Filling and Venting the Loops

There are integral fill/vent valves together with hose connections as part of the manifold assembly. Hose unions are required for the 3/4” thread on the Vario B manifold.

With Compact Control Pack V5 fitted to Vario B manifold the fill/vent valves would have been relocated to positions above and below the UFH pump.

Before starting, ensure that the fill port is uppermost, then:

• •

Ensure all electrical supplies are switched off. Remove the fill port caps and washer and connect hose unions to both end caps.

The integral valves in both end caps must be opened to fill the system. Use the square key in the cap to open the fill port valves.

Ensure both isolating ball valves on the main flow and return pipes to the manifold are CLOSED. Alternatively, if a Compact Control Pack V5 is fitted close both control and lockshield valves. To close the control valve, firstly remove the thermostatic head and use one of the blue caps from a manifold loop to close the valve.

• • •

If using the V5 Compact Control Pack, fully close the valve on the elbow at the circulating pump inlet to ensure that water is forced around the UFH loops when filling and not short circuiting between the upper and lower manifold headers. Close all underfloor heating loop flow and return valves on the manifold. Fit a hose to the lower manifold hose union and run the other end of the hose to a suitable drain point. Connect a hose to the upper manifold hose union and connect the other end of the hose to a mains water tap.

82 l Uponor UFH Technical Guide

• • • •

Individual loops need to be purged of air in turn. This is achieved by opening the manual head (blue cap) on the lower manifold, then fully opening the corresponding topmeter on the upper manifold. To fully open the topmeter, remove the red locking ring and turn the topmeter 3 full turns from the closed position. Turn on the water tap. As the first loop fills with water, air will discharge through the hose to the drain. Once the air stops and there is a steady flow of water, close both ports on the manifold. Repeat this procedure for all UFH loops on the manifold ensuring that the valves are closed on each loop after filling. Close the valves on the end caps and switch-off the mains water before disconnecting the hoses. Important: If using a V5 Compact Control Pack, please remember to open the pimp isolation valve. If the UFH is being installed in the winter, anti-freeze can be added to the system water for protection against freezing. If used, then the pipes will need to be fully flushed with cold water prior to running the system. The system is now ready for pressure testing.


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.
Underfloor heating install guide by Uponor UK - Issuu