GOAL 12: Fisherman’s Wharf Development

GOAL 12: Fisherman’s Wharf Development: Next Steps

Key Issues

 Site Plan  Land Conveyance  Boat Storage Facility 1. Complete “due-diligence” 2. Review land uses 3. Submit site plan 4. TRC Review Complete Complete 12/22 1/23

5. Planning Board Review

2/23 6. DECISION: 1st Reading 4/23 7. DECISION: 2nd Reading and Approval 5/23 8. DECISION: Land Conveyance 9/23

Responsibility: City Manager

October 2022 Update

The City of Fort Pierce and Fort Pierce Redevelopment Agency entered into an Agreement for the Purchase and Development of Fisherman’s Wharf with Pierce 1 Marina, LLC on August 16, 2021. The first amendment to further extend the deadline for the City to cure the title objections and survey objections was executed on March 21, 2022. The City now anticipates that it will need additional time beyond September 1, 2022 to cure the objections. This second amendment will extend the City's deadline to March 1, 2023.