ITS Master Plan Estimated Cost ATC traffic signal cabinet costs are consistent with NEMA TS-2 cabinets, at approximately $15,000 each. One cabinet is required per signalized intersection. The total cost is estimated to be $2,250,000.

Locations Installation of ATC cabinets will replace all existing NEMA TS-1 and/or TS-2 traffic signal cabinets in a phased implementation. First, TS-1 cabinets on priority corridors will be replaced. Next, remaining TS-1 cabinets across the City will be replaced. Finally, TS-2 cabinets across the City will be replaced.

Recommended Deployment Date FY 2022-2025 for TS-1 cabinets on priority corridors, FY 2026-2027 for remaining TS-1 cabinets, and FY 2027-2030 for TS-2 cabinets.

Communications Upgrade Project Description The Communications Upgrade project will procure, install, and configure communications equipment at signalized intersections on priority corridors in support of traffic signal operations. The communications network is expected to include leased line communications via SuddenLink, fixed wireless communications owned by the City, and cellular communications. The final communication architecture will be determined after pilot study of cellular communications.

Estimated Cost Communications unit costs vary widely depending on the ultimate solution, in a range of $6,000 - $10,000 per intersection. Total cost is estimated to be $1,000,000 - $2,000,000 over 2 years.

Locations Initial rollout of communications will install cellular modems at 77 intersections that are currently on TACTICS. Then, cellular modems will be installed at the remaining 66 locations.

Recommended Deployment Date FY 2021 and 2022.