8. ELECTRICAL

$ 290,000

9. PLUMBING

$ 113,000

10. FIRE PROTECTION

$ 70,000

11. GENERAL CONDITIONS

$ 423,120

12. CONSTRUCTION CONTINGENCY

$ 261,900

Gear, panels, distribution wiring and receptacles Fluorescent T8 interior lighting and lighting controls Telecom and data Fire alarm system including strobes, annunciators and exit signs Security System Backup generator

Infrastructure, toilets, lavatory sinks, kitchen sinks, hot water heaters, utility sinks, restroom accessories exterior hose bibs

Sprinklers and pump

Construction management, insurance & bonds, permits & fees

CONSTRUCTION SUBTOTAL CONSTRUCTION COST/SF

$ 3,304,020 $ 220.27

13. DESIGN FEES

$ 240,960

14. SOFT COSTS

$ 50,000

15. PROJECT SCOPE CONTINGENCY

$ 130,950

Architect, landscape architect, civil engineer, structural engineer, systems engineer

Survey, soil testing, traffic studies, etc

PROJECT FIRST COST TOTAL PROJECT COST/SF

$ 3,725,930 $ 248.40