Michael Cooper explores the difficulties of interpreting the Party Wall Act

Back to the wall

P

ractising party wall surveyors like to think of the Party Wall etc. Act 1996 as enabling legislation. It allows one owner to carry out certain works while at the same time offering the adjoining owner certain protections from the impact that these works might have on them. The Act has existed in its present form since 1997 but does not differ much from its predecessor, which applied only to certain parts of London. Although initially there were a number of well reported cases seeking to clarify the interpretation, the main ambiguities were largely ironed out by surveyors taking a pragmatic approach. However, the world changes and now surveyors and owners alike are once again challenging the meaning of various sections of the Act. As a result of this scrutiny, the county courts have lately been providing some interesting decisions. However, until legal precedent is set by a higher court, they can provide contradictory conclusions. So what is the poor surveyor to do? Taking two controversial issues and considering the virtues of each side’s arguments with associate Paul Gill, the results were interesting.

Building on a boundary The first discussion related to the interpretation of sections 1 and 8. In one recent instruction, our clients, who owned a yard that abuts the neighbour’s property, had received notice under section 1 from a neighbour wishing to build up to the boundary on their own side. To do so they also wished to have access and served notice under section 8. Interestingly, there is not a party wall in sight or any intent to build one. You might imagine that this is a simple party wall matter but it is not; the Act (in particular section 1) does not apply where the boundary is already built on. With the presence of a building already on the boundary it seemed clear to us that the Act did not apply and as a result neither did any access that flowed from the notice. The other surveyor disputed this and we agreed to be bound by a third surveyor’s decision who subsequently concurred with me. The neighbour failed to get access and could not build. Sometime later, and literally overnight, the neighbour took down their building and re-issued the same notices saying 6   OCTOBER/NOVEMBER 2015

1 that the boundary was no longer built on. The matter was again referred to the third surveyor who concluded that the circumstances had changed and section 1 now applied because there was no longer a building on the boundary. Thus, he also awarded access to construct under section 8. In hindsight, the surveyors could have foreseen the actions of the developing owner and realised that in the end he was going to get his own way; so why not agree to the first notice avoiding two third surveyor rulings and a heap of fees? Well, the simple answer is we have to apply the rules and if we had accepted the first notice any award made would have been wrong and could have been thrown out if it came under future scrutiny. My feeling is that something is wrong here; surely those who drafted the Act intended that someone constructing, for their own benefit, a building that sits exclusively on their side should not have the benefit of access over another’s land? There are court rulings but they manage to conflict with each other. Sleep v Wise (2006), decided access over an adjacent property was not permissible for building up to a line of boundary. Kaye v Lawrence (2010) concluded common law rights are superseded by the provisions of the Act implying that access is permissible if notice has been served. The virtues of both cases, including the non-binding nature of county court cases, were reviewed with my owner who also took legal advice. He was told that there would be a 50/50 chance of a successful appeal to the second third surveyor decision. My owner was at first keen to have the matter considered at court, but when I told him it was likely to cost £50,000 in legal fees he decided he did not want to fund a trial case. Recently, a panel drafting the latest party wall guidance notes, of which I was part, voted on this and the majority were of the view that access was permitted for works covered under section 1; probably because the judge in Kaye v Lawrence was a high court judge sitting on a lower court. As my associate says: “It does make a bit of sense, the Act is after all an enabling Act”, and while I have to agree, did it simply enable someone to take advantage? If the Act had not applied, the developer would have needed permission for access and may have had to pay consideration or perhaps Images © CBRE


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.
Building Surveying Journal October-November 2015 by RICS - Issuu