Mispaper1

Page 149

Activity

Most likely Duration (Days) 5 8 6 11 7

A B C D E

3

Immediate predecessors to activity D A, D A,C

C

A

4

1

X

E

D 5

2

B

Fig. 14.8 Critical Path.

Activity A B C D E

Early start (ES) 0 11 11 0 17

Early finish (EF) 5 19 17 11 24

SLACK = LS - ES

or

Late start (LS) 6 16 11 0 17

Late finish (LF) 11 24 17 11 24

SLACK 6 5 0 0 0

LF - EF

Critical activities are those where the slack is zero. In the network D, X, C, E are the critical activities : While A and B are non-critical. The slack is a time resource which a project manager can use for manipulating the resource and start and finish of the activity. Project Completion Time = Sum of activity times on a critical path = D+X+C+E = 6 + 0 + 11 + 7 = 24 days. Probability of completing the project

pdfMachine - is a pdf writer that produces quality PDF files with ease! Get yours now! “Thank you very much! I can use Acrobat Distiller or the Acrobat PDFWriter but I consider your product a lot easier to use and much preferable to Adobe's" A.Sarras - USA


Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.