GOAL 9: 17th Street Upgrade (North to Graveyard and South to Okeechobee
GOAL 9: 17th Street Upgrade: Direction and Funding (North to Graveyard and South to Okeechobee)
Key Issues
Streetscape Complete Streets Concepts Sidewalk 1. Complete sidewalk project
Responsibility: City Engineer
12/22
October 2022 Update
• Engineering Department is currently updating streets/curb and gutter/sidewalk inventory list. Emphasis is centered around a 2-mile radius of schools (ongoing). • Preliminary report still under development.