264
Case Study 5: Power Generation Developments in Uganda
37. http://www.wsj.com/articles/privately-funded-electricity-too-expensive-for-uganda -president-says-1413827013, accessed February 1, 2015. 38. $0.589 for hydro and $0.596 for bagasse projects.
References BNEF (Bloomberg New Energy Finance). 2014. “Climatescope 2014.” http://global -climatescope.org/en/. Last accessed February 1, 2015. Dhalla, G. 2011. Performance of the Ugandan Power Sector to 2017. Report submitted to the Ministry of Energy and Mineral Resources, Kampala. Government of Uganda. 2010. “National Development Plan 2010/11–2014/15.” http:// opm.go.ug/assets/media/resources/30/National%20Development%20Plan%202010: 11%20-%202014:15.pdf. Last accessed February 1, 2015. IRENA (International Renewable Energy Agency). 2012. Renewable Energy Technologies: Cost Analysis Series, Volume 1, Hydropower. Abu Dhabi: IRENA. Kapika, J., and A. Eberhard. 2013. Power-Sector Reform and Regulation in Africa: Lessons from Kenya, Tanzania, Uganda, Zambia, Namibia and Ghana. Cape Town: Human Sciences Research Council Press. MEMD (Ministry of Energy and Mineral Development). 2011. “Power Sector Investment Plan.” Prepared by Parsons Brinckerhoff, MEMD, Kampala. SE4ALL. 2012. “Uganda Country Profile.” Kampala. http://www.se4all.org/wp-content /uploads/2014/01/Uganda-Country-Profile.pdf. USAID (U.S. Agency for International Development). 2013. Africa Infrastructure Program, Uganda Power Sector Assessment Report. Washington, DC: USAID. World Bank. 2014. Implementation Completion and Results Report 92996-UG. Component E Under Privatisation and Utility Sector Reform Project, Support to Umeme Ltd. Washington, DC: World Bank.
Independent Power Projects in Sub-Saharan Africa • http://dx.doi.org/10.1596/978-1-4648-0800-5