CFA Campus Master Plan

Page 1


Land Acquisition

Future Enrollment

Projections

• Enrollment 877 (K-12= 800)

• 5 sections in MS (grade-level teaching)

• 5 sections US (program expansion)

• 3 sections in LS (LE2 – Grade 5)

• # of Students per section 15-18

• Generates positive cashflow

• Requires facilities expansion

• Requires capital raising

Navigating Toward Tomorrow Together: Strategic Plan Overview

APPROVED

By Board of Trustees

Cape Fear Academy

April 1, 2025

CFA Master Plan Committee

Mark Maynard Committee Chair

Koo MacQueen Committee Co-Chair

Shana Barclay

Stephen Beacham

Paul Colvin

Tee Nunnelee

Matt Scharf

Elizabeth Wells

Vin Wells

Ed Ellison Head of School

John Furlough Director of Operations, Safety and Security

Todd Morton Facilities Manager

Sarah Schaeffer Director of Business and Finance

Karen Weir Executive Assistant to Head of School

Design Team

Chris Boney
Laura Miller
Holt Robison David Bellamy
Ginny Magrath
CMTA
Zachary Schneider
Erin Smith
Brice Watson
Davenport
Don Bennett
Sitework Studios
Allan Shad
MBP

Master Plan

Master Plan

Master Plan

Priorities

PRIMARY/LOWER SCHOOL

New 2-story building

Close adjacency to Penton Dining Hall, McNeill Fine Arts Center & Athletics Center

MIDDLE SCHOOL

New 2-story building

Close adjacency to Music/Art/Theater building

UPPER SCHOOL

2-story addition

Partial renovation of existing Cameron Hall

MUSIC/ART/THEATER BUILDING

New building

❑ Loading dock

MCNEILL FINE ARTS CENTER

Renovation to expand & enhance seating

Tech Theater Shop expansion with covered outdoor work area

LIBRARY

New building to serve all divisions

Outdoor seating

WELCOME CENTER

New building

Clear and obvious entrance for visitors

Clear view to entrance for security

CAFETERIA & DINING

Renovation of Beane Wright Student Center/Penton Dining Hall

Outdoor seating

ATHLETICS CENTER

Renovation to include additional health & wellness spaces

FACILITIES & MAINTENANCE

New building

Outdoor storage & vehicle parking

TRAFFIC & SECURITY

Identify access point(s) to/from College Road

Eliminate pedestrian & vehicle conflicts

Separate teen drivers from all others

❑ Clear & obvious wayfinding to Welcome Center

Security

Minimize view of students from College Road

Maximize view of cars entering campus

INFRASTRUCTURE

❑ Geothermal field??

Central plant

Stormwater

SITE AMENITIES

❑ Outdoor classroom(s)

❑ Walking trail

Shaded areas

Outdoor seating

❑ Covered walkways between buildings

FACILITIES & MAINTENANCE

Bus parking

Deliveries

Outdoor storage

ATHLETICS

Track & varsity field with field house & bleachers

Athletic fields – 3+

Relocated and reoriented tennis courts

❑ Baseball field??

PRIMARY & LOWER SCHOOL

Pick-up & drop-off

Playgrounds – protected from view

LE1 & LE2

MIDDLE SCHOOL

Pick-up & drop-off

Outdoor free play area

UPPER SCHOOL

Outdoor activity/dining space

CAFETERIA & DINING

❑ Outdoor seating

❑ Deliveries

How do we get there?

Phasing

• 5 phases

• Phases 1 & 2 must happen sequentially

• Phases 3, 4, 5 are interchangeable depending on priorities

Master Plan Phasing Existing

Varsity Field
Cameron Hall
Godwin Hall

Master Plan Phasing Phase 1

Phase 1A

• Build Cameron Hall expansion to serve as Middle School (LS expand through Godwin Hall)

• Construct JV/practice field

• Construct entrance drive

PHASE 1A

Presentation

PHASE 1A

Varsity Field Cameron Hall

Master Plan Phasing Phase 1

PHASE 1B

Presentation

Phase 1A

• Build Cameron Hall expansion to serve as Middle School (LS expand through Godwin Hall)

• Construct JV/practice field

• Construct entrance drive

Phase 1B

• Renovate Beane Wright Student Center/Penton Dining Hall • Enlarge

Varsity

Master Plan Phasing Phase 1

PHASE 1B

PHASE 1C

PHASE 1A

PHASE 1A

Phase 1A

• Build Cameron Hall expansion to serve as Middle School (LS expand through Godwin Hall)

• Construct JV/practice field

• Construct entrance drive

Phase 1B

• Renovate Beane Wright Student Center/Penton Dining Hall

• Enlarge kitchen & dining

• Enlarge Maintenance & Facilities

• Art & Music move to Science & innovation Center

Phase 1C

• Renovate McNeill Fine Arts Center

• Expand & enhance seating

• Band move to Building G

• Renovate Athletics Center

• Add health & wellness spaces

Master Plan Phasing Phase 1

Lower School

• Additional classroom space in Godwin Hall

• Reestablish LS library

• Portion of Penton Dining to serve as after-school space

Middle School

• Additional space in Cameron expansion

• All students & faculty back together in one building

• Out of Building H/Annex

Upper School

• Math classrooms out of Athletic Center (in Cameron expansion)

• Renovated spaces within Cameron Hall

All students

• Enlarged cafeteria & serving area

• Enhanced McNeill Fine Arts Center

• New health & wellness spaces in Athletic Center

• New JV/practice field away from College Road

CFA Community Presentation April 1, 2025

Varsity

Master Plan Phasing Phase 2

PHASE 2

CFA Community Presentation April 1, 2025

Phase 2

• Construct new LE/Lower School & playgrounds

• Construct Central Energy Plant

• Demolish Godwin Hall & Science & Innovation Center

• Construct temporary gravel parking lot to replace Lot 2

Varsity

Master Plan Phasing Phase 3

Phase 3

• Build Music/Arts/Theater + Library Building

• Build Academic Quad & bell tower

PHASE 3

Varsity

Master Plan Phasing Phase 4

Phase 4

• Demolish Primary Building

• Build Middle School (Upper School move into Cameron Hall expansion)

PHASE 4

Varsity

Master Plan Phasing Phase 5

Phase 5

• Build new driveways and parking

• Relocate tennis courts to Athletics campus

• Build Varsity field, Field House & bleachers

• Build Hurricane Alley

• Build Welcome Center & Alumni Garden

• Build Maintenance Building

• Demo Buildings G & H

Master Plan

How long will this take?

Phase 1 - 2 years 4 months

Cameron Hall expansion & JV/practice field
Beane Wright Student Center /Penton Dining
McNeill FAC & Athletics Center

How long will this take? Phases 2, 3,

Phases 3, 4, 5 – interchangeable sequence