GOAL 5: Wayfinding Signage
GOAL 5: Wayfinding Signage: Upgraded Design and Funding
Key Issues
Design Themes Colors Locations Digital “Wayfinding” 1. Prepare plan and finalize design options Complete 2. Finalize report Complete 3. FPRA DECISION: Presentation, Direction and Funding Complete 4. Mobilize project 3/23 5. Complete installation 8/23
Responsibility: City Manager
October 2022 Update
Contract award will be presented to the FPRA Board in February 2023.