train staffing; requests to alter the transport service characteristics, if incompatible with the allocated train paths; requests for preparing and operating trains at very short notice; the request to alter the schedule of services at the facility.

Liaison with the IM’s coordination staff can also be assured by means of total delegation to other RUs. The IM shall ensure that transport services are operated in conditions of safety and in respect of the timetables agreed to with the RU. The IM shall monitor train progress and any exceptional service conditions that may arise and make its findings available to the RUs. 2.4.2 Management rules The purpose of regulating train services is to minimise the effects of any interferences and deviations on the trains, with the ultimate aim of minimising overall delays. Consistently with the Manager’s mission, and in accordance with the primary objective specified above, in the event of any interferences on train services, or the deviation of one or more trains from its allocated path, the following management principles are provided to resolve the interferences and prevent the delays from propagating across the entire network. Commuter time slot 6.00-9.00 and 17.00-20.00 (Monday to Friday) Management principles 1 2 3

Type of service National Premium OA trains – National Basic OA trains – International OA trains – Long distance and commuter trains serving the larger cities Long distance PSO trains – Regional PSO trains Technical services*

Daytime slots 9.00-17.00 and 20.00-22.00 (Monday to Friday) and 6.00-22.00 (Saturday, Sunday, Holidays) Management principles 1 2 3 4

Type of service National Premium OA trains – National Basic OA trains – International OA trains Long distance PSO trains Regional PSO trains Technical services*

Night slots 22.00-6.00 Management principles 1 2 3 4

Type of service National Premium OA trains – National Basic OA trains – International OA trains Long distance PSO trains Regional PSO trains Technical services*

* Scheduled service trains, functional to commercial services (with a turnback time of less than 30’), have the same importance as the corresponding trains. Legend: OA=Open Access; PSO=Public Service Obligations. The management principles set out herein define the guidelines for managing train services in ordinary and slightly disrupted conditions (without any severe disruptions). In the case of a severe disruption,

42


Turn static files into dynamic content formats.

Create a flipbook

Articles inside

2.4.5 INQUIRIES CONCERNING OPERATING ACCIDENTS / DISRUPTIONS

3min
page 48

utilisation of back-up locomotives/vehicles

9min
pages 45-47

2.4.3 DISRUPTED TRAFFIC MANAGEMENT

2min
page 43

2.3.2.1.1 Any further formalities for contract conclusion purposes (updated in December 2021

3min
page 30

2.3.2.3 Insurance covers (updated in December 2021

2min
page 32

2.3.3.2 IM’s Obligations

3min
page 35

declaration for sections with at least three consecutive saturated time slots and how to calculate penalties. (December 2020) Par. 4.3.1. Update of the terms of the allocation process (December 2021) Par. 4.3.2. Inclusion of the specification of the possibility for the IM to re-plan an assigned railway path if re-planning becomes necessary in order to reconcile as effectively as possible all path requests and if it is approved by the applicant to which the path had been assigned (requirement 4.3.1, TRA Resolution 158/2021) Par. 4.3.3. Change of time table for interim adjustment (December 2020) Par. 4.3.3. Change of time table for interim adjustment (December 2021) Par. 4.3.4. New delivery times for commercial scheduling measures (December 2021) Par. 4.4.1.1 elimination, pursuant to requirement 4.3.2. of TRA Resolution 158/2021 Par. 4.4.1.2 Adaptation of the coordination procedure to the provisions of art. 10, par. 5, of Regulation 2016/545/EU (December 2020) Par. 5.2. Adaptation of the description of the Public Information (IaP) included in the MAP to the new RFI CoP 365/RFI procedure of 01/04/2021 (December 2021) Par. 5.5.2 proposal for streamlining the process of requesting and providing customised public information (December 2020) Introduction of the description of the complementary HUB information system (December 2020) Adaptation of the description of the complementary information to the new RFI CoP 365/RFI procedure of 01/04/2021 (December 2021) Par. 6.2. reference to the methodological document sent by the IM to the TRA with a note dated 17 November 2020 (Article prot. 18147/2020). (December 2020) Par. 6.3.1. new MAP tariffs after sending the tariff proposal to TRA Par. 6.3.3.2 reference to a possible introduction of an extra MAP tariff for the PRM assistance service (December 2020) Par. 6.3.4.1. New specifications regarding customised public information. (December 2020) Introduction of the complementary HUB information system (December 2020) Par. 6.4 Alignment of the Performance Regime regulation with the provisions of the annexes to TRA Resolutions no. 70/2014 point 7.6.1 no. 76/2014 point 6.2 (December 2020) Appendices to Chapter 6 - Part B introduced a time line for the presentation of any corrections by the RUs to the paths/services reported in order to further regulate the process (updated December 2021) Appendices to Chapter 6 - Part C Alignment of the Performance Regime regulation with the provisions of the relevant regulatory changes

4min
page 4

2.4.2 MANAGEMENT RULES

1min
page 42

1.7 PUBLISHING

1min
page 22

GLOSSARY (UPDATED IN DECEMBER 2021

14min
pages 10-16

2.3.3.3 RU’s obligations

2min
page 36