Mass Transit Project Development During the Period between 2005 and 2012 The time frame for implementation of the mass transit projects during 2005 – 2012 under the resolution passed by the Council of Ministers on 14 June 2005 for the government mega projects shall be as follows:

Mass Transit Projects

Distance (Kilometres)

Period

Target Year for Service

1. Purple Line

43.00

1.1 Bang Yai - Bang Sue

23.00

2005 - 2009

2009

1.2 Bang Sue - Rat Burana

20.00

2005 - 2012

2012

2. Blue Line (Extension)

27.00

2.1 Hua Lamphong - Bang Khae

14.00

2005 - 2012

2012

2.2 Bang Sue - Tha Phra

13.00

2005 - 2010

2010

3. Orange Line

24.00

2005 - 2012

2012

4. Red Line

66.80

4.1 Rangsit - Bang Sue

24.60

2005 - 2008

2008

4.2 Bang Sue - Hua Lamphong

6.20

2005 - 2009

2009

4.3 Hua Lamphong - Maha Chai

36.00

2005 - 2009

2009

5. Light Red Line

71.41

5.1 Airport Link

28.00

2005 - 2007

2007

5.2 Extension of Airport Link

21.10

2005 - 2011

2011

5.3 Bang Sue - Taling Chan

14.71

2005 - 2008

2008

5.4 Bang Sue - Makkasan

7.60

2005 - 2009

2009

6. Dark Green Line

26.50

2005 - 2010

2010

7. Light Green Line

18.70

2005 - 2010

2010

Total

277.41

Notes: 1. 2.

The above information may be subject to change. As at 17 December 2005, the Ministry of Transport announced its policy and plan to expand the M.R.T. Project to 10 lines, with the yellow line, pink line and brown line as the expected additional 3 lines, but the details of the said projects are currently pending the drafting of terms of reference (TOR), and further feasibility study in the future.