control. Use concrete saws that can have a vacuum attached to minimise the amount of dust produced during cutting, OR use a wet/dry vacuum, to collect all concrete or asphalt contaminated material or runoff on site. If the above is not practical, divert all runoff to the construction pit/ trench or unsealed ground, away from overland flow paths. Runoff or wash water contaminated with concrete fines / dust is highly alkaline and cannot be diluted, therefore, all captured runoff from concrete cutting and/or cement mixing must be treated or disposed off-site. Wash all equipment and tools in a designated site wash out area. Do not allow concrete trucks or concrete pumpers to wash out on site unless there is a designated wash area. Use tarpaulin sheets under concrete pumps and delivery chutes to capture any spills.
3.2.3.
Erosion and Sediment Source Control
The erosion and sediment source controls listed in Table 3-2 have been identified as applicable to all of the early works area. This includes CSAs and work zones identified in stages for utilities relocation and site clearance. Table 3-2 General source control measures applicable to the works area for elimination and/or minimisation of erosion and sediment generation
Source/Activity
Source Control Measure
General site management
Soil Management & Stockpiles
Sediment transport due to runoff from external catchments entering the construction site Page 16
Ensure overland flow paths are unobstructed and stabilised (if required), if practicable. Check the weather forecast and plan accordingly if there is to be heavy rainfall/wind; Stabilise work areas with high sediment generation potential as soon as practicable by placing geotextile and covering with clean hardfill or other approved method; Regularly sweep or remove any accumulated sediment associated with the works; Dampen dusty exposed working areas to minimise wind distribution of sediments. Soil removal using hydrovac will be disposed of at an approved off-site facility. All soil removed should be placed in covered trucks for off-site transport. Stockpiles are to be in construction areas serviced by ESCMs only. Stockpiles of fine material shall be dampened or covered to reduce the potential for windblown sediments or the generation of sediment laden runoff (refer to the AQ DWP for detail on stockpile management). Stockpiles shall be located away from overland flow paths. Any hazardous construction materials shall be stored in an isolated and bunded area in accordance with the CEMP. Construct diversion bunds/channel to divert runoff from external catchments entering land disturbance sites; and Use clean water diversions (e.g. sandbags, compacted earth, bund) where there is steep terrain uphill of the works area to reduce the volume of water requiring management.
| Karangahape Station Early Works
Erosion and Sediment Control Plan – Karangahape Station Source/Activity
Source Control Measure
Open trench work
Erosion due to runoff travelling over reinstated ground
3.2.4.
Cut and Cover methodology shall be adopted. Backfill and compact trenches as soon as possible in an immediate and progressive manner; Exposed areas shall be stabilised as soon as possible and at the end of each day’s operations. This can include aggregate for carriageway and footpath areas and topsoil, seed and mulch/geotextile for landscaping and berm areas. Dewatering of trenches and/or excavations must be pumped to a retention device (settlement device) and using a hydrovac to be disposed of at an appropriate off-site location. Do not remove ESCMs until the reinstatement of active working areas is established.
Beresford Square / Pitt Street
The section details erosion and control measures that will be implemented for construction work within Beresford Square and Pitt Street (tree removal, café/toilet demolition, excavation of service trenches, network utility relocation and CSA establishment).
3.2.4.1
Beresford Square Construction Support Area
The Beresford Square CSA footprint and ESCM are shown on the ESCP Drawings provided in Appendix B. The following erosion and sediment controls will be implemented during the works:
Page 17
Diversion bund to divert clean water away from the construction zone to a stormwater inlet and dirty water to a settlement tank. Clean water and dirty water diversion (CWD and DWD) must have sufficient capacity to carry the flow safely from a 5% annual exceedance probability (AEP) storm. Stabilised entrance will be provided at the entrance/exit level to Beresford Square where practicable. The truck exit area shall have a shaker ramp installed so that sediment is not transported out of the construction area. The shaker ramp shall have adequate teeth depth so that material dropped from one vehicle is not picked up by the next. Sediment laden water from the shaker ramp/wash area will be diverted to a sediment retention facility at the northern corner of the CSA. Where it is not practicable to implement these control measures, the minimum requirement will be the provision of a localised wheel wash or shaker ramps for trucks, with a temporary holding tank positioned within the CSA to capture runoff. A settlement tank will be placed in the northern corner of Beresford Square CSA to service the wheel wash for the trucks as well as runoff within CSA. The settlement tanks will be emptied using hydro-excavation when full and the sediment-laden runoff will be disposed of at an appropriate off-site location. Two in-line settlement tanks are proposed, designed to service at minimum 2% of the contributing catchment area with tank sizing outlined in Table 3-3.
| Karangahape Station Early Works
Erosion and Sediment Control Plan – Karangahape Station Table 3-3 Settlement Tank Sizing for Beresford Square CSA
Stage Number
Settlement Tank / Sediment Retention
Contributing Catchment Area (m2)
Minimum Settlement Tank Volume (m3)*
Beresford Square CSA
(Sediment Retention) SR containing 2 in-line tanks (included in the water treatment area)
1,880 m2
37.6m3
* Minimum volume for settlement retention device is calculated as 2% of the contributing catchment area.
3.2.4.2
Beresford Square / Pitt Street Stages 1 and 2
Beresford Square / Pitt Street Stage 1 and 2 works footprint and ESCM are shown on ESCP Drawings in Appendix B. The proposed erosion and sediment controls that will be implemented during these works are as follows:
Inlet protection will be required at each stormwater catchpit within the works area which discharges into the existing stormwater network at one existing catchpit (CP1) by Beresford Square Bar Restaurant. Diversion bund to divert clean water away from the construction zone to a stormwater inlet and dirty water to a settlement tank. Clean water and dirty water diversion (CWD and DWD) must have sufficient capacity to carry the flow safely from a 5% annual exceedance probability (AEP) storm. The settlement tanks will be emptied using hydro-excavation when full and the sedimentladen runoff will be disposed off-site at an appropriate location. The settlement tanks have been sized to service at minimum 2% of the contributing catchment area. Tank sizing for each stage can be found in Table 3-4.
Table 3-4 Settlement Tank Sizing for Beresford Square / Pitt Street Stages 1 and 2
Stage Number
Settlement Tank / Sediment Retention
Contributing Catchment Area (m2)
Minimum Settlement Tank Volume (m3)*
Stage 1
SR1
250 m2
5 m3
Stage 2 (Silt sock)
SR2
100 m2
2 m3
* The recommended tank volume applies to the total area of each stage. ** Open Excavation Area is based on a trench width provided by the contractors, and the length of trench provided by the contractors. ***Volume for Stormwater Management applies to each stage and is not the cumulative value of all the stages listed in the row. **** Minimum settlement tank volume has been calculated using a conservative approach of 2% of the open excavation area
3.2.4.3
Beresford Square / Pitt Street Stages 3 and 4
Beresford Square / Pitt Street Stage 3 and 4 works footprint and ESCM are shown on the ESCP Drawings in Appendix B. The proposed erosion and sediment controls that will be implemented during these works are as follows:
Inlet protection will be required at each stormwater catchpit within the works area which discharges into the existing stormwater network:
Page 18
One existing catchpit (CP1) by Beresford Square Bar Restaurant; One existing catchpit (CP2) in front of 61 Pitt Street;
| Karangahape Station Early Works
Erosion and Sediment Control Plan – Karangahape Station
One existing catchpit (CP3) in front of 259-281 Karangahape Road; One existing catchpit (CP4) in front of 22-28 Beresford Square; and One existing catchpit (CP5) in front of 15 Beresford Square.
Diversion bund to divert clean water away from the construction zone to a stormwater inlet and dirty water to a settlement tank. CWD and DWD must have sufficient capacity to carry the flow safely from a 5% AEP storm. Settlement tanks will be emptied using hydro-excavation when full and the sediment-laden runoff will be disposed off-site at an appropriate location. The settlement tanks have been sized to service at minimum 2% of the contributing catchment area. Tank sizing for each stage can be found in Table 3-5. SR4A, SR4 and SR5 refer to silt socks depicted in the drawings in Appendix B of this ESCP.
Table 3-5 Settlement Tank Sizing for Beresford Square / Pitt Street Stage 3 and 4
Stage Number
Settlement Tank / Sediment Retention
Contributing Catchment Area (m2)
Minimum Settlement Tank Volume (m3)*
Stage 3
SR3
410 m2
8.2 m3
Stage 4
SR4
100 m2
2 m3
* Minimum volume for settlement retention device is calculated as 2% of the contributing catchment area.
** Open Excavation Area is based on a trench width provided by the contractors, and the length of trench provided by the contractors. ***Volume for Stormwater Management applies to each stage and is not the cumulative value of all the stages listed in the row. **** Minimum settlement tank volume has been calculated using a conservative approach of 2% of the open excavation area
3.2.5.
Mercury Lane
This section details the erosion and control measures that will be implemented for the Mercury Lane construction works, being the excavation of service trenches, network utility relocation, reinstatement of pavement and establishment of the Mercury Lane CSA.
3.2.5.1 Mercury Lane Construction Support Area and Site Establishment The Mercury Lane CSA footprint and ESCM are shown on the ESCP Drawings in Appendix B of this ESCP. The following erosion and sediment controls will be implemented during the works:
Page 19
Diversion bund to divert clean water away from the construction zone to a stormwater inlet and dirty water to a settlement tank. CWD and DWD must have sufficient capacity to carry the flow safely from a 5% AEP storm. Stabilised entrance will be provided at the entrance/exit level to the CSA where practicable. The truck exit area shall have a shaker ramp installed so that sediment is not transported out of the construction area. The shaker ramp shall have adequate teeth depth so that material dropped from one vehicle is not picked up by the next. Sediment laden water from the shaker ramp/wash area will be diverted to a sediment retention facility in the north-western corner of the CSA. Where it is not practicable to implement these control measures, the minimum requirement will be the provision of a localised wheel wash or shaker ramps for trucks, with a temporary holding tank positioned within the CSA to capture runoff. Two in-line settlement tanks will be placed in the south-western corner of the Mercury Lane CSA to service the wheel wash for the trucks as well as runoff within the CSA. The settlement tanks will be emptied using hydro-excavation when full and the sediment-laden runoff will | Karangahape Station Early Works
Erosion and Sediment Control Plan – Karangahape Station be disposed off-site at an appropriate location. The settlement tanks will be designed to service at minimum 2% of the contributing catchment area with tank sizing outlined in Table 3-6. Table 3-6 Settlement Tank Sizing for Mercury Lane CSA
Stage Number
Settlement Tank / Sediment Retention
Contributing Catchment Area (m2)
Minimum Settlement Tank Volume (m3)*
Mercury Lane CSA
SR containing 2 in-line tanks (included in the water treatment area)
6,710 m2
134.2 m3
+ Site Establishment
* Minimum volume for settlement retention device is calculated as 2% of the contributing catchment area.
3.2.5.2
Mercury Lane Stages 1, 1A and 2
Mercury Lane Stages 1, 1A and 2 works footprint and ESCM are depicted in ESCP Drawings attached in Appendix B of this ESCP. The proposed erosion and sediment controls that will be implemented during these works are as follows:
Inlet protection required at each stormwater catchpit which discharges into the existing stormwater network.
One existing catchpit (CP1) in front of 9A Mercury Ave; and Three existing catchpits (CP2, CP3 & CP4) by Mercury Lane and Cross Street intersection.
Diversion bund to divert clean water away from the construction zone to a stormwater inlet and dirty water to a settlement tank. CWD and DWD must have sufficient capacity to carry the flow safely from a 5% AEP storm. The settlement tank will be emptied using hydro-excavation when full and the sedimentladen runoff will be disposed at an appropriate off-site location. The settlement tanks have been sized to service at minimum 2% of the contributing catchment area. Tank sizing for each stage can be found in Table 3-7. Note: SR2 refers to silt socks depicted in the drawings in Appendix B of this ESCP.
Table 3-7 Settlement Tank Sizing for Mercury Lane Stage 1,1A and 2
Stage Number
Settlement Tank
Contributing Catchment Area (m2)
Minimum Settlement Tank Volume (m3)*
Stage 1
SR1
80 m2
1.6 m3
Stage 1A
SR1A and silt sock
50 m2
1 m3
Stage 2
SR2 (silt socks)
320 m2
6.4 m3
* Minimum volume for settlement retention device is calculated as 2% of the contributing catchment area.
** Open Excavation Area is based on a trench width provided by the contractors, and the length of trench provided by the contractors. ***Volume for Stormwater Management applies to each stage and is not the cumulative value of all the stages listed in the row. **** Minimum settlement tank volume has been calculated using a conservative approach of 2% of the open excavation area
Page 20
| Karangahape Station Early Works
Erosion and Sediment Control Plan – Karangahape Station
3.3
Monitoring During Construction
All site-specific erosion and sediment control measures will be inspected on a weekly basis and after rainfall events by the Link Alliance. Inspection will include, but will not be limited to, the requirements outlined in Table 3-8. Table 3-8 Monitoring Requirements for ESCM
Erosion and Sediment Control Catchpit / Stormwater Inlet Protection
Inspection/Maintenance Requirements
Frequency
Check for damage, blockages and leaks – repair immediately. Remove accumulated sediment immediately.
Daily, before & after rainfall
Check for scour and areas where a breach may or has occurred – repair immediately. Remove sediment build up deposited in the DWD channel. Check for low spots, formation of gullies or debris – repair immediately.
Weekly & after rainfall
Clean & Dirty Water Diversion Bunds and Channels
Settlement Tanks
Check if the tank is full, then empty using hydrovac and the sediment-laden runoff to be disposed offsite.
Weekly & after rainfall
Stabilised Entranceway and Surface
Check quantity of aggregate and geotextile for sediment build up and deterioration – apply more aggregate as required. Check aggregate thickness and if not GD05 to specification then apply more aggregates or change as required.
Weekly & after rainfall
Check for any structure used to trap runoff and clean it out. Add further aggregate as necessary if aggregate thickness is not to specification or mud blockage is evident.
Weekly & after rainfall
Truck Wash and/or Shaker Ramp
3.4
Heavy Rainfall Response & Contingency Measures
The Karangahape early works are planned to extend over five months, between October 2019 and March 2020. High intensity rainfall events can occur during the summer months as well as prolonged rain events during winter months. The Link Alliance shall monitor weather forecasts, inspect all erosion and sediment control measures for adequacy, and undertake any remedial works required prior to forecasted rain events.
3.5
Other Environmental Management Considerations
3.5.1.
Contamination
The majority of spoil from the early works will likely meet clean fill classification (refer to the Contamination Delivery Work Plan (CDWP) in Appendix O of the CEMP).
Page 21
| Karangahape Station Early Works
Erosion and Sediment Control Plan – Karangahape Station During all land disturbance activities site staff will actively monitor active works areas for the conditions/materials specified in the CDWP. The CDWP outlines the measures to be implemented if suspected contaminated material is discovered.
3.5.2.
Dust Control
Land disturbance activities shall be undertaken in accordance with the AQ DWP (Appendix I to the CEMP) in order to minimise the potential for dust generation.
3.6
Site Reinstatement
Decommissioning of ESCM shall only occur once the active works areas are permanently stabilised. Due care will be taken during the removal process so as not to mobilise any sediment.
Page 22
| Karangahape Station Early Works
Erosion and Sediment Control Plan – Karangahape Station
4. Roles and Responsibilities, Training and Complaints Response 4.1 Roles and Responsibilities The key management roles in relation to environmental management during construction are outlined in the Project CEMP. However, all site personnel will be responsible for following the requirements of this ESCP during the early works.
4.2 Training All site staff will undergo general environmental awareness training and training about their responsibilities relating to this ESCP. Training requirements are described in detail in the CEMP. Specific training requirements relating to this ESCP are outlined in Table 4.1. Table 4.1: ESCP training requirements
Training requirements
Frequency
Attendance
Training on ESCP requirements and resource consent conditions.
As required and during new staff induction
All new site staff
Tool box meetings on site to include erosion and sediment control as a standard agenda item.
Weekly tool box meetings, or as required (e.g. start of new substantial activity)
All site staff
Construction, maintenance and inspections of erosion and sediment control devices
As required
Site supervisors and staff site with erosion and sediment control management responsibilities
4.3 Complaints Any complaints received during the early works shall be recorded and promptly investigated to identify and resolve the cause of the complaint in accordance with the complaints response protocol detailed in the early works Communication and Consultation Plan.
Page 23
| Karangahape Station Early Works
Erosion and Sediment Control Plan – Karangahape Station
Appendix A: ISCA Requirements Table A identifies the ISCA Credit Requirements relevant to this ESCP and where they are addressed in the CEMP. Further details regarding the specifics of the evaluation and means of achieving the relevant targets is provided in the relevant sub-plans and other relevant documents. Table A: ISCA Requirements Credit
Relevant section of the ESCP
Requirement *
Other Relevant Information / Comments
Receiving Water Quality DIS-1 Level 1
Measures to minimise adverse impacts to receiving wai environmental values during construction and operation have been identified and implemented. These measures demonstrate an awareness of the values of wai ora and its Mauri, and opportunity for mana whenua feedback has been provided and where practicable incorporated into these measures. AND Monitoring of wai discharges and receiving wai is undertaken at appropriate intervals and at times of discharge during construction.
DIS-2 Level 2
Monitoring and modelling of wai discharges and receiving wai demonstrates no adverse impact on receiving wai environmental values. The infrastructure does not increase peak stormwater flows for rainfall events of up to a 1.5 year ARI event discharge
DIS-3 Level 3
Opportunities to improve receiving wai environmental values have been identified and implemented. Monitoring and modelling demonstrates improvement of receiving wai environmental values
Section 3.2, 3.3, 3.5
Section 3.3, 3.4
Section 3
* Refer to ISCA Rating Tool for full details of the requirement
Page 24
| Karangahape Station Early Works
Also refer to the Emergency Spill Response Plan, Contamination Delivery Work Plan and the Groundwater and Settlement Monitoring and Contingency Plan
Also refer to the Sustainability Ratings Management Plan
Erosion and Sediment Control Plan – Karangahape Station
Appendix B: ESCP Drawings
Page 25
| Karangahape Station Early Works
VG
.0 63
VG
SW
T
N
VG
SW
T
.0
PITT ST SW
SW
SW
SW
VG
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
LEGEND:
SW
SW
VG
SW
T
SW
SW
SW
T
SW
SW
N SW
S SW
SW
S
FO
SW
S
C
C FO
SW W VG
S
S S S
SW W VG
S S FOC
W
S SW FOC VG
SW
S SW FO C VG
S
WASTEWATER
SW
STORMWATER
W
POTABLE WATER
VG
VECTOR GAS
FO
VECTOR COMMS FO
VE
VECTOR ELEC
T
VODAFONE
C
CHORUS
CL
CITYLINK
STORMWATER
SW
258
SW
D
SW
PE R
268
SW
AHA
SW
ANG KAR
270
SW
SW
SW
C
FO
EXISTING
SW
SW
FO
S S W SW VG C
FO
C
C FO
S S S W SW VG
C FO
S S S W SW VG
S S S S W FOC V W G
256
SW
W
S S S SW VG C
SW FO VG C
W
S S
S
PROPOSED
FO
W
S
W
S S S S S S
4-6
FOC
S S S SW W VG
SW
S S S SW S W FO C V W G
S FO V W CG
S S S W
W
S S
S
SW VG C
S S
SW
FO
S
W
S FO V W G C
SW
SW
SW SW
W
S S
S W
FO VSW G C
S S
S S S
278
16-18
SW
S
DIRTY WATER DIVERSION
SETTLEMENT TANK
C
S S
SW
S S S
S S S
CLEAN WATER DIVERSION BUND
> SILT SOCK UTILITIES LEGEND:
W SW VG C
S
STABILISED ENTRANCE
> >
SW INLET PROTECTION
267-281
FCO
SW
S SW VGW
S S
S FOC SWW VG
S S TS
SW W
W
S
FO
SW
W
VE
VE
FO
T
W
S
W T
VE
S
284
SW
SW
246-254
FO C SW W VG
C
VE
W
SW
W SW
SW
SW
VG
C
T
T
W
VE
VE
VE
S
VG
C
W
T
VE
VG C SW
SS
VE
VE SW
ESCP LEGEND:
243
W C FO VSW G
SW
SW
VE
VG C
W T
VE
S S
SW
VG
VE
VGC
SW
SS
VE
VE
VE
S
S
SW
EXISTING CRL DESIGNATION BOUNDARIES
W C FO VSW G
SW
SW
C VG
SW
W FO VSW G C
SW
SW
S S S W SW VG
SW
SW
SW SW
SW
SW SW
SW SW SW SW
VG C C VG
S
S
S
SW SW
SW
VG SW
C
SW
VE W
VG C
SW
W VE
VE C VG
SW
W VE
VE C VG
SW
W VE VE
C VG
SW
W VE
VE VGC SW
W VE VG C
VE
PEDESTRIAN ACCESS ROUTES
8-10
SW
63.0
SW
SW
TREE REMOVAL
S
61-65
CP1 WILL HAVE FILTER SOCK OR SIMILAR MECHANISM TO PROVIDE FILTRATION AND STORMWATER INLET PROTECTION
SW
W
S
SW
VE
S SW
259-261
SW
S
S SW
12-14
SW
SW
SW
VE
VG
SW
SW
SW
VE
T
S S
SW
SW SW
SW SW SW
SW
SW
C
VE C
VE W VE
C
VE W
VG VE
SW
SW
VE W
S SW
249
64.0
W VE
S
SW
C FO
SW
SW
SW
SW
C
VG
W VE VE
VG C
VW E VE
SW
VG
VEW
SW
T
SW SW W VG
SW
C VG
C
VEW
VG
VE C
SW
VE W
VG
VE
C
VE W SW
C
VG
VE W VE C VG
VE W VE SW
VE
VG
C
W VE
SW
C
VE W
Last saved by: JOSEPH.DELATORRE(2019-09-12) Last Plotted: 2019-09-12 Filename: AECOM_DS10_AU\Documents\60604837-CRL C3-Alliance Detail Design\DesignJV\900 CAD-GIS\01_WIP\25-SKETCHES\CRL-KRD-RME-LKA-SKE-000001
SW
SW
SW
S SW T
SW
1-7
SW
SW
2
S
SW
VE
55
SW
VG SW T
SW
W
SW
SW
SW
S
W
S
W VG
S W
59
SETTLEMENT TANK TO BE EMPTIED WHEN FULL AND DISCHARGED OFFSITE
VG
SW T
T
SW VG
C
SW
SW
VG
VG
SW
S
SW
SW
VG
SW T
SW
SW
C
SW
C
VG
S
SW
W
SW
C
SW
W
SW
SW
SW
SW
SW
SW
SW
SW
SW
T
SW SW
SW
SW
T
WORK ZONE
SW
15-25
SW
SW
SW
S
0
SW
62.
SW FO 290
NOTES: SW SW
SW
SW
SW
0
61.
1. FOR EROSION AND SEDIMENT CONTROL MEASURE STANDARD DETAILS REFER TO GUIDELINE DOCUMENT 005.
S
SW
SW
SW
S
SW
2. STABILISED ENTRANCEWAYS ARE REQUIRED AT ANY ENTRY OR EXIT POINT OF A CONSTRUCTION SITE.
2
0
4
3. ALL DRAWINGS SHALL BE READ IN CONJUNCTION WITH KARANGAHAPE STATION EARLY WORKS ESCP AND CEMP.
8m
SCALE 1:200 4. ALL AREAS ARE INDICATIVE ONLY.
Link Alliance has prepared this document for the sole use of the client and for a specific purpose, each as expressly stated in the document. No other third party should rely on this document without the written consent of Link Alliance. Link Alliance undertakes no duty, nor accepts any responsibility, to any third party who may rely upon or use this document.
CLIENT:
0
10
20
30
40
50
60
CREATOR ID : CRL_KRD_390_00_LKA_SKE_000001 70
80
90
100mm
SIZE A1
FOR INFORMATION APPROVED
PROJECT:
DRAWN
D. ROLLO
TITLE:
J. DELA TORRE A
FOR INFORMATION DESCRIPTION
DR
19.08.19
CHECKED
DATE
APPROVED
DATE
C. SECRETIN
19.08.19
This drawing is confidential and shall only be used for the purpose of this project. The signing of this title block confirms the design and drafting of this project have been prepared and checked in accordance with the Link Alliance quality assurance system to ISO 9001-2000.
CITY RAIL LINK KARANGAHAPE STATION
ZONE:
E. CHANG
REV
COMPANY NUMBER : 6267870
SCALE AS SHOWN
DESIGNED REVISIONS
ISO A1 594mm x 841mm
65
64 .0
.0
62 .0
61
PITT ST
KEY PLAN
EROSION AND SEDIMENT PITT STREET - STAGE 1 SHEET 1 OF 1 PROJECT
DOCUMENT:
ZONE
DISCIPLINE
ORGANISTION
TYPE
SHEET
CRL - KRD - RME - LKA - SKE - 000001
REVISION
A
N
SW
N
ISO A1 594mm x 841mm
KEY PLAN
CL
CL
VG
CL
CL
CL
CL
VG
SW
LEGEND: WORK ZONE
T
65 SW
.0
63
64 .0
62 .0
.0
VG
TREE REMOVAL
T
SW
PEDESTRIAN ACCESS ROUTES VG
EXISTING CRL DESIGNATION BOUNDARIES
ESCP LEGEND:
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
T SW
SW
W
S S
FO
SW
S
SW VG C FO
SW W VG C FO
S
FOC
W SW FOC VG
W
S S SW FO C VG
S
SW
SW FO VG C
W
SS S
SS W
S
SW VG C
SS
SW
FO
W
S
SS
W SW VG C
S
FO
SS
SW
C
FO
W SW VG C
S
FO
SW
C
SW
D
268
AHA ANG KAR
SW SW
SW SW
SW
SW
SW
C
S
SW SW
FCO
S FOC SWW VG
S
256
NOTES:
SW
1. FOR EROSION AND SEDIMENT CONTROL MEASURE STANDARD DETAILS REFER TO GUIDELINE DOCUMENT 005. 2. STABILISED ENTRANCEWAYS ARE REQUIRED AT ANY ENTRY OR EXIT POINT OF A CONSTRUCTION SITE. 3. ALL DRAWINGS SHALL BE READ IN CONJUNCTION WITH KARANGAHAPE STATION EARLY WORKS ESCP AND CEMP.
SW FO
SW
CITYLINK
C FO
S SS W SW VG
S SS S W FOC V W G
FOC
S SS SW W VG
SW
S FO V W CG
S SS W
S FO V W CG
W
SS S
SS S
W
S FO V W G C
W
SS S
FO VSW G C
W
S S
S S
W FO VSW G C
SS SS SW
SW
SW
4. ALL AREAS ARE INDICATIVE ONLY. 290
SCALE
SIZE
AS SHOWN
A1
DESIGNED REVISIONS
100mm
CL
284
FO
90
CHORUS
W S VGW
S SW VGW S
SW VGW
SS S S
S
SW
C FO
SS
SW
W SW
W
80
VODAFONE
C
267-281
W
SW
W
70
VECTOR ELEC
T
278
FO C SW W VG
SW
T
TS
60
VECTOR COMMS FO
VE
16-18
SW
SW
S
50
VECTOR GAS
FO
270
C FO
S S SW
SW
SW
W
W 40
VG
FO
SW
S
259-261
12-14
S S S SW S W FO C V W G
SW SW
SW SW SW SW SW SW
S
T
CREATOR ID : CRL_KRD_390_00_LKA_SKE_000002
POTABLE WATER
C FO
S S S W SW VG
SW
SW SW
SW
SW
SW
VE
W
S
S SS W SW VG
SW
SW
SW
SW VG
C
VE
VE W
VG
C
SW
VE W VE C VG
SW
W VE VE
C VG
SW
W VE
VE C VG
SW
W VE
VE
VGC SW
W VE VE
SW
T
VE
VE
VE
VE
VE
VE
W
SW
C
C
T
T S
VG
C
VE VE
VE
VG C VG
W
VE
VG C
W T
VE
S SS
VE
VE
VE
VE
VGC
S
VG
VE
VE
W
VG C
S S
SS
VE W
VG C
C VG
W VE
C VG
S SW
WASTEWATER
S W
8-10
SW
SW
246-254
STORMWATER
SW
258
SW
SW
EXISTING STORMWATER
SW
4-6
SW
30
PROPOSED
SW
20
> UTILITIES LEGEND: SILT SOCK
243
SW
10
T
VE
SETTLEMENT TANK
S
SW
SW
SW
FOR INFORMATION APPROVED
PROJECT:
DRAWN
D. ROLLO
TITLE:
J. DELA TORRE A
FOR INFORMATION DESCRIPTION
DR
19.08.19
CHECKED
DATE
APPROVED
DATE
C. SECRETIN
19.08.19
This drawing is confidential and shall only be used for the purpose of this project. The signing of this title block confirms the design and drafting of this project have been prepared and checked in accordance with the Link Alliance quality assurance system to ISO 9001-2000.
CITY RAIL LINK KARANGAHAPE STATION
ZONE:
E. CHANG
REV
COMPANY NUMBER : 6267870
SW
S
61-65
Link Alliance has prepared this document for the sole use of the client and for a specific purpose, each as expressly stated in the document. No other third party should rely on this document without the written consent of Link Alliance. Link Alliance undertakes no duty, nor accepts any responsibility, to any third party who may rely upon or use this document.
CLIENT:
0
S
SW SW
SW SW SW SW
SW
VE C
VEW
VG VE
C
VG
VE W VE
C
VE W
SW SW
SW
0
62.
SCALE 1:200
S
249
SW
8m
SS
SW
SQ OR D
RE SF BE
SW
C
W VE
VG
SW
VE
VG C
VW E
SW
VE C
VG
VEW
SW
SW
4
15-25
SS
SW SW
SW
SW SW
T
SW W VG
C
SW
VG
VE VEW
VG
VE C
VE W
VG
VE
C
SW
VE W SW
C
VG
VE W VE
C VG
VE W VE
SW
VG
C
W VE
VE
Last saved by: JOSEPH.DELATORRE(2019-09-12) Last Plotted: 2019-09-12 Filename: AECOM_DS10_AU\Documents\60604837-CRL C3-Alliance Detail Design\DesignJV\900 CAD-GIS\01_WIP\25-SKETCHES\CRL-KRD-RME-LKA-SKE-000002
SW
SW
64.0
63.0
0
SW SW
2
2
SW
S
S S
SW
55
1-7
SW W
SW
C
W
SW
SW
SW
S
SW
DIVERTED DIRTY WATER WILL BE FILTERED THROUGH SILT SOCKS, OR EQUIVALENT METHOD, BEFORE BEING RELEASED TO KERB AND CHANNEL
SW
S
T
SW VG
C W
VG
S W
59
VG
S SW
SW
SW
SW T
SW
SW INLET PROTECTION
S
C
C
VG
SW
VG SW T
SW
DIRTY WATER DIVERSION
SW
SW
VG SW T
S
SW
C SW
SW T
S
T
SW
W
SW
W
SW
S
C
SW
S
VG
CLEAN WATER DIVERSION BUND
SW
SW SW
S
SW
SW
SW
SW
SW
SW
W
PITT ST
SW
STABILISED ENTRANCE
> >
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
PE R
SW
VG
SW
VG
SW
T
SW
VG
SW SW
SW
SW
T
SW
SW
SW
SW
SW
SW
SW
SW
61 .0
PITT ST
EROSION AND SEDIMENT PITT STREET - STAGE 2 SHEET 1 OF 1 PROJECT
DOCUMENT:
ZONE
DISCIPLINE
ORGANISTION
TYPE
SHEET
CRL - KRD - RME - LKA - SKE - 000002
REVISION
A
SW
SW
SW
T
N
SW
VG
SW
T
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
VG
SW
T
SW
SW
SW
SW
SW
SW
SW S
SW
FO C
S
S W VG SW
S
S
S
C FO
S S
W VG SW
S S
S
C FO 4-6
SW
FCO
D
SW
FOC
S
SW
PE R
FO
S C VG W
8-10
AHA
W
S
S
S C VG W
S W S S S FO C VG SW W
S S
VG SW W
S
VG SW W
S
S
243
SW SW
KAR
FO
ANG
249
FO
S S S V W S CG W
S S S
268
259-261
SW
12-14
FO
SW
W VGSW
C
S S S
270
C FO
SW
S
SW
VGSWW
S
61-65
FOC
SW
VGSW W
LEGEND:
16-18
SW
FO C
C V SW G W
FO
SW
S S W
S
SW
CVGSW
S
S
W
ESCP LEGEND:
VGSW C
S
FO
S
EXISTING CRL DESIGNATION BOUNDARIES
FO
FO
284
W
STABILISED ENTRANCE
> >
FO
S
PEDESTRIAN ACCESS ROUTES
267-281
SW SW
W
278
WORK ZONE
FO
SW TS
SW
S S C VGSW S W
SW SW
VEVE
C
VEVE
T
C
T VEVE
W
W
S
T
W SW
W
SW
VG
S
VEVE
W
W
SW
SW
SW
S VG
C
T VEVE
SW
VG C
S
VG
T VEVE
SW S
VG C
S
S
S
SW
S
S
SW
VG VGC
S S
S
W VVEE
SW
W
S
SW
SW
FCO
VGSWW
S
S
SW
VG C
SW
W
S
S
S
SW
T
S
SW SW
SW SW
SW SW
SW
SW SW
SW
SW WSWS SW S S S VG W C W S FO S S S VG W S C W FO S S S VG W S C W
SW
C SW VG
VVEE W
C SW VG
VVEE W
W
SW VGC
VVEE W
SW VG C
VVEE
SW VG C
W C
VVEE W
SW VG
C
W SW VG
C
S
SW
VVEE
S
SW
SW
SW
VVEE
S SW
SW
VVEE
SW
SW
62.
CLEAN WATER DIVERSION BUND DIRTY WATER DIVERSION SW INLET PROTECTION
SW
0 SW
SW
290
SETTLEMENT TANK SW
SW
PROPOSED
SW
S SW
SW
0 61.
> UTILITIES LEGEND: SILT SOCK
SW
S
SW
S
S SW
T W VG SW
SW
C
C
SW
SW
64.0
63.0
15-25
SW
S
SW
S
SW VG C
W C
W VVEE C
SW V G
VVEEW C
SW V BE G RE SF OR D SQ
VVEEW
C
SW V G
VVEE W C SW V G
VVEE W
SW SW
2
SW
SW
S
SW
SW
SW SW
1-7
Last saved by: JOSEPH.DELATORRE(2019-09-13) Last Plotted: 2019-09-23 Filename: AECOM_DS10_AU\Documents\60604837-CRL C3-Alliance Detail Design\DesignJV\900 CAD-GIS\01_WIP\25-SKETCHES\CRL-KRD-RME-LKA-SKE-000003
SW
SW
SW V G
W VVEE
SW VG
W VVEE
SW
S
T
SW
55
W
59
47
S VG SW
T
W VG SW C
SW
SW
SW
S VG SW T
SW T
FO
SW
C
SW
S
W C
SW
SW
VG
SW
C
SW
W
SW
VG
SW
SW
SW
T
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
VG
T
SW
PITT ST
SW
N
SW
VG
.0
ISO A1 594mm x 841mm
63
SW
.0 65
SW
64 .0
62 .0
61 .0
PITT ST
FILTER SOCK OR LOGS CAN BE USED TO FILTER SEDIMENT AND TO THEN DISCHARGE TO AN EXISTING CP DOWNSTREAM
KEY PLAN
EXISTING
SW
STORMWATER
S
WASTEWATER
SW
STORMWATER
SW 283-287
S
SW SW
SW
SW
S
SW
SW
SW
SETTLEMENT TANK TO BE EMPTIED WHEN FULL AND DISCHARGED OFFSITE
SW
SW
VECTOR COMMS FO
VE
VECTOR ELEC
T
VODAFONE
C
CHORUS
CL
CITYLINK
292-300
SW
SW
SW
SW
SW
SW
SW
SW
1. FOR EROSION AND SEDIMENT CONTROL MEASURE STANDARD DETAILS REFER TO GUIDELINE DOCUMENT 005.
W
ST
5
VECTOR GAS
FO
NOTES:
UN 0
POTABLE WATER
SW
SW
SW
SW 295
SW
SW
SW
SW
TO PE HO 2.5
W VG
22-28
2. STABILISED ENTRANCEWAYS ARE REQUIRED AT ANY ENTRY OR EXIT POINT OF A CONSTRUCTION SITE. 3. ALL DRAWINGS SHALL BE READ IN CONJUNCTION WITH KARANGAHAPE STATION EARLY WORKS ESCP AND CEMP.
10m
SCALE 1:250 4. ALL AREAS ARE INDICATIVE ONLY.
Link Alliance has prepared this document for the sole use of the client and for a specific purpose, each as expressly stated in the document. No other third party should rely on this document without the written consent of Link Alliance. Link Alliance undertakes no duty, nor accepts any responsibility, to any third party who may rely upon or use this document.
CREATOR ID : CRL_KRD_390_00_LKA_SKE_000003
0
10
20
30
40
50
60
70
80
90
100mm
SIZE A1
FOR INFORMATION APPROVED
PROJECT:
DRAWN
D. ROLLO
TITLE:
J. DELA TORRE A
FOR INFORMATION DESCRIPTION
DR
19.08.19
CHECKED
DATE
APPROVED
DATE
C. SECRETIN
19.08.19
This drawing is confidential and shall only be used for the purpose of this project. The signing of this title block confirms the design and drafting of this project have been prepared and checked in accordance with the Link Alliance quality assurance system to ISO 9001-2000.
CITY RAIL LINK KARANGAHAPE STATION
ZONE:
E. CHANG
REV
COMPANY NUMBER : 6267870
SCALE AS SHOWN
DESIGNED REVISIONS
CLIENT:
EROSION AND SEDIMENT PITT STREET - STAGE 3 SHEET 1 OF 1 PROJECT
DOCUMENT:
ZONE
DISCIPLINE
ORGANISTION
TYPE
SHEET
CRL - KRD - RME - LKA - SKE - 000003
REVISION
A
CL
CL
N
CL
CL
ISO A1 594mm x 841mm
KEY PLAN
. 63
0
.0 T
SW
VG
T
.0 65
N
SW
VG
CL
.0
64
62
61 .0
PITT ST
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
WORK ZONE
W
S
SW
SW
FO
S S
W VG SW C
C FO
VG SW W
> SILT SOCK UTILITIES LEGEND: 256
PROPOSED SW
FCO
SW
FOC
VG SW W
S S S W S S S FO C VG SW W
SW
FO S C VG W
S
246-254
DIRTY WATER DIVERSION
EXISTING
SW
STORMWATER
S
WASTEWATER
SW
W
POTABLE WATER
VG
VECTOR GAS
FO
VECTOR COMMS FO
VE
VECTOR ELEC
T
VODAFONE
C
CHORUS
CL
CITYLINK
STORMWATER
249
SW
FO
S C VG W
CLEAN WATER DIVERSION BUND
S
S
S
C FO
W VG SW
S S S
S S
S
SW
D PE R ANG
SW
AHA
259-261
268
SW
KAR
W VGSW
VE
FO
S S S V W S CG W
S
W
4-6
8-10
270
SW
C FO
SW
VGSWW
S S
VE
SW
SW
FCO
VGSWW
S
SW
FOC
S
VGSW W
278
16-18
SW
FO C
C V SW G W
C VGSW
SW
W
S S S W
S
SW
S CVG W
S S VGSW C
S
FO
W
S S
W
TS SW
FO
SW
FO
S
284
W
VEVE C
T
C
T VEVE
SW
267-281
FO
SW
VG
S
VEVE
W
W
W
W S
VEVE
T
W SW
W
SW
S
VG
C
VG
T VEVE
SW
SW
SW
FO
SW SW
VG C
S
S
T VEVE
SW S
VGC
SW
S
VGC
S
S
S
S
S
SW
S
VG
SW
W
S
C
S
VG
SW
W
S
S
VE
SETTLEMENT TANK
12-14
SW
W VVEE
VE
SW INLET PROTECTION
243
FO
S S S
S
WSWS SW S S S VG W C W S FO S S S VG W S C W FO S S VG W C
S S
SW SW
SW
> >
61-65
C
SW
S
SW
SW
SW
C SW V G
VVEE W SW VGC
W
VVEE SW VG C
W
VVEE W
SW VG C
VVEE
W
SW VG C
C
W
SW VG
C
T
VE
STABILISED ENTRANCE
SW
VVEE
VE
ESCP LEGEND:
S
258
SW
VVEE
S SW
SW
VVEE
SW
FO
62.
SW
0 SW
SW
SW
S
SW
SW
290
SW
S
S SW
SW
VVEE W
C SW VG
SW
S
W
S
BE
SW
S
S
SF RE
SW
SW
15-25
SW
S SW
S
SW SW
SW SW
SW
2
T
W VG SW
SW
W
SQ OR D
SW
SW
SW
S
SW
S SW
SW
0
SW
S
SW
S
SW VG C
C
W VVEE
SW V G
C
W VVEE C
SW V G
VVEEW C
SW V G
VVEEW C
SW V G
VVEE W C SW V G
VVEE W
SW
SW
64.0
63.0
SW
61.
SW 283-287
S
SW SW
22-28
SW
SW
S
SW
SW
SW
SETTLEMENT TANK TO BE EMPTIED WHEN FULL AND DISCHARGED OFFSITE
292-300
SW
SW
2. STABILISED ENTRANCEWAYS ARE REQUIRED AT ANY ENTRY OR EXIT POINT OF A CONSTRUCTION SITE.
SW
3. ALL DRAWINGS SHALL BE READ IN CONJUNCTION WITH SW KARANGAHAPE STATION EARLY WORKS ESCP SWAND CEMP. SW SW
SW
SCALE 1:250
SW
SW
SW
10m
SW
SW
SW
SW
5
1. FOR EROSION AND SEDIMENT CONTROL MEASURE STANDARD DETAILS REFER TO GUIDELINE DOCUMENT 005.
SW
SW
SW
295
SW
0
SW
SW
2.5
NOTES:
SW
4. ALL AREAS ARE INDICATIVE ONLY. SW
W
Last saved by: JOSEPH.DELATORRE(2019-09-13) Last Plotted: 2019-09-13 Filename: AECOM_DS10_AU\Documents\60604837-CRL C3-Alliance Detail Design\DesignJV\900 CAD-GIS\01_WIP\25-SKETCHES\CRL-KRD-RME-LKA-SKE-000004
SW
SW
SW
1-7
Link Alliance has prepared this document for the sole use of the client and for a specific purpose, each as expressly stated in the document. No other third party should rely on this document without the written consent of Link Alliance. Link Alliance undertakes no duty, nor accepts any responsibility, to any third party who may rely upon or use this document.
CREATOR ID : CRL_KRD_390_00_LKA_SKE_000004
10
20
30
40
50
60
70
80
90
100mm
SIZE A1
FOR INFORMATION APPROVED
PROJECT:
DRAWN
D. ROLLO
TITLE:
J. DELA TORRE A
FOR INFORMATION DESCRIPTION
DR
19.08.19
CHECKED
DATE
APPROVED
DATE
C. SECRETIN
19.08.19
This drawing is confidential and shall only be used for the purpose of this project. The signing of this title block confirms the design and drafting of this project have been prepared and checked in accordance with the Link Alliance quality assurance system to ISO 9001-2000.
CITY RAIL LINK KARANGAHAPE STATION
ZONE:
E. CHANG
REV
COMPANY NUMBER : 6267870
SCALE AS SHOWN
DESIGNED REVISIONS
CLIENT:
0
SW
C
SW VG
W VVEE
SW
S
T
SW
55
W
59
47
S VG SW
T
VG SW C
SW
S VG SW T
SW T
FO
SW
SW
SW
C
SW
S
W C
VE
SW S
SW
VG
SW
C
SW
W
SW
VG
SW
SW
SW
EXISTING CRL DESIGNATION BOUNDARIES
SW
SW
T
SW
SW
SW
SW
VG
T
SW
SW
SW
RY LAN E
PEDESTRIAN ACCESS ROUTES
SW
SW
SW
MERCU
SW
64.0
SW
VE
SW
SW
SW
VE
SW
VG
LEGEND:
PITT ST
65.0
SW
VG
SW
T
SW
SW
SW
W
SW
SW
SW
SW
SW
SW
SW
SW
SW
FILTER SOCK OR LOGS CAN BE USED TO FILTER SEDIMENT AND TO THEN DISCHARGE TO AN EXISTING CP DOWNSTREAM
EROSION AND SEDIMENT PITT STREET - STAGE 4 SHEET 1 OF 1 PROJECT
DOCUMENT:
ZONE
DISCIPLINE
ORGANISTION
TYPE
SHEET
CRL - KRD - RME - LKA - SKE - 000004
REVISION
A
CRO
ISO A1 594mm x 841mm
KEY PLAN
SW
N
VE
SW
SW
SW SW
SW
VE
C
SW SW
SW
SW SW
SW
C
SW
C
S
S
SW
S VE
S
SW
VE
C
SW
S
VE
C
S
SW
S
S
S
S
LEGEND:
VE
SW
S
SW VE
SW
S S
PEDESTRIAN ACCESS ROUTES SW
S S VE
STABILISED ENTRANCE CLEAN WATER DIVERSION BUND DIRTY WATER DIVERSION SW
SW
> >
VE
SW
SW INLET PROTECTION
SW
SW
SW
SW
SW
SW
VE
SW
SW
SW
EXISTING CRL DESIGNATION BOUNDARIES
ESCP LEGEND: SW
SW
VE
SW
S
SW
WORK ZONE
SW
VE
SW SW
SETTLEMENT TANK
SW
SW
SW
VE
SW
S
VE
SW
S
Last saved by: JOSEPH.DELATORRE(2019-08-21) Last Plotted: 2019-09-12 Filename: AECOM_DS10_AU\Documents\60604837-CRL C3-Alliance Detail Design\DesignJV\900 CAD-GIS\01_WIP\25-SKETCHES\CRL-KRD-RME-LKA-SKE-000011
SW W
SW
SW W S
VE
W
SW
VE
S
W
S
SW
S
SW
C
S
S W
SW S
SW
SW
S
S
C
S
SWS W
C
S
S
STORMWATER INLET PROTECTION TO BE ESTABLISHED AROUND CP1
W
SW
S VG
C C
C
C C
C C
SW
T
SW SW
C VE
VE
T
C C
C C
C C
C C C
C C C
CANA DA ST
C
C C
C
VG T
S
W
VG
S
W
S VG
W
57.0
C
59.0
C C
C C
C C
C C
C
CL
58.0
C SW
S SW W
VE
C C
C C
C
VE VE
S
VE
SW
SW
C
W
SW
VG W
VG W
VG
S SW
S
C C C
C C
C C
C C
C C
C C
T
C
VE
T VE
T S
60.0 S
63.0
C
T
C VE
C
VE VE
C C
C C
C C
61.0
VE
SW
T C
C C
62.0
SW
SW
SW
SW
23-31
VE
SW
SW SW
SW SW
SW
VE VE
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
W
W
W
SW
SW
SW
W
SW W
SW
SW SW
SW 11-13
SW
S
SW W
SW
9
VG S
VG S
SW W
SW
SW
SW
SW
SW
3
CL
S
CL T CL T C C VE VEVG S VG S SW W SW W W
SW
SW
SW
SW
SW
SW
T
T T
VE
C
C
C
T
VE
VE
URY MERC
SW
VE
CL
SW
VE
C
SW
SW
VE
CL VE
S
S
VE
VE
S
S
LANE
VE VG
VG VG
S
E
CL T VG VE S
VG
T
CL T
SW
RY LAN
CL T VG VE S
SW L C T
VE
SW
VE T
MERCU
SETTLEMENT TANK TO BE EMPTIED WHEN FULL AND SW SW DISCHARGED OFFSITE SW
VE VE
SW
SW
SW
VE
N
SW
SW
VE
SW
SW
S 2
VE
SW
SW VE
PROPOSED
EXISTING SW
VE
SW
SW
> SILT SOCK UTILITIES LEGEND:
SW
SW
SW
STORMWATER
S
WASTEWATER
SW
STORMWATER
SW VE
SW
SW SW
POTABLE WATER VECTOR GAS
FO SW VE
VECTOR COMMS FO SW
SW
W VG
VECTOR ELEC SW
VE
SW
VE
SW
38
T
VODAFONE
C
CHORUS
CL
CITYLINK
SW SW
VE
ST EAST
SW SW
SW
SW
20
SW
SW
18
NOTES:
SW
SW
VE
SW
SW
SW SW
1. FOR EROSION AND SEDIMENT CONTROL MEASURE STANDARD DETAILS REFER TO GUIDELINE DOCUMENT 005.
SW
16
SW
SW SW
SW
2. STABILISED ENTRANCEWAYS ARE REQUIRED AT ANY ENTRY OR EXIT POINT OF A CONSTRUCTION SITE.
SW
SW
14
SW SW
29
SW
4
SW
8m
SW
SW
3. ALL DRAWINGS SHALL BE READ IN CONJUNCTION WITH KARANGAHAPE STATION EARLY WORKS ESCP AND CEMP. SW
0
SW
SW
12
SW
SCALE 1:200
SW
SW
SW
SW
2
8
SW
4. ALL AREAS ARE INDICATIVE ONLY.
SW
Link Alliance has prepared this document for the sole use of the client and for a specific purpose, each as expressly stated in the document. No other third party should rely on this document without the written consent of Link Alliance. Link Alliance undertakes no duty, nor accepts any responsibility, to any third party who may rely upon or use this document.
CREATOR ID : CRL_KRD_390_00_LKA_SKE_000011
0
10
20
30
40
50
60
70
80
90
100mm
SIZE A1
FOR INFORMATION APPROVED
PROJECT:
DRAWN
D. ROLLO
TITLE:
J. DELA TORRE A
FOR INFORMATION DESCRIPTION
DR
19.08.19
CHECKED
DATE
APPROVED
DATE
C. SECRETIN
19.08.19
This drawing is confidential and shall only be used for the purpose of this project. The signing of this title block confirms the design and drafting of this project have been prepared and checked in accordance with the Link Alliance quality assurance system to ISO 9001-2000.
CITY RAIL LINK KARANGAHAPE STATION
ZONE:
E. CHANG
REV
COMPANY NUMBER : 6267870
SCALE AS SHOWN
DESIGNED REVISIONS
CLIENT:
EROSION AND SEDIMENT MERCURY LANE - STAGE 1 SHEET 1 OF 1 PROJECT
DOCUMENT:
ZONE
DISCIPLINE
ORGANISTION
TYPE
SHEET
CRL - KRD - RME - LKA - SKE - 000011
REVISION
A
SW
N
SW SW
SW
SW
SW
VE
C
SW
VE
SW
C
T
SW
C VE
C
SW
SW
C
SW
S
S
C
SW
C
S
S
SW
S VE
S
SW
VE
C
S
VE VE
WORK ZONE SW
S
S
VE
S
SW
S SW
VE
SW
DIRTY WATER DIVERSION
VE
SW
SETTLEMENT TANK
VE
> SILT SOCK UTILITIES LEGEND:
SW
SW
VE VE
SW
SW
SW
PROPOSED
VE
SW
VE
SW
SW
STORMWATER
S
WASTEWATER
SW VE
SW
W
POTABLE WATER
VG
VECTOR GAS
FO
VECTOR COMMS FO
VE
VECTOR ELEC
STORMWATER
SW
VE
SW
38
EXISTING SW
SW
SW
SW
SW INLET PROTECTION
SW
SW
SW
SW SW
CLEAN WATER DIVERSION BUND SW
S
SW
STABILISED ENTRANCE
> >
SW
SW
VE
SW
S
ESCP LEGEND:
SW
SW
EXISTING CRL DESIGNATION BOUNDARIES SW
S
SW
VE
SW
S
PEDESTRIAN ACCESS ROUTES
SW
SW
SW
LEGEND:
S
S
SW
S
VE
SW
SW
C
S
S
SW
SW W
Last saved by: JOSEPH.DELATORRE(2019-09-12) Last Plotted: 2019-09-12 Filename: AECOM_DS10_AU\Documents\60604837-CRL C3-Alliance Detail Design\DesignJV\900 CAD-GIS\01_WIP\25-SKETCHES\CRL-KRD-RME-LKA-SKE-000012
SW W S
VE
W
SW
VE
S
W
S
SW
S
SW
C
SW
C
CANA
S
SW
DA ST
SW
S
C
SWS W SW S
S W
W
SW
S VG S S
C C
C C C
C C
C C
C C
C C
C C
STORMWATER INLET PROTECTION TO BE ESTABLISHED AROUND CP1
SW
VG T S
W
VG
S
W
S VG
W
57.0 C C
SW
CL
T
C
C C
C C
C C C
C C C
C C
C
C C
C C
C C
C
59.0
S
C C
C C
SW
SW
SW SW
VE
VE
SW VE
VE
S
VE
58.0
SW
W
VG
S SW
SW
SW
C
C
W
VG
W
VG S
60.0 S
VE
C
VE VE
T
SW
T VE
T
C
T
C
61.0
VE
SW
S SW W
C C
SW
T C
C C
SW
SW
63.0
C
VE
SW
SW SW SW
SW
C C
SW
SW
SW
62.0
VE
SW
C C
C C
C C
C C
SW
SW
SW SW SW
VE
N
SW
SW
23-31
VE
SW
SW
VE VE
SW
SW
SW
SW
W
SW
SW
SW
SW
SW
SW
SW
W
W
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
W
SW
SW W
SW
SW
SW
SW
T
T
T 11-13
T
SW
W
SW SW
SW
SW W
SW
9
VG S
SW
SW
3
CL S
CL T C VE VG S
W
SW
SW
C
VE
VE
VG S
SW
S
VE
CL
S W
S
VE
C
VG
S
SW W
SW
SW
SW
VE
CL VE
S
S
SW
VE
C
VE S
ANE
SW
SW
VE
VE
C
CL T VG
CL T VG VE S
CL T C VEVG S
URY L MERC
VE VG
VG
SW
CROSS ST
SW
RY LAN E
T
CL T
SW
MERCU
SW
T SW L C T VG
SW
VE
VE
SW
SETTLEMENT TANK TO BE EMPTIED WHEN FULL AND DISCHARGED OFFSITE
VE VE
SW
SW
2
SW
SW
SW
ISO A1 594mm x 841mm
KEY PLAN
DIVERTED DIRTY WATER WILL BE FILTERED THROUGH SILT SOCK, OR EQUIVALENT METHOD, BEFORE BEING RELEASED TO KERB AND CHANNEL TO AN EXISTING SW CP
T
VODAFONE
CSW
CHORUS
SW
SW
VE
CL
SW
CITYLINK
SW
SW
SW
20
SW SW
VE VE
NOTES:
SW
SW
1. FOR EROSION AND SEDIMENT CONTROL MEASURE STANDARD DETAILS REFER TO GUIDELINE DOCUMENT 005.
SW
SW
SW
SW
SW
18
SW SW
SW
SW
3. ALL DRAWINGS SHALL BE READ IN CONJUNCTION WITH KARANGAHAPE STATION EARLY WORKS ESCP AND CEMP.
SW
SW SW
29
SW
SCALE 1:200
SW
12
4. ALL AREAS ARE INDICATIVE ONLY.
SW
REVISIONS
CREATOR ID : CRL_KRD__00_LKA_SKE_000012
COMPANY NUMBER : 6267870 10
20
30
40
50
60
70
80
90
100mm
SCALE
SIZE
AS SHOWN
A1
DESIGNED
FOR INFORMATION APPROVED
PROJECT:
DRAWN
D. ROLLO
TITLE:
J. DELA TORRE A
FOR INFORMATION DESCRIPTION
DR
19.08.19
CHECKED
DATE
APPROVED
DATE
C. SECRETIN
19.08.19
This drawing is confidential and shall only be used for the purpose of this project. The signing of this title block confirms the design and drafting of this project have been prepared and checked in accordance with the Link Alliance quality assurance system to ISO 9001-2000.
CITY RAIL LINK KARANGAHAPE STATION
ZONE:
E. CHANG
REV
0
SW
Link Alliance has prepared this document for the sole use of the client and for a specific purpose, each as expressly stated in the document. No other third party should rely on this document without the written consent of Link Alliance. Link Alliance undertakes no duty, nor accepts any responsibility, to any third party who may rely upon or use this document.
CLIENT:
SW
8m
SW
4
SW
SW SW
14
0
2. STABILISED ENTRANCEWAYS ARE REQUIRED AT ANY ENTRY OR EXIT POINT OF A CONSTRUCTION SITE.
SW
16
2
SW
T
S EAST
SW SW
EROSION AND SEDOMENT MERCURY LANE - STAGE 1A SHEET 1 OF 1 PROJECT
DOCUMENT:
ZONE
DISCIPLINE
ORGANISTION
TYPE
SHEET
CRL - KRD - RME - LKA - SKE - 000012
REVISION
A
CRO
SW
N
C
SW SW
VE
SW
VE VE
C
SW SW
SW
S VG
C
SW
C
SW SW SW
C
S
S
SW
S VE
S
SW
VE
C
SW
S
VE
C
S
SW
S
S
S
S
LEGEND:
VE
SW
S
SW VE
SW
S S
PEDESTRIAN ACCESS ROUTES SW
S S VE
STABILISED ENTRANCE CLEAN WATER DIVERSION BUND DIRTY WATER DIVERSION SW
SW
> >
VE
SW
SW INLET PROTECTION
SW
SW
SW
SW
SW
SW
VE
SW
SW
SW
EXISTING CRL DESIGNATION BOUNDARIES
ESCP LEGEND: SW
SW
VE
SW
S
SW
WORK ZONE
SW
VE
SW SW
SETTLEMENT TANK
SW
SW
SW
VE
SW
S
VE
SW
S
Last saved by: JOSEPH.DELATORRE(2019-08-19) Last Plotted: 2019-08-19 Filename: AECOM_DS10_AU\Documents\60604837-CRL C3-Alliance Detail Design\DesignJV\900 CAD-GIS\01_WIP\25-SKETCHES\CRL-KRD-RME-LKA-SKE-000013
SW W
SW
SW W S
VE
W
SW
VE
S
W
S
SW
C
S
SW
SW
CANA DA ST
DIVERTED DIRTY WATER WILL BE FILTERED THROUGH SILT SOCKS, OR EQUIVALENT METHOD, BEFORE BEING RELEASED TO KERB AND CHANNEL TO AN EXISTING SW CP S
SW S
SW
S
S
C
S
SWS W
C
S
S
S W
W
SW
S VG
C C
C C C
C C C
C C
C
SW
W
57.0 C C
C C
C
VG T
S
T S
W
T
C
C C
C C
C C
C C
C C
C
59.0
C C
C C
C C
C C
C
CL
W
SW
SW
58.0
C SW
S SW W
VG
VE
VE
S
C
W
SW
VG W
VG W
VG
S SW
S
C C C
C C
C C
C C
C C
C C
T
C
VE
T VE
T S
60.0 S
63.0
C
T
C VE
C
VE VE
C C
C C
C C
61.0
VE
SW
T C
C C
62.0
VE
SW
SW
SW
23-31
SW
SW
VE VE
VE
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
W
W
W
W
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW SW
SW SW 11-13
SW W
SW
SW
SW
SW
SW SW
SW 9
SW W
W
W
SW
SW
SW SW
SW
SW
C VE VG S
SW
W
SW
SW
SW
SW
SW
SW
3
VG S
S
VE
VG S
S
S
SW W
SW
SW
SW
T
T T C
VE
T
VE
CL
VG
S
S
SW
VE
C
VE S
SW
VE
CL VE
CL T VG
CL T VG VE S
CL T VEVG S
VG
SW
VE
C
CL
C
A URY L MERC
VG S
VE
VE
C
CL T
NE
VE VG
T
CL T
S
E
SW L C T
SW
RY LAN
VE
T
CP2
MERCU
VE SW
VE
VE VE
SW
SW
2
SW SW
SW
VE
SW
SW
VE
SW
VE
SW
SW
SW
SW
SW
SW
SW
SW
N
KEY PLAN SW
ISO A1 594mm x 841mm
SW
CP3
CP4
SW
SW
VE
SW
SW VE
PROPOSED
EXISTING SW
VE
SW
SW
> SILT SOCK UTILITIES LEGEND:
SW
SW
SW
STORMWATER
S
WASTEWATER
SW
STORMWATER
SW VE
SW
SW SW
POTABLE WATER VECTOR GAS
FO SW VE
VECTOR COMMS FO SW
SW
W VG
VECTOR ELEC SW
VE
SW
VE
SW
38
T
VODAFONE
C
CHORUS
CL
CITYLINK
SW SW
VE
ST EAST
SW SW
SW
SW
20
SW
SW
18
NOTES:
SW
SW
VE
SW
SW
SW SW
1. FOR EROSION AND SEDIMENT CONTROL MEASURE STANDARD DETAILS REFER TO GUIDELINE DOCUMENT 005.
SW
16
SW
SW SW
SW
2. STABILISED ENTRANCEWAYS ARE REQUIRED AT ANY ENTRY OR EXIT POINT OF A CONSTRUCTION SITE.
SW
SW
14
SW SW
29
SW SW
8m
SW
SW
3. ALL DRAWINGS SHALL BE READ IN CONJUNCTION WITH KARANGAHAPE STATION EARLY WORKS ESCP AND CEMP.
SW
SW
4
SW
0
SW
SW
12
SCALE 1:200
SW
SW
SW
SW 8
SW
4. ALL AREAS ARE INDICATIVE ONLY.
SW
2
SW
Link Alliance has prepared this document for the sole use of the client and for a specific purpose, each as expressly stated in the document. No other third party should rely on this document without the written consent of Link Alliance. Link Alliance undertakes no duty, nor accepts any responsibility, to any third party who may rely upon or use this document.
CREATOR ID : CRL_KRD__00_LKA_SKE_000013
0
10
20
30
40
50
60
70
80
90
100mm
SIZE A1
FOR INFORMATION APPROVED
PROJECT:
DRAWN
D. ROLLO
TITLE:
J. DELA TORRE A
FOR INFORMATION DESCRIPTION
DR
19.08.19
CHECKED
DATE
APPROVED
DATE
C. SECRETIN
19.08.19
This drawing is confidential and shall only be used for the purpose of this project. The signing of this title block confirms the design and drafting of this project have been prepared and checked in accordance with the Link Alliance quality assurance system to ISO 9001-2000.
CITY RAIL LINK KARANGAHAPE STATION
ZONE:
E. CHANG
REV
COMPANY NUMBER : 6267870
SCALE AS SHOWN
DESIGNED REVISIONS
CLIENT:
EROSION AND SEDIMENT MERCURY LANE - STAGE 2 SHEET 1 OF 1 PROJECT
DOCUMENT:
ZONE
DISCIPLINE
ORGANISTION
TYPE
SHEET
CRL - KRD - RME - LKA - SKE - 000013
REVISION
A
SW
ISO A1 594mm x 841mm
SW
LEGEND: WORK ZONE
SW
TN
SAFETY ZONE / CONES PEDESTRIAN ACCESS ROUTES
SW
N
SAFETY BARRIER LINES
SW
UTILITIES LEGEND:
SW
PROPOSED
DIRTY WATER TO BE DIVERTED TO THE SETTLEMENT TANK. WHICH IS TO BE EMPTIED WHEN FULL AND DISCHARGED OFFSITE
S
WASTEWATER
STORMWATER
SW
POTABLE WATER VECTOR GAS VECTOR COMMS FO
FO
OUN ST
STORAGE
VECTOR ELEC T
VODAFONE
C
CHORUS
CL
CITYLINK
STORAGE
ESCP LEGEND: STABILISED ENTRANCE
OFFICES
HOPE T
STORMWATER
CANTEEN
SILT FENCE
CHANGING ROOMS\ TOILETS\ SHOWERS
> >
HOPETOUN ALPHA
WATER TREATMENT AREA
CLEAN WATER DIVERSION BUND DIRTY WATER DIVERSION INDICATIVE FLOW PATH INDICATIVE CONSTRUCTION YARD INDICATIVE LAYDOWN AREA SW INLET PROTECTION SETTLEMENT TANK
NOTES:
STORAGE
Last saved by: JOSEPH.DELATORRE(2019-09-12) Last Plotted: 2019-09-12 Filename: AECOM_DS10_AU\Documents\60604837-CRL C3-Alliance Detail Design\DesignJV\900 CAD-GIS\01_WIP\25-SKETCHES\CRL-KRD-RME-LKA-SKE-000021
EXISTING
SW
CAR PARK
1.
FOR EROSION AND SEDIMENT CONTROL MEASURE STANDARD DETAILS REFER TO GUIDELINE DOCUMENT 005.
2.
STABILISED ENTRANCEWAYS ARE REQUIRED AT ANY ENTRY OR EXIT POINT OF A CONSTRUCTION SITE.
3.
ALL DRAWINGS SHALL BE READ IN CONJUNCTION WITH KARANGAHAPE STATION EARLY WORKS ESCMP.
SURGE PILE
WHEEL WASHING
OFFICES
OFFICE
5
W
W VE
VE VE
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
W VE
SW
SW
SW
C
C
VG
VG
VG
VG
C
W
W
VG
VE
SW
VE
S
S
C VG VE
S
S
SW
VE
C VG
S VE
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
S T
C VG
T
SW
SW
S VE
VE
60m
SCALE 1:1500
SW
Link Alliance has prepared this document for the sole use of the client and for a specific purpose, each as expressly stated in the document. No other third party should rely on this document without the written consent of Link Alliance. Link Alliance undertakes no duty, nor accepts any responsibility, to any third party who may rely upon or use this document.
CREATOR ID : CRL_KRD_390_00_LKA_SKE_000021
0
10
20
30
40
50
60
70
80
90
100mm
SIZE A1
FOR INFORMATION APPROVED
PROJECT:
DRAWN
D. ROLLO
TITLE:
J. DELA TORRE A
FOR INFORMATION DESCRIPTION
DR
19.08.19
CHECKED
DATE
APPROVED
DATE
C. SECRETIN
19.08.19
This drawing is confidential and shall only be used for the purpose of this project. The signing of this title block confirms the design and drafting of this project have been prepared and checked in accordance with the Link Alliance quality assurance system to ISO 9001-2000.
CITY RAIL LINK KARANGAHAPE STATION
ZONE:
E. CHANG
REV
COMPANY NUMBER : 6267870
SCALE AS SHOWN
DESIGNED REVISIONS
CLIENT:
VE C
C
SW
VE SW
C
SW
C
SW
W
30
VE
SC VG
SW
SW
0
W VE
C VG
SW
T
SW
VE
SW
VE
VE
SW
VE
VE
T
SW
W
SW
W
SW
15
VG
W
SW
SW
SW
SW
C VG
SW
W
T W
SW
SW
W VE
VE
W SW
T
SW SW
.0
63
62
SW
W
VE
VE
VG
VE
W
W
SW
.0
BERESFORD SQUARE
.0
SW
VE
C
W
T W
SW
T
SW
PUBLIC CAR PARK CLOSED DURING WORKS
61
SW
W
VE
C
VE
PEDESTRIAN ENTRANCE
SHAKER RAMP AND/OR WHEEL WASH SHOULD BE PLACED AT THE EXIT TO REMOVE SEDIMENT FROM TRUCK TYRES. OTHERWISE LOCALISED WHEEL WASH WILL BE USED AS A MINIMUM REQUIREMENT
W VE
VE
VG
STABILISED ENTRY AND EXIT FOR TRUCKS. IT SHOULD BE MINIMUM 5m IN LENGTH
W VE
VE
W
EXIT
ENTRANCE
CONSTRUCTION LAYDOWN AREA PITT STREET SHEET 1 OF 3 PROJECT
DOCUMENT:
ZONE
DISCIPLINE
ORGANISTION
TYPE
SHEET
CRL - KRD - RME - LKA - SKE - 000021
REVISION
A
SW
SW
SW
ISO A1 594mm x 841mm
SW
SW
VE
SW
C CC
C C C
SW
SW
SW
SW
SW
SW
SW
ENTRANCE
VE
CC
C C
CC
C C
CC
C C
C C C
C
SW
SW SW
SW
SW SW
SW SW
SW
STABILISED ENTRY AND EXIT FOR TRUCKS. IT SHOULD BE MINIMUM 5m IN LENGTH
SW
CAR CA EXIT ENT R RANCE
VE
C
C
W
C
SW
C
SW
SW
SW
SW
VE
SW
SW
SW
SW
VE
CHANGING ROOMS TOILETS / SHOWERS
SURGE PILE
LEGEND: WORK ZONE SW
SW
SAFETY ZONE / CONES SW
SW
BANK
SW
CRANE AREA
SW
VE
SW
SW
SW
VE
SW
VE
SW
VE
SW
BANK
BANK
SW
VE VE
VE
SW
VE VE
C SW
CA
CAR PARK
C C
SW
SW
SW SW
SW
SW
SW
SW
OFFICES
SW SW
VE
PEDESTRIAN ACCESS ROUTES
VE
SW
SAFETY BARRIER LINES
SW
PROPOSED
SW
VE
CANTEEN
VECTOR COMMS FO
STORMWATER
VECTOR ELEC VODAFONE
C
CHORUS
CL
CITYLINK
SW
T
ESCP LEGEND: SW
VE
SW
STORAGE
OFFICES
SW
VECTOR GAS
FO VE
SW SW
TUNNEL STORAGE
WATER TREATMENT AREA
SW
POTABLE WATER
SW
SW VE VE
VE VE
STORAGE
FOR EROSION AND SEDIMENT CONTROL MEASURE STANDARD DETAILS REFER TO GUIDELINE DOCUMENT 005.
WASTEWATER
VG
SW
1.
S
SW
VE
SITE TRACK
SW
NOTES:
STORMWATER
W
SURGE PILE
EXISTING
SW
SW
VE
SW
UTILITIES LEGEND:
SW
STABILISED ENTRANCE
4
SCALE 1:200 SW SW
8m
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW SW
SW
SW
SW
SW
SW
30
40
50
60
70
80
90
100mm
SW
SW
SW
SCALE
SIZE
AS SHOWN
A1
DESIGNED REVISIONS
CREATOR ID : CRL_KRD_390_00_LKA_SKE_000022
COMPANY NUMBER : 6267870 20
SW
Link Alliance has prepared this document for the sole use of the client and for a specific purpose, each as expressly stated in the document. No other third party should rely on this document without the written consent of Link Alliance. Link Alliance undertakes no duty, nor accepts any responsibility, to any third party who may rely upon or use this document.
SW
SW
SW
SW
FOR INFORMATION APPROVED
SW
SW
SW
DRAWN
A
FOR INFORMATION DESCRIPTION
TITLE:
DR
19.08.19
CHECKED
DATE
APPROVED
DATE
C. SECRETIN
19.08.19
This drawing is confidential and shall only be used for the purpose of this project. The signing of this title block confirms the design and drafting of this project have been prepared and checked in accordance with the Link Alliance quality assurance system to ISO 9001-2000.
CLEAN WATER DIVERSION BUND DIRTY WATER DIVERSION INDICATIVE FLOW PATH INDICATIVE CONSTRUCTION YARD
CITY RAIL LINK KARANGAHAPE STATION CONSTRUCTION LAYDOWN AREA MERCURY LANE SHEET 2 OF 3 PROJECT
DOCUMENT:
SW INLET PROTECTION SETTLEMENT TANK
SW
ZONE:
D. ROLLO
J. DELA TORRE
SW
PROJECT:
E. CHANG
REV
10
SW
> >
INDICATIVE LAYDOWN AREA
EAST ST
SW
0
DIRTY WATER TO BE DIVERTED TO THE SETTLEMENT TANK. WHICH IS TO BE EMPTIED WHEN FULL AND DISCHARGED OFFSITE
SW
2
SW
ALL DRAWINGS SHALL BE READ IN CONJUNCTION WITH KARANGAHAPE STATION EARLY WORKS ESCMP.
SW
3.
VE
STABILISED ENTRANCEWAYS ARE REQUIRED AT ANY ENTRY OR EXIT POINT OF A CONSTRUCTION SITE.
SW
SILT FENCE 2.
SW
Last saved by: JOSEPH.DELATORRE(2019-09-12) Last Plotted: 2019-09-12 Filename: AECOM_DS10_AU\Documents\60604837-CRL C3-Alliance Detail Design\DesignJV\900 CAD-GIS\01_WIP\25-SKETCHES\CRL-KRD-RME-LKA-SKE-000022
SW
SW
SW
CLIENT:
0
SW
SW
TEMPORARY SHAFT
SW
SW
MERCURY LANE STATION
NA
SW
SW
ST
SW
SW
DA
SW
S C
SW
SW
SITE TRACK
SW
SW S
SW SW
SW
SW
SW
CC
SW
SW
C
VE
STABILISED ENTRY AND EXIT FOR TRUCKS. IT SHOULD BE MINIMUM 5m IN LENGTH
SW
C
VE
SW SW
SW
SW
C C
SW
EXIT VG
C
CC
SW
SW
CC C
SW S W
C C
SW
SW
T
VG
SW
W
57.0
58.0
C
59.0
SW
SW
SW
SHAKER RAMP AND/OR WHEEL WASH SHOULD BE PLACED AT THE EXIT TO REMOVE SEDIMENT FROM TRUCK TYRES. OTHERWISE LOCALISED WHEEL WASH WILL BE USED AS A MINIMUM REQUIREMENT
SW
T
VG SW
CC CC
CC
MERCURY LANE
W
SW
SHAKER RAMP AND/OR WHEEL WASH SHOULD BE PLACED AT THE EXIT TO REMOVE SEDIMENT FROM TRUCK TYRES. OTHERWISE LOCALISED WHEEL WASH WILL BE USED AS A MINIMUM REQUIREMENT
C
W
SW
SW
SW
VE
VE
W
C
W
VG W
CC
CC
CC
CC
SWS W
SW
SW
VG
S SW
SW
VE
C
W
C
T
S
VE
60.0
VE
C
SW
VE
SW
CC CC
CC
T
SW
VE
SW
VE VG
SW
VE
SW W
S
C
SW W
VG S
T
SW
SW W
T
T
T VG
S
VE
CL
VG SW
SW CL T VG S VE
T VG
SW
W
SW
VE
T C
SW
CL
W
VE S
S
VE
W
SW W
CL
T
N IA TR CE ES N D RA PE NT E
SW
SW
VE
SW
SW
VE
SW
VG
W
S
SW
VG
C
SW
CL VE S
SW
N
SW
CRO SS ST VE
T
VE T
SW
SW
CL T C VG VE S
SW
63 .0
T
VE C
CL T C VG VE S
C
SW
VE
CL C VE VG S
SW
SW
SW
61. 0
S
SW
VG
SW
C CL VE
CL
S
SW
C
SW
VE
C
SW
SW
SW
62 .0
CLEAN WATER DIVERSIONS TO DIVERT AWAY FROM THE CSA
SW
SW
E
SW
LAN
T
RY
T
VE
S
RCU SW
VE
T
VE
S
ME
SW
VE
SW
VE
SW
SW
VE
SW
SW
SW
VE
SW
SW SW
TN
VE
ZONE
DISCIPLINE
ORGANISTION
TYPE
SHEET
CRL - KRD - RME - LKA - SKE - 000022
REVISION
A
Erosion and Sediment Control Plan – Karangahape Station
Appendix C: Record of CLG and Auckland Council Comments C1. CLG Comments A Karangahape CLG meeting was held on 17 September 2019 to discuss the Karangahape early works and for the CLG to provide comments / feedback on the CEMP and sub-plans, including this ESCP. No comments were received in relation to this ESCP.
C2. Auckland Council Comments This ESCP was provided to Auckland Council as a draft for comment. No comments were received.
Page 26
| Karangahape Station Early Works