Site Plan Land Conveyance Boat Storage Facility 1. Complete “due-diligence” Complete
2. Review land uses 3. Submit site plan 4. TRC Review Complete 9/22 10/22
5. Planning Board Review
11/22 6. DECISION: 1st Reading 1/23 7. DECISION: 2nd Reading and Approval 1/23 8. DECISION: Land Conveyance 6/23
Responsibility: City Manager
August 2022 Update
A Planning Project Discussion Meeting was held on August 17, 2022. Staff discussed the rezoning, future land use and site plan process. A contract amendment will be presented to the FPRA Board and City Commission in September to continue work to address title and survey objections identified by the developer.