SIBD Annual Report – Aotea Station
2.
Aotea Station
Once completed, the Aotea Station will include platforms, lifts, escalators, rooms for housing stations and tunnel services equipment, an entrance building at Wellesley Street, two additional entrance buildings at Victoria Street, a Plenum at Kingston Street, services, internal and architectural finishings, structural fittings, utilities services diversions and connections. Given the nature and scale of the Aotea Station construction, works will be undertaken in a staged manner. These construction works have been authorised by three separate Outline Plan Packages, with construction works expected to continue until the completion of the Project in 2024. The Aotea Construction Works have been staged as follows: Table 1: Staging of the Aotea Construction Works
Construction Works
Description
Date Approved
Status
Stage 1 to 3 (authorised by OPW60345651)
Canopy removal, network utility relocation and site establishment works.
1 October 2019
Stage 4 and 5 (authorised by OPW60348747)
More Canopy removal and utility relocation works. Micro-tunnelling works along Victoria Street. Site establishment works involving tree removal.
6 December 2019
Main Works (authorised by OPW6035461)
Construction of the Aotea station and associated above ground structures. Mined tunnels for the rail tracks and structural fitout and internal and architectural finishings.
8 May 2020
Complete – the work was undertaken from October 2019 to March 2020. The work commenced in December 2019. Large parts are complete. The work commenced in early 2020 and is scheduled to continue through to late-2023.
Summary of Key Construction Works The following outlines key construction activities occurring during the various stages of the Aotea Construction Works. A detailed account of the Aotea Construction Works is provided in the Construction Environmental Management Plan as relevant to the stage of works. It is noted that the Aotea Construction Works (described in Table 1), are concentrated along Albert Street, between Wyndham Street in the North to Mayoral Drive in the South, and includes works within the adjacent Streets of Kingston, Victoria and Wellesley Streets. Some of the works listed below have already been undertaken. Some will be undertaken later in the Project. Aotea Stage 1 – 3 Canopy removal works along the western side of Albert Street between Victoria Street West and Wellesley Street West. Approximately 680m of trenching works required to relocate utilities, predominantly within the footpaths along Albert Street including within the northern section of the Albert Street slip lane. Page 7
| 2019-2020 SIBD Annual Report - Aotea Station