TenneT Spacial Planning

Page 1

Spatial Planning with Set Stakeholder Groups – TenneT  2010: Grid acceleration agreement in SchleswigHolstein, initiated by government

Denmark

Concept for 380 kV grid extension Existing 380kV lines New 380kV lines (rough routeing) New 380kV lines using 220kV route corridor (rough routeing) 380/110 kV transformer Designated wind priority sites

 Involved actors: government, TSOs, DSOs, industry  Regular meetings with local politicians  Joint strategy for early involvement of public (series of events, email address for comments)

Beyond Public Opposition Lessons Learned across Europe

DC (1,100 MVA) – sites variable

Nort h Sea

Baltic Sea

Status of planning procedure: September 2011

©TenneT