GOAL 15: Seaplanes: Facility and Service

Key Issues

 Design  Funding  Construction 1. Obtain permits 2. DECISION: Funding and Design 3. Complete construction 4. Ribbon-cutting and 1st Flight

Responsibility: City Engineer

9/22 9/22 TBD TBD

August 2022 Update

Proposal received from Tetra Tech for preliminary design and permitting with FDEP and Army Corp. Proposal to be presented at October 3, 2022 meeting.