C1 C2 Minutes August 2020

Page 1

City Rail Link – C1-C2 Community Liaison Group Meeting MINUTES AND ACTION POINTS Rā: Wā: Wāhi:

26 August 2020 5pm – 6:30pm Online, via Microsoft Teams CRL CRL staff & contractors

ATTENDEES CLG Members T Loveridge – Heart of the City

Maria Hernandez-Curry (MHC)

Stakeholder Communications Manager – CRL Ltd

N Quigley

Lucas Nikkel (LN)

C2 Project Manager – CRL Ltd

Nicole Lawton (NL)

Communications Coordinator – CRL Ltd

Andrew Swan (AS)

C1 Construction Manager – CRL Ltd

Jhon Aragon (JA)

C1 Delivery Manager – CRL Ltd

Brandy Smith (BS)

Downer Stakeholder Engagement Manager

Abigail Judson (AJ)

Downer Stakeholder & Communications Assistant

P McLuckie

J Smith

ITEM

UPDATE/ACTIONS

1

Welcome and introductions

• MHC welcomed everyone then introduced the meeting agenda • MHC noted the meeting would be recorded for minute-taking purposes C9 Britomart East Introduction – Maria Hernandez-Curry

2.

Page | 1

MHC Introduces Contract 9 and explains its context/relevance to the wider project: - Futureproof Britomart Station for increased patronage - Ensure station can accommodate 9-car trains up to 24 times / hour - Already contained within $4.4b funding envelope - Construction partners include KiwiRail, who are doing the bulk of the work - Construction to start later this year, completed in early 2024

MHC explains scope: - Large portion of the C9 works is happening underground - Track infrastructure in Britomart East junction - Platform and concourse works