Appendix C: Record of CLG, IPR and Auckland Council Comments
C-1: Community Liaison Group (CLG) Comments
A Mt Eden CLG meeting was held on 8 th October to discuss the Mt Eden Enabling Works and for the
CLG to provide comments / feedback on the CEMP and sub-plans, including this C DWP.
No comments were received from the CLG on this C DWP.
C-2: Independent Peer Review (IPR) Comments
The Contamination DWP was reviewed by the Independent Peer Reviewer –Terre Nicholson of HD Geo Limited. Comments received from the Independent Peer Reviewer are documented along with details of resolution are in the following table.
Section of this Contamination DWP
5.10, 5.11, 6.4, 6.6.3 Comment Response
Minor edits for clarity. Edits made as noted.
C-3: Auckland Council Comments
The Contamination DWP was reviewed by Auckland Council Senior Contamination Specialist –Marija Jukic. Comments received from Auckland Council are documented along with details of resolution are in the following table.
Section of this Contamination DWP
5.3: Managed Fill
5.10: Imported fill
7.10: Unexpected Discovery of Contamination Comment Response
Definition of Managed Fill under the Auckland Unitary Plan (Operative in Part) explicitly excludes the acceptance of any asbestos to such facilities within the Auckland region. Proposed sampling rate and analytes to be tested have not been included.
No reference is made to the Team Leader of Central Monitoring being notified upon the unexpected discovery of contamination. Added note that there are currently no managed fill tip sites in the Auckland Region that can accept asbestos.
Added typically sampling rate and
analytes. To be confirmed by the CLS
based on the source site. With further
update to reduce the typically sampling rate from 1 in 1,000 m 3 to 1 in 500 m 3 .
Added requirement to advise prior to carrying out any further work in the area of unexpected contamination.