City of Tyler
ITS Master Plan Recommended Implementation Plan A workshop focused on ATMS Alternatives was conducted on May 12, 2020, with multiple City staff. The discussion below documents the decisions made on 12 possible ITS elements. It should be noted that the core ITS elements are proceeding forward. There are some elements identified that can add value and benefit to the City but require other elements to be deployed first. For those elements, the final decision will be made in the future, which is the appropriate strategy. From these elements, the recommended implementation plan identified staged implementation of the key projects selected to address the needs and future buildout identified throughout the project. The plan also considered project priorities and an annual budget of $1 million. The implementation plan summary table is provided in the Appendix. Complete details of each project are included in the CIP Recommended Projects document, which was developed as part of the ITS Master Plan.
School Zone Flasher System Upgrade Project Description The School Zone Flasher System Upgrade Project will upgrade to a new school zone beacon control system with remote communications, centralized command, and remote monitoring capabilities.
Estimated Cost Upgraded school zone flashers are estimated to cost $3,500 per location, including necessary management software. Total estimated budget is $240,000.
Locations Upgrade 36 school zones that include 72 individual school clocks.
Recommended Deployment Date Deploy in FY 2021.
Traffic Signal Cabinet Modernization Project Description The Traffic Signal Cabinet Modernization project will upgrade outdated NEMA TS-1 and TS-2 traffic signal cabinets to modern ATC traffic signal cabinets.