FOREMOST ON THE FORESHORE

PAGE 2


AFS LOGICWALL速 building multi-residential apartments smarter, faster, better 6+1

146

4,641m2

HEIGHT

UNITS

LOGICWALL速

Element Apartments

AFS LOGICWALL速 162MM PARTY WALLS

KINGSTON 2


HARBOUR 3


9+5

AFS LOGICWALL®

120MM PARTY WALLS

HEIGHT

AFS LOGICWALL®

120MM BLADE WALLS

AFS LOGICWALL®

200MM BLADE WALLS

91

AFS LOGICWALL®

200MM EXTERNAL WALLS

UNITS

AFS LOGICWALL®

200MM PARTY WALLS

AFS LOGICWALL®

200MM LIFT & STAIR WALLS

AFS LOGICWALL® for speed of construction, materials handling and cost efficiencies.

2,612m2 LOGICWALL®

REID

43 Constitution Avenue

4


5


2

AFS LOGICWALL®

120MM EXTERNAL WALLS

HEIGHT

AFS LOGICWALL®

120MM INTERNAL WALLS

AFS LOGICWALL®

120MM PARTY WALLS

78

AFS LOGICWALL®

150MM LIFT & STAIR WALLS

UNITS

AFS LOGICWALL®

200MM BLADE WALLS

5,074m2 LOGICWALL®

Cnr Jerrabomberra and Hindmarsh Drive

NARRABUNDAH 6


7


4 +1

AFS LOGICWALL®

120MM EXTERNAL WALLS

HEIGHT

AFS LOGICWALL®

150MM EXTERNAL WALLS

AFS LOGICWALL®

150MM CORRIDOR WALLS

32

AFS LOGICWALL®

150MM PARTY WALLS

UNITS

AFS LOGICWALL®

150MM LIFT & STAIR WALLS

AFS LOGICWALL® 1 50MM PARAPET WALLS

4,126m2 LOGICWALL®

6 High Street

QUEANBEYAN 8


AFS ticked many boxes for this project and could be incorporated into various components of the building. It offered a structural solution, formed part of the external façade system, provided the necessary fire separation and was also a cost effective system within very tight site parameters.” NICK PELLE, DIRECTOR, OZTAL ARCHITECTS

9


3+1 HEIGHT

78 UNITS

6,190m2 LOGICWALL®

AFS REDIWALL®

200MM BASEMENT RETAINING WALLS

AFS REDIWALL®

200MM LIFT & STAIR WALLS

AFS LOGICWALL®

120MM EXTERNAL WALLS

AFS LOGICWALL®

120MM INTERNAL WALLS

AFS LOGICWALL®

120MM BLADE COLUMNS

AFS LOGICWALL®

120MM LIFT & STAIR WALLS

AFS LOGICWALL®

200MM BLADE COLUMNS

1,386m2 REDIWALL®

PVC PERMANENT FORMWORK

Zest Apartments

FRANKLIN 10


We used AFS LOGICWALL® for external walls and internal partition walls and the REDIWALL® product for the basements walls on the Zest Apartments Project. The project comprised 2 and 3 storey buildings, totalling 78 units with a total build duration of 9½ months. We can contribute the ease and speed of construction during structure to the use of the AFS and REDIWALL® Systems. AFS always met their delivery dates and were always very helpful, from detailing shop drawings to delivery on site.” DAMIAN RUMBALL, PROJECT COORDINATOR, GEOCON

11


AFS LOGICWALL速 and REDIWALL速 the perfect combination for above and below ground applications.

HARRISON 12

Sapling Street


4+1 HEIGHT

AFS REDIWALL®

200MM BASEMENT RETAINING WALLS

AFS LOGICWALL®

150MM BLADE COLUMNS

AFS LOGICWALL®

LIFT & STAIR WALLS

76 UNITS

2,161m2 LOGICWALL® PVC PERMANENT FORMWORK

1,496m2 REDIWALL®

13


Certified resistant to fire and water Ideal for basements, columns, party walls, retention tanks, foundation and retaining walls, service and stormwater pits, stair and lift walls.

PVC PERMANENT FORMWORK

14


AFS can help you design and build your next project, contact us at: PVC PERMANENT FORMWORK

1300 727 237 or visit: afswall.com.au

3 men + 1 day = 100m

This information is copyright protected and may not be copied, rebroadcast or redistributed in any way, in whole or in part without the written permission of AFS Systems Pty Ltd. This newsletter is copyright© of AFS Systems Pty Ltd ABN 455 760 727 88.

A three-man team can erect one hundred square metres of LOGICWALL® in just one day