THE PHYSICAL PROCESS: A preparatory period of two weeks preceded the glue up, which was done in two phases over two days of Beam A. The prep work required planning material down to lamella thickness, milling and shaping each lamella, fabricating a form-work to lay the beam into, and coordinating space and materials to allow the glue up to unfold seamlessly when it came time to production. Thousands of pounds of material, within the jig, the glue and milled lamellas were at stake if any phase of the glue up were to happen not as planned.