Time to engage – consultation draft released on NZS 3910 construction contract 16 June, 2023
The committee tasked with reviewing NZS 3910:2013 – Conditions of contract for building and civil engineering construction (NZS 3910) has released a consultation draft of a revised version of NZS 3910, entitled DZ 3910:202X (DZ 3910).
more than the TOC, then the Contractor bears a pre-agreed share of the overrun (or “pain”) potentially up to a maximum amount equal to, say, its total Margin (i.e., the Contractor cannot lose more than its Margin on account of an overrun); or
The review, led by Standards New Zealand and commissioned by the Construction Sector Accord and the New Zealand Infrastructure Commission – Te Waihanga, identified that a comprehensive review was needed to update NZS 3910 which (with the exception of an interim update of recommended special conditions published in October 2022) had not been reviewed since 2013.
less than the TOC, then the Contractor is paid a preagreed share of the underrun (or “gain”).
This article examines certain key areas of change to NZS 3910 as set out in DZ 3910, namely:
the addition of a target outturn cost (TOC) contract pricing option;
the replacement of the role of Engineer to the Contract with the roles of Contract Administrator and Independent Certifier;
the dispute resolution regime; and
contractor indemnity and limit of liability.
We also identify some features which we consider would be useful additions to DZ 3910.
TARGET OUTT UR N COST DZ 3910 includes a TOC pricing option, which may be utilised either on a standalone basis or together with other (existing) pricing options. The TOC pricing model under DZ 3910 provides for the reimbursement of the Contractor’s Net Costs, plus Preliminary & General and Margin, subject to a “pain/gain” concept. This concept essentially provides that if the final Contract Price (i.e., the aggregate of all Net Costs plus Preliminary & General and Margin) is: WWW.BELLGULLY.COM
A TOC contract is based on the idea that each party will primarily act in its own self-interest, and so seeks to align those interests by prioritising a “best for project” outcome whereby a positive outcome is jointly positive, and a negative outcome is jointly negative. In this sense, it is not that different from an alliancing agreement, but without the inclusion of the “no fault, no blame” edict that characterises an alliance. We have advised on a number of major projects which utilise a TOC pricing model under NZS 3910 through special conditions. The mechanical drafting included in DZ 3910 generally reflects the equivalent drafting which was adopted on those projects, and (for the most part) does what it needs to do establish a workable TOC pricing regime. That said, the mechanical “pain/gain” provisions are but one key feature of a TOC contract. For a TOC contract to work effectively, a number of additional features, both contractual and non-contractual, are required. We discuss some of these features below.
Consistent with the fundamental premise that the parties are jointly banking on the actual final Contract Price being less than the TOC: o
all Net Costs should be incurred, documented and shared on a fully transparent and open book basis (so that both parties are able to establish what Net Costs are being incurred and counted towards the TOC (and on what basis)), and