GOAL 12: Fisherman’s Wharf Development

GOAL 12: Fisherman’s Wharf Development: Next Steps

Key Issues

 Site Plan  Land Conveyance  Boat Storage Facility 1. Complete “due-diligence” Complete

2. Review land uses 3. Submit site plan 4. TRC Review Complete 9/22 10/22

5. Planning Board Review

11/22 6. DECISION: 1st Reading 1/23 7. DECISION: 2nd Reading and Approval 1/23 8. DECISION: Land Conveyance 6/23

Responsibility: City Manager

August 2022 Update

A Planning Project Discussion Meeting was held on August 17, 2022. Staff discussed the rezoning, future land use and site plan process. A contract amendment will be presented to the FPRA Board and City Commission in September to continue work to address title and survey objections identified by the developer.