Contamination environmental control plan

Page 10

CONTAMINATION ENVIRONMENTAL CONTROL PLAN ABERCROMBIE PRECINCT REDEVELOPMENT PROJECT

28.

Unexpected Discovery In the event of an unexpected discovery of contamination, cease works in the area and contact PM / PER. Refer to “Unexpected Asbestos Find Procedure” – JH-B834-PSP-001.

Staff Responsible

When

All staff

On Find

All staff

On Find

29.

Fence off area and no further works to occur in the area until otherwise advised.

30.

Undertake further testing or engage suitably qualified person to determine the nature of the contamination.

PM / PER

On Find

31.

JH to inform UoS

PM / PER

On Find

32.

Determine appropriate course of action with relevant stakeholders.

PM / PER

On Find

Seepage Water Where surface water run off or perched groundwater is encountered in areas of impacted soil, a strategy will be established to ensure that off-site or vertical migration of contaminated waters does not occur. Should contaminated excavation areas require dewatering, water samples will be collected by experienced personnel and analysed for TPH, lead and PAH’s prior to pump-out and off-site disposal. Waste liquid disposal dockets will be provided in the validation report. In accordance with the Soil & Water Environmental Control Plan (JH-B834-PLN-EMP-SWECP-012), a dewatering checklist will be completed by RG and signed by the PER and Forman prior to the commencement of dewatering. Refer to “Dewatering Checklist” – JH-B834-ENV-CHK-001.

Staff Responsible

When

JH / ES

As required

ES through WSP/DLA/ECS

Prior to dewatering

ES / PER / FM

Prior to dewatering

Importing of Recycled Fill Materials

Staff Responsible

When

All staff

At all times

Staff Responsible

When

33. 34.

35.

36.

No recycled fill materials to be used on-site.

5.2 Monitoring No

Monitoring Required

1.

Daily informal observations to be recorded in site diaries.

FM

As required

2.

Any buffer / ‘no go’ zones, shall be regularly inspected and maintained as required.

PER

Weekly (if required)

3.

Air Monitoring during material screening and excavation.

ES through Airsafe/DLA

As required

Staff Responsible

When

PER

All times

5.3 Reporting No Reporting Required Details of field observations shall be reported via the SQE Inspection Checklist – JH-B834-SQE-CHK-001 and communicated 1. to all staff during pre-starts, toolbox and team meetings. 2.

Any sampling results to be recorded in the Lotus Notes Project Pack.

PER

All times

3.

Newly identified potentially contaminated sites will be documented and UoS notified.

PER

All times

JH-B834-PLN-EMP-CECP-012 Rev (2) Page 9 of 12 Disclaimer: This report has been provided by John Holland Pty Ltd (John Holland) for information purposes only and is strictly confidential. John Holland or anyone on its behalf does not warrant, guarantee or assume any responsibility or duty of care in respect of the information in this report, or represents that the information in this report is accurate, adequate, suitable or complete for any purpose. A recipient of this report must not copy, produce or disclose any information in this report without the prior written permission of John Holland. To the extent permitted by law, John Holland or anyone on its behalf, accepts no liability for any claim, loss, damage, expense or costs incurred by any person as a result of or in connection with any information in this report.